PM - Project Management Processes
Project management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements. This application of knowledge requires the effective management of appropriate processes.
Start
Congratulations - you have completed PM - Project Management Processes.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
A project manager plans communications. What previous task he worked on?
A | Determine quality standards, processes, and metrics. |
B | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
C | Prepare procurement documents. |
D | Determine all roles and responsibilities. |
Question 1 Explanation:
Plan communications is following after determine all roles and responsibilities.
[2 - Rita's Process Chart]
Question 2 |
What should be used in project initiating?
A | Requirements for project team. |
B | Project plan. |
C | Business case, product description, or known products requirements, product scope. |
D | Stakeholders management strategy. |
Question 2 Explanation:
What is the project being asked to do? Business case, product description, or known products requirements, product scope.
[2 - Rita's Project Chart]
Question 3 |
What input should be used in project initiation processes?
A | Communication plan, stakeholder management plan. |
B | Historical information, company change control system, industry standards. |
C | List of risks, risk management plan, risk audit. |
D | Industry standards, list of vendors. |
Question 3 Explanation:
Historical information, company change control system, industry standards - all are part of Project Initiation Group.
[2 - Rita's Project Chart]
Question 4 |
What is the task following develop schedule?
A | Estimate time and cost. |
B | Determine critical path. |
C | Determine team. |
D | Develop budget. |
Question 4 Explanation:
The right sequence is: estimate time and cost > determine critical path > develop schedule > develop budget.
[2 - Rita's Process Chart]
Question 5 |
What processes belong to the project initiating group?
A | Divide large projects into phases, understand business case, determine initial requirements and risks. |
B | Determine critical path. |
C | Perform risk identification, quantitative and qualitative risk analysis, and risk response planning. |
D | Estimate time and costs. |
Question 5 Explanation:
Divide large projects into phases, understand business case, determine initial requirements and risks are the part of the initiating process group.
[2 - Rita's Project Chart]
Question 6 |
Which project process group represents the project performance measurement?
A | Planning. |
B | Closing. |
C | Executing. |
D | Monitoring and controlling. |
Question 6 Explanation:
Monitoring and controlling.
Question 7 |
What project processes group helps to determine variances and may initiate change requests.
A | Closing. |
B | Monitoring and controlling. |
C | Planning. |
D | Executing. |
Question 7 Explanation:
Monitoring and controlling process group is looking after initiation of change requests.
Question 8 |
Project manager holds meetings mostly with developers, quality assurance team and customers. What is the current stage of the project?
A | Closing. |
B | Planning. |
C | Initiation. |
D | Execution. |
Question 8 Explanation:
The current stage of the project is execution.
Question 9 |
What project manger does when generates change requests?
A | Executes project. |
B | Performs monitoring and controlling. |
C | Creates project plan. |
D | Uncovers requirements during project initiation. |
Question 9 Explanation:
Change request usually generate during project execution. It means the planning phase has been completed, the requirements and project plan have been already signed off.
Question 10 |
Which of the following activities to be done in project closing?
A | Give recognitions and rewards. |
B | Release resources. |
C | Hold final meeting with the team. |
D | Verify with stakeholders if all the project requirements have been addressed. |
Question 10 Explanation:
Project resources have to be released at the end of the project.
Question 11 |
What that means performing the work according to the project management plan?
A | Initiating the project or phase. |
B | Closing the project phase or project. |
C | Perform monitoring and controlling. |
D | Executing the project. |
Question 11 Explanation:
This activity belongs to executing process group; the answer is executing the project.
Question 12 |
Rewarding motivates project members and increases their performance. During which part of the project motivation is most effective?
A | Motivation of the team is most effective during project closing, so people will stay to the end of the project. |
B | Motivation of the team is most effective during project execution. |
C | Motivation of the team is most effective during project initiation; so the team would feel appreciation during the rest of the project. |
D | Motivation of the team is most effective during project planning. |
Question 12 Explanation:
Motivation of the team is most effective during project execution.
Question 13 |
What type of activities the quality control is?
A | Executing. |
B | Monitoring and controlling. |
C | Quality control is executed to ensure the product or service quality and its metrics determined by the project manager. |
D | Quality control performed during project planning and closing. |
Question 13 Explanation:
Quality control belongs to monitoring and controlling process group.
Question 14 |
Project manager reports the project performance on monthly basis. What type of process project manager performs?
A | Eecuting. |
B | Monitoring and controlling. |
C | Closing. |
D | Planning. |
Question 14 Explanation:
Project performance reporting is a part of the monitoring and controlling process group.
Question 15 |
What task should be done right before estimate time and cost, and determine critical path?
A | Develop schedule. |
B | Estimate resource requirements |
C | Create activity list. |
D | Determine team. |
Question 15 Explanation:
Estimate resource requirements should be done right before the estimate time and cost > determine critical path.
[2 - Rita's Process Chart]
Question 16 |
Project manager estimates the required type and quantity of materials, people, equipment, or supplies to perform each activity. What process project manager works on?
A | Create procurement plan. |
B | Determine what to purchase. |
C | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
D | Estimate Activity Resources. |
Question 16 Explanation:
Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. In other words - estimate resource requirements.
[1 - 3.4.7 Estimate Activity Resources]
Question 17 |
What of the following processes used during project initiation?
A | Create measurable objectives, develop project charter, identify stakeholders, develop stakeholders management strategy, determine how you will do planning. |
B | Develop project charter, determine quality standards, processes and metrics, determine team. |
C | Select project manager, determine quality standards, processes and metrics, create project scope statement. |
D | Create measurable objectives, develop project charter, identify stakeholders, develop stakeholders management strategy. |
Question 17 Explanation:
Create measurable objectives, develop project charter, identify stakeholders, develop stakeholders management strategy - all the part of the project initiation group.
[2 - Rita's Project Chart]
Question 18 |
What needs to be done before create network diagram?
A | Determine critical path. |
B | Finalize requirements. |
C | Create activity list. |
D | Estimate time and cost. |
Question 18 Explanation:
The right sequence is: create activity list > create network diagram > estimate resource requirements > estimate time and cost > determine critical path.
[2 - Rita's Process Chart]
Question 19 |
Integrated change control is the part of monitoring and controlling process group. What other processes associated with this activity?
A | Request change, get approval for work, acquire a team to complete change. |
B | Influence factors that cause changes, Change request approval, informing stakeholders about changes. |
C | Acquire approval of change and authorization to perform work. |
D | Implement change, perform quality assurance after change is completed, informing stakeholders about changes. |
Question 19 Explanation:
Influence factors that cause changes, change request approval, informing stakeholders about changes are processes associated with change in the monitoring and control process group. Other answers are mixed or related to project executing process group.
Question 20 |
Estimate time and cost, determine critical path, develop schedule. What should be done next?
A | Develop budget. |
B | Determine quality standards, processes, and metrics. |
C | Create activity list. |
D | Determine quality standards, processes, and metrics. |
Question 20 Explanation:
Develop budget would be the next step in Planning Process Group.
[2 - Rita's Process Chart]
Question 21 |
What should be done after develop final project management plan and performance measurement baseline?
A | Gain formal approval of the plan. |
B | Determine what to purchase. |
C | Execute the work according to PM plan. |
D | Hold kickoff meeting. |
Question 21 Explanation:
Formal approval of the plan should be received before providing a kickoff meeting.
Question 22 |
Project manager proceeds with procurement closure. What should be done first?
A | Confirm if the work was completed in accordance to the requirements. |
B | Inform stakeholders that project is completed. |
C | Release resources in order to reduce project cost. |
D | The formal acceptance of the project or phase is received. |
Question 22 Explanation:
Before the procurements will be closed, project manager needs to confirm the work was completed in accordance to the requirements.
Question 23 |
A project manager has determined quality standards, processes, and metrics what would be the next task to do?
A | Perform quality assurance. |
B | Develop budget. |
C | Estimate time and cost. |
D | Create process improvement plan. |
Question 23 Explanation:
The right sequence is: create activity list > develop schedule > develop budget > determine quality standards processes, and metrics. The process of perform quality assurance belongs to executing process group, not to planning.
[2 - Rita's Process Chart]
Question 24 |
Which of the following activities belong to project closing process group?
A | Execute project audit. |
B | Verify the project results against project charter. |
C | Complete final report of the project performance. |
D | Reward the project team. |
Question 24 Explanation:
Complete final report of the project performance.
Question 25 |
How often project manager should evaluate the team and project performance?
A | Evaluation of the team and project performance should be performed during project execution to ensure the project success. |
B | Evaluation of the team and project performance needs to be done throughout the course of the project from initiation to closing. |
C | Evaluation of the team and project performance needs to be done at least once per month throughout the project from initiation to closing. |
D | Evaluation of the team and project performance needs to be done on weekly basis. |
Question 25 Explanation:
Evaluation of the team and project performance should be performed during project execution to ensure the project success. The frequency of evaluation depends on the duration, size and complexity of the project.
Question 26 |
When the final team to be acquired?
A | Final team to be acquired after all roles and responsibilities have been determined. |
B | Final team to be acquired after the project scope, project schedule, and all roles and responsibilities have been determined. |
C | During project execution. |
D | Final team to be acquired after the project schedule, and all roles and responsibilities have been determined. |
Question 26 Explanation:
Final team to be acquired during project execution.
Question 27 |
A project manager determined the longest chain in executing of project packages, while was not able avoid two significant floats. What next should be done?
A | Revise requirements. |
B | Create activity diagram. |
C | Determine team. |
D | Develop schedule. |
Question 27 Explanation:
The right sequence is: create activity list > create network diagram > estimate resource requirements > estimate time and cost > determine critical path > develop schedule.
[2 - Rita's Process Chart]
Question 28 |
In order for a project to be successful, the project team must:
A | Provide risk audit and facilitate conflict resolution. |
B | Develop closure procedures. |
C | Document assumptions and constrains. |
D | Use a defined approach that can be adopted to meet requirements. |
Question 28 Explanation:
In order for a project to be successful, the project team must use a defined approach that can be adopted to meet requirements.
Question 29 |
What reference to be used in project performance evaluation?
A | Approved requirements, project and products scope statements are the references to evaluate project performance. |
B | Comparing the current status with project schedule and planned budget. |
C | Measure performance against the performance measurement baseline. |
D | Project quality, standards, processes and metrics to be used as the evaluation references. |
Question 29 Explanation:
Project performance measures against the performance measurement baseline.
Question 30 |
What process in planning group is iterative?
A | Project management processes are iterative, and many processes are repeated during the project. |
B | Finalize requirements. |
C | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
D | Estimate time and cost. |
Question 30 Explanation:
Project management processes are iterative, and many processes are repeated during the project.
[1 - 3.1 Common project management process interactions]
Question 31 |
What follows after create process improvement plan?
A | Develop schedule. |
B | Develop budget. |
C | Determine team. |
D | Determine all roles and responsibilities. |
Question 31 Explanation:
Determine all roles and responsibilities should be done after process improvement plan.
Question 32 |
The project requirements have been finalized and project manager received sign off for project scope statement. What would be the best to do next?
A | Plan communications. |
B | Determine team. |
C | Create measurable objectives. |
D | Determine what to purchase. |
Question 32 Explanation:
Determine what to purchase.
Question 33 |
During which phase of the project the process of managing people is most intensive?
A | During project initiation, because of so many communication required to coordinate all initial requirement between all stakeholders. |
B | It is essential that project planning required the most intensive use of resources. There are many processes to be coordinated and so much information to be collected from different parties to ensure that requirements are finalized. |
C | During project closing - end users, sponsors and other stakeholders require the most communications and coordination. |
D | The process of managing people is most intensive during project execution. |
Question 33 Explanation:
The process of managing people is most intensive during project execution.
Question 34 |
What reference can be used in project performance measurement?
A | Approved requirements, project and products scope statements. |
B | Stakeholder and customer satisfaction. |
C | The metrics determined by customer. |
D | The metrics determined by project manager. |
Question 34 Explanation:
Project manager may determined the metrics for project performance measurement.
Question 35 |
Administering procurements is the part of which process group?
A | Planning. |
B | Executing. |
C | Monitoring and controlling. |
D | Closing. |
Question 35 Explanation:
Administering procurements is the part of monitoring and controlling process group.
Question 36 |
Project manager forecasts the project performance. In which process group this activity is?
A | Closing. |
B | Monitoring and controlling. |
C | Executing. |
D | Planning. |
Question 36 Explanation:
Project manager forecasting is a part of the monitoring and controlling process group.
Question 37 |
What type of processes should be performed to ensure the right version of changes to be implemented?
A | Executing. |
B | Monitoring and controlling. |
C | Creating activity list to ensure the right sequence of work. |
D | Planning. |
Question 37 Explanation:
Version control is the part of configuration management and relates to monitoring and controlling process group.
Question 38 |
What would you use during the project initiation?
A | Project requirements. |
B | Contracts, list of stakeholders, industry standards, information about company strategic plan. |
C | WBS and WBS dictionary. |
D | Communication plan, procurement plan, |
Question 38 Explanation:
Contracts, list of stakeholders, industry standards, information about company strategic plan refer to the input to the initiating process group.
[2 - Rita's Project Chart]
Question 39 |
The project requirements have been finalized and project manager received sign off for project scope statement. What would be the best to do next?
A | Plan communications. |
B | Determine team. |
C | Determine what to purchase. |
D | Create measurable objectives. |
Question 39 Explanation:
Determine what to purchase.
Question 40 |
What project manager know before develop schedule?
A | Determine team. |
B | Project budget. |
C | Estimate time and cost. |
D | Critical path. |
Question 40 Explanation:
The right sequence is: create activity list > create network diagram > estimate resource requirements > estimate time and cost > determine critical path > develop schedule.
[2 - Rita's Process Chart]
Question 41 |
Which of the following activities belong to project closing process group?
A | Facilitate conflict resolution. |
B | Inform stakeholders about project completion. |
C | Hold a final meeting with project team. |
D | Index and archive the project records. |
Question 41 Explanation:
Index and archive the project records.
Question 42 |
Which of the following activities execute in project closing phase?
A | Give recognitions and rewards. |
B | Hold final meeting with the team. |
C | Confirm the project scope statement against the project charter. |
D | Update lessons learned. |
Question 42 Explanation:
Update lessons learned is one of the tasks in closing process group.
Question 43 |
What input should be used for project initiating?
A | Project plan and product requirements. |
B | List of work packages. |
C | Project schedule. |
D | Information about company culture, major activities of the company related to the project, list of people who may be good team members. |
Question 43 Explanation:
Information about company culture, major activities of the company related to the project, list of people who may be good team members is a list of inputs for the project initiating group.
Question 44 |
During project initiation project manager collected such project assets as processes, procedures. During the project execution, to expedite vendor selection, project manager whats to ease the process, but there is not enough time left to coordinate it with management. What project manager needs to do?
A | Coordinate the new idea with potential vendors. |
B | Follow the old process. |
C | Coordinate new idea with legal department. |
D | Discuss the new idea with technical leads and use it if they agree. |
Question 44 Explanation:
Use the old process until the new idea is well coordinated with subject mater specialists, legal department if needed and management.
Question 45 |
Project manager have difficulty to create a network diagram based on WBS and WBS dictionary. What activity is missing in this work?
A | Estimate time and cost. |
B | Finalize requirements. |
C | Determine a list of work packages. |
D | Create activity list. |
Question 45 Explanation:
Create WBS and WBS dictionary > Create activity list > Create network diagram
Question 46 |
A project manager has estimated resources requirements and documented all roles and responsibilities. What is the next task?
A | Determine what to purchase. |
B | Prepare procurement documents. |
C | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
D | Plan communications. |
Question 46 Explanation:
Plan communications is the next step.
[2 - Rita's Process Chart]
Question 47 |
A project manager has determined quality standards, processes, and metrics. What would be the nest task?
A | Create process improvement plan. |
B | Create network diagram. |
C | Create activity list. |
D | Determine all oles and responsibilities. |
Question 47 Explanation:
The right sequence is: develop schedule > develop budget > determine quality standards, processes, and metrics > create process improvement plan.
[2 - Rita's Process Chart]
Question 48 |
It is required that project team must..
A | Divide project into more manageable components. |
B | Determine variances and of the warrant corrective action o a change. |
C | Comply with requirements to meet stakeholder needs and expectations. |
D | Implement approved changes, defect repair, preventive and corrective actions. |
Question 48 Explanation:
In order for a project to be successful, the project team must comply with requirements to meet stakeholder needs and expectations.
Question 49 |
The project requirements have been finalized. What project manager should do before determining the team?
A | Develop schedule. |
B | Create project scope statement and determine what to purchase. |
C | Create activity list and network diagram. |
D | Estimate resource requirements. |
Question 49 Explanation:
The sequence is the following:
create project scope statement then determine what to purchase, and then determine the team.
[2 - Rita's Process Chart]
Question 50 |
Project manager records issues into issues log. What is the current stage of the project?
A | Execution. |
B | Closing. |
C | Planning. |
D | Initiating. |
Question 50 Explanation:
The project is in executing stage, when the most issues are logged.
Question 51 |
Project team revises planning artifacts; determined a new critical path and planned scheduled. What would be the next task?
A | Determine role and responsibilities. |
B | Identify risks and develop risk response plan. |
C | Create project improvement plan. |
D | Plan communications. |
Question 51 Explanation:
Create project improvement plan is the right answer. This would be the next closest task available in the offered list.
Question 52 |
Perform risk identification, qualitative and quantitative risk analysis, and risk response planning is one of the most important tasks. To which process group this task belongs?
A | Executing. |
B | Monitoring and Controlling. |
C | Initiating. |
D | Planning. |
Question 52 Explanation:
Planning.
[2 - Rita's Process Chart]
Question 53 |
Ensuring project success and meeting project objectives, the team must..
A | Select appropriate processes required to meet the project objectives. |
B | Create WBS dictionary. |
C | Schedule and hold progress meetings. |
D | Coordinate project schedule with customer. |
Question 53 Explanation:
In order for a project to be successful, the project team must select appropriate processes required to meet project objectives.
Question 54 |
Estimate resource requirements, estimate time and cost, determine critical path. What task misses in this sequence?
A | Determine quality standards, processes, and metrics. |
B | Create activity list. |
C | Estimate time and cost. |
D | Create process improvement plan. |
Question 54 Explanation:
Estimate time and cost is missing. The right sequence: estimate resource requirements > estimate time and cost > determine critical path, develop budget.
[2 - Rita's Process Chart]
Question 55 |
It is required that project manager perform project audit. When this should be done?
A | Project audit should be performed during project execution. |
B | It would be right to perform project audit in each phase throughout the project from initiation to closing. |
C | Project audit is one of the project closing processes. |
D | Project audit is the part of project monitoring and controlling. |
Question 55 Explanation:
Project audit is the part of project execution.
Question 56 |
What is the last task of in the planning process group?
A | Perform iterations for risk identification. |
B | Hold kickoff meeting. |
C | Gain formal approval of the plan. |
D | Complete procurement documentation. |
Question 56 Explanation:
Hold kickoff meeting.
Question 57 |
What type of activities the quality assurance is?
A | Quality assurance is executed during measurement of performance against other metrics determined by the project manager. |
B | Executing. |
C | Quality assurance performs during project planning and closing. |
D | Monitoring and controlling. |
Question 57 Explanation:
Quality assurance performs during project execution.
Question 58 |
A project manager has completed developing schedule and budget. What needs to be done before determine all roles and responsibilities?
A | Create process improvement plan. |
B | Create measurable objectives. |
C | Determine critical path. |
D | Determine team. |
Question 58 Explanation:
The right sequence is: develop budget > determine quality standards, processes, and metrics > create process improvement plan > determine all roles and responsibilities.
[2 - Rita's Process Chart]
Question 59 |
Significant change in the product scope has been approved for implementation. What project manager needs to do first?
A | Achieve common understanding of the change. |
B | Create implementation plan. |
C | Execute change as approved. |
D | Manage configuration. |
Question 59 Explanation:
First, project manager needs to ensure common understanding of the change.
Question 60 |
What would be the best next step after stakeholder management strategy has been developed?
A | Develop project charter. |
B | Create project scope statement. |
C | Determine how to do planning. |
D | Finalize requirements. |
Question 60 Explanation:
Determine how to do planning is the first planning task project manager have to perform in the planning process group. This task delivers a development approach to all management plans.
Question 61 |
Create activity list, create network diagram, estimate resource requirements, estimate time and cost, determine critical path, develop budget. What is missing in this sequence?
A | Plan communication. |
B | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
C | Determine all roles and responsibilities. |
D | Develop schedule. |
Question 61 Explanation:
The right sequence is: create activity list > estimate time and cost > determine critical path > develop schedule > develop budget.
[2 - Rita's Process Chart]
Question 62 |
Continuously improve project processes is the project management responsibility. When the project improvement takes place?
A | Project improvement needs to be approached every time when the change is approved. |
B | During project execution. |
C | Project improvement is the monitoring and controlling activities. |
D | Improvement of the project processes need to be done during project planning. |
Question 62 Explanation:
Project improvement performs during project execution.
Question 63 |
Project manager analyses change requests. Some changes will be approved while most of them rejected. What type of activity the project manager performs?
A | Execute project. |
B | Monitoring and controlling. |
C | Performs project improvement. |
D | Planning. |
Question 63 Explanation:
Project manager performs monitoring and controlling processes.
Question 64 |
After creating a network diagram and estimating resource requirements, a project manager has found that more information is needed to determine a longest chain of the tasks in the project. What was needed to be done?
A | Perform quality audit. |
B | Estimate time and cost. |
C | Create activity list. |
D | Develop schedule. |
Question 64 Explanation:
The right sequence is: create activity list > create network diagram > estimate time and cost > determine critical path.
Question 65 |
Which set of processes belongs to the project initiating group?
A | Select project manager, determine company culture, and existing systems, collect processes, and historical information. |
B | Collect historical information information, select project manager, determine quality standards, evaluate team and project performance, create project scope statement. |
C | Determine what to purchase, collect historical information information, select project manager, determine quality standards, determine how you will do planning, create project scope statement. |
D | Select project manager, determine quality standards, processes and metrics, create project scope statement. |
Question 65 Explanation:
Select project manager, determine company culture, and existing systems, collect processes, and historical information is the part for the initiating process group.
[2 - Rita's Project Chart]
Question 66 |
Some project managers complained about issues of managing resources, others mentioned issues to communicate with stakeholders. What advantages brings matrix project organization.
A | Highly visible project objectives. |
B | Easier manage communications. |
C | Two bosses accountable for project delivery. |
D | Resources assigned full time on the project. |
Question 66 Explanation:
Highly visible project objectives is the correct choice. Both functional and project managers have the same objectives to deliver project results. In strong matrix organization project manager has more power on the project, in week - functional manager, and in balanced both are equal. This question also contains distracting information.
Question 67 |
During which part of a project the most conflicts usually happen and require resolve?
A | Planning. |
B | Closing. |
C | Initiation. |
D | Execution. |
Question 67 Explanation:
The most conflicts on a project usually happen during project execution and require facilitation.
Question 68 |
What does it mean perform control of the project?
A | Execute monitoring and controlling processes. |
B | Measure performance against the project metrics, continuously perform project improvement and evaluate team and project performance. |
C | Execute project auditing, maintaining issues log, and reporting status to the management. |
D | Keep team on short leash and communicate with stakeholders to ensure they satisfied with project results. |
Question 68 Explanation:
Execute monitoring and controlling processes.
Question 69 |
Project manager works on change request, manages the reserves of time, cost and contingencies. What type of process the project manager performs?
A | Planning. |
B | Executing. |
C | Monitoring and controlling. |
D | Initiating. |
Question 69 Explanation:
Project manager manages reserves. This type of activities belongs to monitoring and controlling process group.
[1 - Time, Cost and Risk Management - search for "reserve analysis" and "reserves"]
Question 70 |
What project manager should be done before estimate time and cost?
A | Create activity list. |
B | Determine critical path. |
C | Estimate resource requirements. |
D | Determine critical path. |
Question 70 Explanation:
The right sequence is: create activity list > create network diagram > estimate resource requirements > estimate time and cost > determine critical path.
[2 - Rita's Process Chart]
Question 71 |
While executing the work, project manager received three requests. The project sponsor asks for insignificant change that doesn't affect the time or cost, but may significantly enhance user experience. A group of stakeholders requested new functionality that changes business logic of the product, significantly reduces the project cost, brings new opportunities and meets company's strategic plans. Change management committee approved the change originated from customer, although this change does not add much value to the company. Which of these changes have to be implemented?
A | Sponsor pays money so their request has highest priority and has to be implemented. |
B | Implement only approved changes. |
C | Implement all three changes, because all of them make sense. |
D | Request from a group of stakeholders represents the interests of all the company, majority of stakeholders and end users. Also, this group of stakeholders is most influential in the company. |
Question 71 Explanation:
It is project manager's responsibility to implement only approved changes.
Question 72 |
Project manager prepared procurement documents. What needs to be done next?
A | Plan communications. |
B | Acquire resources. |
C | Determine "how to execute and control" parts of all management plans. |
D | Develop final project management plan. |
Question 72 Explanation:
Determine "how to execute and control" parts of all management plans.
[2 Rita's Process Planning"
Question 73 |
During which part of the project vendors or suppliers should be selected?
A | Planning. |
B | Execution. |
C | Closing. |
D | Initiation. |
Question 73 Explanation:
Sellers should be selected during execution phase of the project.
Question 74 |
Which of the following activities execute in project closing phase?
A | Ask team to complete lessons learned knowledge base. |
B | Complete lessons learned knowledge base. |
C | Provide functional manager with team members performance evaluation. |
D | Ask stakeholder to update lessons learned knowledge base. |
Question 74 Explanation:
Ask stakeholder to update lessons learned knowledge base.
Question 75 |
Project manager communicates with customer and hold meeting in order to get approval for interim project deliverable. To which process group this activity belongs?
A | Initiating. |
B | Closing. |
C | Planning. |
D | Monitoring and controlling. |
Question 75 Explanation:
Gaining acceptance of interim project deliverable from the customer belongs to project monitoring and controlling process group.
Question 76 |
Project manager compares the completed work with requirements. What type of process project manager executes?
A | Performing integrated change control. |
B | Executing. |
C | Monitoring and controlling. |
D | Closing. |
Question 76 Explanation:
This is the part of closing process group. The completed work needs to be confirmed against requirements.
Question 77 |
During what part of the work project manager exchanges with communications most often?
A | Initiation. |
B | Execution. |
C | Planning. |
D | Closing. |
Question 77 Explanation:
Most communications usually happen during project execution.
Question 78 |
When the product scope should be produced?
A | During project initiation. |
B | During project execution. |
C | During project planning. |
D | Project manager looks after project scope, not product scope. |
Question 78 Explanation:
Product scope produced during project execution.
Question 79 |
Create network diagram, estimate resource requirements, estimate time and cost, develop schedule. What is missing in this sequence?
A | Estimate time and cost. |
B | Develop schedule. |
C | Determine critical path. |
D | Develop schedule. |
Question 79 Explanation:
The right sequence is create network diagram > estimate resource requirements > estimate time and cost > determine critical path > develop schedule.
Question 80 |
What process group looks after informing stakeholders about approved changes?
A | Monitoring and controlling |
B | Executing. |
C | Planning. |
D | Communicating. |
Question 80 Explanation:
Project manager performs monitoring and controlling type of activity when informs stakeholders about approved changes.
Question 81 |
Create network diagram, estimate time and cost, determine critical path, develop schedule. What process is missing in this sequence?
A | Create process improvement plan. |
B | Estimate resource requirements. |
C | Determine quality standards, processes, and metrics. |
D | Develop budget. |
Question 81 Explanation:
The right sequence: create network diagram > estimate resource requirements > estimate time and cost > determine critical path > develop schedule.
Question 82 |
When the work authorization system is used?
A | During project execution. |
B | Work authorization system is used while monitoring and controlling the project. |
C | When the product scope is authorized. |
D | Work authorization system is used when selecting vendors. |
Question 82 Explanation:
Work authorization system is used during project execution.
Question 83 |
Which of the following activities belongs to project monitoring and controlling process group?
A | Perform quality assurance. |
B | Determine quality standards, processes, and metrics. |
C | Perform quality audit. |
D | Perform quality control. |
Question 83 Explanation:
Perform quality control belongs to monitoring and controlling process group. The rest choices are from executing or planning process groups.
Question 84 |
What should be used as an input in project initiation processes?
A | Templates, historical estimates and WBSs, and communications with stakeholders. |
B | Configuration plan. |
C | Determine what to purchase. |
D | Stakeholders management strategy. |
Question 84 Explanation:
Templates, historical estimates and WBSs, and communications with stakeholders can be a list of inputs for project initiation group.
[2 - Rita's Project Chart]
Question 85 |
What should be done next after completion of risk identification, qualitative and quantitative risk analysis, and risk response planning?
A | Plan communications. |
B | Prepare procurement documents. |
C | Perform iterations of previous steps. |
D | Request changes. |
Question 85 Explanation:
After performing risk identification, qualitative and quantitative risk analysis, and risk response planning go back iterations needs to be done in most cases. The identify risk is an iterative process because new risks may evolve or become know as the project progresses through the life cycle. The frequency of iteration and who participates in each cycle will vary by situation.
[1 -11.2 Identify Risks]
Question 86 |
A project manager is going to determine quality standards, processes, and metrics. What task needs to be finished first?
A | Develop budget. |
B | Create WBS and WBS dictionary. |
C | Create process improvement plan. |
D | Estimate time and cost. |
Question 86 Explanation:
The task of develop budget should be completed prior to determine quality standards, processes, and metrics?
[2 - Rita's Process Chart]
Question 87 |
What type of activities project manager applies when validates assumptions, verifies if risk management policies been followed, and assesses the risks?
A | Monitoring and controlling. |
B | Planning. |
C | Executing. |
D | Project audit. |
Question 87 Explanation:
The described activity is monitoring and controlling risks that belongs to the monitoring and controlling process group.
[1 - Monitor and Control Risks]
Question 88 |
Project manager completed subdividing project deliverables and project work into smaller, more manageable components. Description of such work components as work packages and control accounts has been finished too. What should be done next to create network diagram.
A | Determine team. |
B | Estimate resource requirements. |
C | Determine what to purchase. |
D | Create activity list. |
Question 88 Explanation:
After create WBS and WBS dictionary but before create network diagram, create activity list should be completed.
Question 89 |
What is the principal objective of the project stakeholder management?
A | Protecting project from unnecessary changes. |
B | Thwart criticism of the project. |
C | Maintain goodwill in case of overrun budget or schedule. |
D | Identifying all potential users. |
Question 89 Explanation:
The project manager must be vigilant in ensuring that stakeholders continuously support the project. The project manager must take quick action to ensure that the project objectives will be met and that a plan is in place to mitigate the influence and actions of negative stakeholders. [Planning]
Question 90 |
Project sponsor allocated a special fund for team-building activities. During which phase of the project these activities take place most often?
A | During project initiation, the team as getting together most often; so this is most important to support these activities from start. |
B | Most of the team-building activities happen during project execution. |
C | The project planning phase requires more communications with the project members; so, team-building activities the most important during planning period. |
D | It is important the most to support team at the end of the project. During the closing process it is required that the team will stay till to end to ensure all project activities have been completed. |
Question 90 Explanation:
Most of the team-building activities happen during project execution.
Question 91 |
After completing of which planning task it is recommended to perform iterations of the previous tasks?
A | Prepare procurement documents. |
B | Perform risk identification. |
C | Create measurable objectives. |
D | Identify stakeholders. |
Question 91 Explanation:
It is recommended to perform iterations after risk identification, qualitative and quantitative risk analysis, and risk response planning.
[1 - 3.1 Common project management process interactions]
Question 92 |
Which of the following activities belong to project closing phase?
A | User manuals of the product need to be published. |
B | Hand off completed product. |
C | The product results need to be archived and stored. |
D | Document all changes done during course of the project. |
Question 92 Explanation:
Hand off completed product.
Question 93 |
When formal approval of the plan should be received?
A | Before produce product scope. |
B | After the project management plan and performance measurement baseline are completed. |
C | After Preparation of procurement documents. |
D | Before preform quality assurance. |
Question 93 Explanation:
After the project management plan and performance measurement baseline are completed.
[2 - Rita's Process Chart]
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 93 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
| 1 | 2 | 3 | 4 | 5 |
| 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 |
| 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 |
| 31 | 32 | 33 | 34 | 35 |
| 36 | 37 | 38 | 39 | 40 |
| 41 | 42 | 43 | 44 | 45 |
| 46 | 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 | 55 |
| 56 | 57 | 58 | 59 | 60 |
| 61 | 62 | 63 | 64 | 65 |
| 66 | 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| 76 | 77 | 78 | 79 | 80 |
| 81 | 82 | 83 | 84 | 85 |
| 86 | 87 | 88 | 89 | 90 |
| 91 | 92 | 93 | End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!