Development of this quiz is in progress.
PM - Cost Management
Start
Congratulations - you have completed PM - Cost Management.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
A project manager concerns about increasing of productivity and saving money. What of the following may help in estimating costs process?
A | Scope baseline. |
B | Human resources plan. |
C | Policies on estimating, processes, templates, company culture and existing systems. |
D | Project schedule. |
Question 1 Explanation:
All listed choices are inputs to the Estimating Costs process; however, the Human Resources Plan provides information about the resources rates, as well as rewarding expenses, which important in estimating costs.
[1 - 7.1.1 Estimate Costs: Inputs]
Question 2 |
What parts of the estimated budget included to control account?
A | Activities and work packages. |
B | Project estimate, contingency estimate. |
C | Contingency and management reserves. |
D | Cost baseline, plus management reserves. |
Question 2 Explanation:
Control Account includes Activity Estimates and Work Packages Estimates. The hierarchy of estimated budget is the following: activity, Work Package, Control Account, Project, Contingency, Cost Baseline, Cost Budget.
[1 - 7.2 Determine Budget]
Question 3 |
Earned Value (EV) means _____.
A | What is the value of completed work. |
B | How much money earned. |
C | How much finds are spent. |
D | How much time is spent. |
Question 3 Explanation:
Earned Value (EV) means how much work is done.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 4 |
At the start of a project, the Budget at Completion (BAC) and the Project Budget have the same values.
A | These terms are not related. |
B | False. |
C | True. |
D | These are the same terms. |
Question 4 Explanation:
Before any changes are made to a project, the BAC and the Project Budget have the same value. A change in project scope might change the Project Budget, but it does not change the original BAC, with also called Planned Value (PV) or Original Cost Estimate (OCE).
Question 5 |
The project sponsor determined a cost constrain that does not seem to cover the project's objectives. What project manager needs to do to provide realistic project plan?
A | Not to engage the project. |
B | Analyze the scope and requirements and come up with options to cut scope or reduce quality. |
C | Ask other project manager for advise. |
D | Let the sponsor know about the risk and continue project while budget is available. |
Question 5 Explanation:
All choices may make sense, but first you need to analyze are the reasons, and come up with the options.
[1 - 7.1 Estimate Costs]
Question 6 |
What is the Planned Value (performance measurement baseline or total planned value - Budget at Completion)?
A | Current estimate of authorized budget assigned to complete the work. |
B | A budget that left after the work is complete. |
C | The allocated amount of money, plus management reserves. |
D | The allocated amount of money, plus contingency reserves and management reserves. |
Question 6 Explanation:
Planned value (budget) that authorized assigned to complete the work.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 7 |
Which output of the estimating costs process explains the approach of applied estimating method?
A | Activity costs estimates. |
B | Estimation management plan. |
C | Basis of Estimates. |
D | Procurement plan. |
Question 7 Explanation:
Basis of Estimates explains the applied approach of the estimate.
[1 - 7.1.3 Estimate Costs: Output]
Question 8 |
Calculation To Complete Performance Index (TCPI)?
A | A quotient of Earned Value on Actual Cost
CV = EV / AC |
B | A difference between Earned Value and Actual Cost
CV = EV - AC |
C | A difference between Earned Value and Present Value
CV = EV - PV |
D | To Complete Performance Index (TCPI) is a quotient of the remaining work to residual of money.
(BAC - EV) / (BAC - AC) |
Question 8 Explanation:
To Complete Performance Index (TCPI) is a quotient of the remaining work to residual of money.
TCPI = (BAC - EV) / (BAC - AC)
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 9 |
What level of accuracy provides +/-50% from actual cost?
A | Budget estimate. |
B | Estimate of internal design. |
C | Definitive estimate. |
D | Rough order of magnitude. |
Question 9 Explanation:
Rough order of magnitude is the right answer.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 10 |
While selecting a project, what of the following financial factors are important?
A | Project costs and after implementation costs. |
B | Sponsor's constrains. |
C | After implementation costs. |
D | Feasibility of stakeholders' expectations. |
Question 10 Explanation:
Project costs and after implementation costs, both needs to be considered during project selection process.
[1 - 7. Project Cost Management]
Question 11 |
What aggregated parts included in estimated budget?
A | Project estimate and management reserves. |
B | Cost Baseline and management reserves. |
C | Control account estimate, contingency, and management reserves. |
D | Project estimate and contingency reserves. |
Question 11 Explanation:
The hierarchy of estimated budget is the following: Activity, Work Package, Control Account, Project, Contingency, Cost Baseline, Cost Budget.
[1 - 7.2 Determine Budget]
Question 12 |
How 50/50 Rule is used for project reporting?
A | Status of an activity is judged for 100% completed work. |
B | Status of an activity is judged by completeness of 50% of the work. |
C | Status of an activity is judged by each 20% (20x5=100%) of completeness. |
D | Status of an activity is judged for each half (50%) of completeness. |
Question 12 Explanation:
Status of an activity is judged for each half (50%) of completeness.
[1 - 7.2 Determine Budget]
Question 13 |
What earned value management is?
A | Financial method to identify project performance by measuring actual costs against planned costs. |
B | Project management techniques for measuring of spent costs and time to identify project performance in an object manner. |
C | Project management technique for measuring project performance and progress in an object manner. |
D | Management methodology for measuring the expense again planned values to identify project progress in an object manner. |
Question 13 Explanation:
Earned Value Management is a project management technique for measuring project performance and progress in an object manner.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 14 |
Which process develops an approximation of the monetary resources needed to complete project activities?
A | Estimate costs. |
B | Control account. |
C | Determine Budget. |
D | Control costs. |
Question 14 Explanation:
Estimate costs is the process that develops an adequate numbers for expenses related to resources needed to complete project activities.
[1 - 7. Project Cost Management]
Question 15 |
Who takes cost risk on fixed-price contracts?
A | User. |
B | Equally both vendor and buyer. |
C | Buyer. |
D | Vendor. |
Question 15 Explanation:
Vendor has more risk on fixed price contract. The risk is reduces when the scope and requirements are documented in more details.
[1 - Scope, Cost, Procurement project management knowledge areas]
Question 16 |
What cost types should be estimated?
A | Direct and indirect. |
B | Variable. |
C | Fixed. |
D | All choices are right. |
Question 16 Explanation:
All choices are right.
[1 - 7.1 Estimate Costs]
Question 17 |
How to calculate Schedule Performance Index (SPI)?
A | Schedule Performance Index is a quotient of Earned Value on Actual Cost
CV = EV / AC |
B | Schedule Performance Index is a quotient of Earned Value on Present Value
CV = EV / PV |
C | Schedule Performance Index equals a difference between Earned Value and Actual Cost
CV = EV - AC |
D | Schedule Performance Index equals a difference between Earned Value and Present Value
CV = EV - PV |
Question 17 Explanation:
Schedule Performance Index is a quotient of Earned Value on Present Value (CV = EV / PV). Result means percentage of progress: >1 - good, <1 bad.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 18 |
Amount that vendor received for conducting a project called _____.
A | Net income. |
B | Gross Profit. |
C | Revenue. |
D | Expense. |
Question 18 Explanation:
Revenue is the total amount of funds a vendor receives for its product or service.
Question 19 |
Who is responsible for realistic and accurate estimation of the project?
A | Project sponsor. |
B | Project manager. |
C | Project team. |
D | Stakeholders. |
Question 19 Explanation:
Project manager is responsible for realistic and accurate estimations, and maintain their integrity throughout the project.
[1 - 7.1 Estimate Costs]
Question 20 |
What is actual cost (total cost) (AC)?
A | Current estimated and authorized budget assigned to complete the work. |
B | A planned budget assigned to complete the work. |
C | Cost of the work to complete the work. |
D | The total cost of accomplished work at its current stage. |
Question 20 Explanation:
The total cost of accomplished work at its current stage.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 21 |
Which of the following sources provides estimate costs with human resource plan?
A | Scope statement. |
B | Risk register. |
C | Develop human resource plan. |
D | Cost estimate. |
Question 21 Explanation:
Human Resource Plan feeds Estimate Costs, but produced by Develop Human Resource Plan process.
[1 - 7.1 Estimate Costs]
Question 22 |
What does the Basis of Estimates explain?
A | Indication of the confidence level of the estimate. |
B | All units, references and ranges of estimate. |
C | All answers are right. |
D | How the estimates were developed, documentation on all assumptions and constrains. |
Question 22 Explanation:
All answers are right. The basis of estimate explains how the estimating process work, what sources and methodologies were used, what thresholds are, and what action to be taken when they are reached. An example of such document or even a standard could be found in enter[rise environmental factors or historical records on other projects.
[1 - 7.1.3 Estimate Costs: Output]
Question 23 |
What advantages brings the analogous estimating?
A | Gives an analogous estimation to overall project cost. |
B | Provides a reference to a level of the management\s and stakeholder's expectations, similarly as with another project. |
C | All choices are right. |
D | Easier to faster to create. |
Question 23 Explanation:
All choices are right.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 24 |
Which document provides estimating cost process with the details about the estimating subject?
A | All choices are right. |
B | Human resources plan. |
C | Scope baseline. |
D | Project schedule. |
Question 24 Explanation:
Scope baseline provides cost estimating process with the details about estimating subject.
[1 - 7.1.1 Estimate Cost:s Inputs]
Question 25 |
How 20/80 Rule is used for project reporting?
A | Status of an activity is judged by each 20% (20x5=100%) of completeness. |
B | Status of an activity is judged for its 20% and then 80% of completeness. |
C | Status of an activity is judged for each half (50%) of completeness. |
D | Status of an activity is judged by completeness of 50% of the work. |
Question 25 Explanation:
Status of an activity is judged for its 20% and then 80% of completeness.
[1 - 7.2 Determine Budget]
Question 26 |
What is the purpose of project cost management?
A | Complete project within approved budget. |
B | Providing structured reporting about project status. |
C | Ensure that project progress is on budget. |
D | Provide structured control account for project budget. |
Question 26 Explanation:
Complete project within approved budget is the right answer.
[1 - 7. Project Cost Management]
Question 27 |
How to calculate Variance at Completion (VAC)?
A | A quotient of Earned Value on Actual Cost
CV = EV / AC |
B | Variance at Completion is a difference between Budget at Completion and Estimation at Completion
VAC = BAC - EAC |
C | A difference between Earned Value and Present Value
CV = EV - PV |
D | A quotient of the remaining work to residual of money.
(BAC - EV) / (BAC - AC) |
Question 27 Explanation:
Variance at Completion is a difference between Budget at Completion and Estimation at Completion
VAC = BAC - EAC
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 28 |
How to calculate Estimate At Completion (EAC)?
A | Actual cost plus is a quotient of Budget at Completion to Cost Performance Index.
EAC = BAC / Cumulative CPI |
B | Actual cost plus estimate for the remaining work.
EAC = AC + ETC |
C | Actual cost plus difference between Budget at Completion (BAC) and Earned Value.
EAC = AC + (BAC - EV) |
D | All choices are right. |
Question 28 Explanation:
All choices are right, in addition,
AC + [(BAC-EV) / CPI * SPI)]. This formula calculates actual to date, plus remaining budget modified by performance.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 29 |
What project management knowledge area supports creating cost management plan as a part of project management plan?
A | Integration management. |
B | Initiation. |
C | Planning. |
D | Time management. |
Question 29 Explanation:
Integration management knowledge area supports creation of cost management plan as a part of project management plan.
[1 - 7. Project Cost Management]
Question 30 |
A company's analysis and decision to purchase a product or service instead of producing the service or product itself is called _____.
A | Life cycle costing. |
B | Variable costing. |
C | Make-or-buy decision. |
D | Cost accounting. |
Question 30 Explanation:
A make-or-buy decision is made by a company when selecting between making a product or service or buying it. Such decision is based internal rate of return IRR, and other factors, ROI, Payback Period, Present Value, Net Present Value, Benefit Ratio.
Question 31 |
The project has the following numbers: Revenue $2,400,000; Salaries 1,100,000; Sale Commissions: $180,000; Cost of Equipment $280,000; Cost of Software Licenses $120,000; Cost of Advertising $90,000; Travel by Sales and Marketing staff $80,000; Import and Export duties: $30,000. What is net income of the project?
A | $520,000 |
B | $630,000 |
C | $810,000 |
D | $920,000 |
Question 31 Explanation:
Net income = $2,400,000 revenue - $1,100,000 salaries - $280,000 equipment - $120,000 software licenses - $90,000 advertising - $180,000 sales commission - $80,000 travel - $30,000 import and export duties = $520,000.
Question 32 |
What criterion influences the project costs and after implementation product maintenance costs?
A | Project duration. |
B | Quality. |
C | Unknown risks. |
D | Allocated budget. |
Question 32 Explanation:
Quality is the criterion that effects both costs of the project and after implementation product maintenance expenses. Poor quality may save some funds of the project, but become times more expensive to maintain. So along with other selection criteria, the costs throughout product life cycle need to be considered, when determine the product quality.
[1 - 7. Project Cost Management]
Question 33 |
What disadvantages of the analogous estimating?
A | Counts only similarities, not differences in the comparing projects. |
B | All choices are right. |
C | May required considerable experience for complete, especially for cases with uncertainty. |
D | Risk to gain bigger estimation without justification. |
Question 33 Explanation:
All choices are right.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 34 |
Why the cost of quality should be added to project costs?
A | Because the cost of quality is a contingency part of budget. |
B | Because the cost of quality if a part of management reserve. |
C | Such costs should be assumed in the project charter. |
D | It may take considerable time and efforts to provided accurate estimation. |
Question 34 Explanation:
An accurate estimation may take considerable time, efforts, and costs to provide accurate estimation.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 35 |
How to calculate Estimation to Complete (ETC)?
A | A quotient of Earned Value on Actual Cost
CV = EV / AC |
B | A difference between Earned Value and Present Value
CV = EV - PV |
C | A quotient of the remaining work to residual of money.
(BAC - EV) / (BAC - AC) |
D | Estimation to Complete is a difference between Estimation at Completion and Actual Cost.
ETC = EAC - AC |
Question 35 Explanation:
Estimation to Complete is a difference between Estimation at Completion and Actual Cost. This defines how much more money needs to complete the project.
ETC = EAC - AC.
Question 36 |
How the vendor's estimation may help project performing organization in estimating costs?
A | Cannot be used because the seller has different enterprise environmental factors and organizational process assets. |
B | Assumption of the costs for outsourced project cannot be used because it includes planned profit of the seller. |
C | The outsourced estimation is the most accurate because it presents an existing project team. |
D | It gives a reference to the costs that associated with the outsources project. This can be used for calculating the internal costs. |
Question 36 Explanation:
Vendor Bid Analysis gives a reference to the costs associated with the outsources project, which can be used for calculating the internal costs.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 37 |
Which estimation is more accurate?
A | Rough order of magnitude. |
B | Definitive estimate. |
C | Estimate of external design. |
D | Budget estimate. |
Question 37 Explanation:
Definitive estimate is usually done with +/-10% accuracy, budget estimate as +/-10% - 25%, and ROM can be done with +/-50%-300%; all depends on the available information about the project.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 38 |
Which term refers to the money it takes to sell a product after it is made?
A | Gross income. |
B | Expence. |
C | Revenue. |
D | Cost. |
Question 38 Explanation:
Expenses are the funds used to sell products or services.
Question 39 |
The schedule variance (SV) of your project shows that the project is likely to have a schedule overrun. You know this because the budget is much:
A | Lower than the actual cost (AC). |
B | Lower than the Earned Value (EV). |
C | Higher than the value of Earned Value (EV). |
D | Higher than the actual cost (AC). |
Question 39 Explanation:
If the budget is higher than the Earned Value, more work is scheduled than has been completed. Therefore, the Schedule Variance SV is negative.
Question 40 |
While determining budget a project manager uses _____ processes.
A | Communication. |
B | Executing. |
C | Planning. |
D | Controlling. |
Question 40 Explanation:
Determine Budget is one of the processes of planning process group.
[1 - 7. Project Cost Management]
Question 41 |
During the application development a project manager performs control costs. What process group is used?
A | Executing. |
B | Initiating. |
C | Planning. |
D | Monitoring an controlling. |
Question 41 Explanation:
Control Costs is a part of Monitoring an Controlling process Group.
[1 - 7. Project Cost Management]
Question 42 |
What of the following documents are needed to Estimate Costs based on scope baseline with acceptance criteria, key deliverables, project boundaries, assumptions and constrains, as well as the detailed relations between all components of the project and project deliverables?
A | Scope statement and project schedule. |
B | Scope statement and work breakdown structure. |
C | Project scope statement and resource estimate. |
D | Project scope and activity cost estimate. |
Question 42 Explanation:
Scope statement and work breakdown structure are inputs to Scope Baseline, which is used in Estimate Costs process to produce Activity Cost Estimates, along with updating Project Document.
[1 - 7.1 Estimate Costs]
Question 43 |
What advantages creates the bottom-up estimating?
A | Provides detailed references for monitoring and controlling, performance management, and management. |
B | Obtains buy-in from the team and stakeholders. |
C | All choices are right. |
D | Provides more accurate estimation that based on detailed analysis. |
Question 43 Explanation:
All choices are right.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 44 |
What action should try first for decreasing estimation of cost and/or time?
A | Reducing or eliminating the risks. |
B | Reasonable cut of project scope. |
C | Increasing thresholds tolerance. |
D | Increasing time and budget. |
Question 44 Explanation:
Reducing or eliminating the risks may decrease estimation.
[1 - 7.1 Estimate Cost]
Question 45 |
Which of the following terms refers to amount of money required to create a product and put it on the shelf ready for sale?
A | Expense. |
B | Costs. |
C | Budget to Complete. |
D | Revenue. |
Question 45 Explanation:
* Costs are the all expenditures to complete the project and get a product or service ready for sale.
Question 46 |
What disadvantages of the bottom-up estimating?
A | All choices are right. |
B | This is one of the most expensive types of estimation because of it detailed level. |
C | Requires deep understanding and detailed breakdown of the project. |
D | Padding may happen because of complexity of the work, if no reserve was considered. |
Question 46 Explanation:
All choices are right.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 47 |
The project has the following numbers: Revenue $2,400,000; Salaries 1,100,000; Sale Commissions: $180,000; Cost of Equipment $280,000; Cost of Software Licenses $120,000; Cost of Advertising $90,000; Travel by Sales and Marketing staff $80,000; Import and Export duties: $30,000. What is the Gross Profit of the Project?
A | $1,020,000 |
B | $900,000 |
C | $720,000 |
D | $810,000 |
Question 47 Explanation:
Gross profit = $2,400,000 revenue - ($1,100,000 salaries + $280,000 equipment + $120,000 software licenses) = $900,000.
Question 48 |
What measurements earned value management integrates?
A | Scope, cost, schedule, and risks measures. |
B | Scope, cost, and schedule measures. |
C | Scope, cost, schedule, and procurement measures. |
D | Scope, cost, schedule, and communications measures. |
Question 48 Explanation:
Earned Value Management integrates Scope, Cost, and Schedule measures.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 49 |
A project manager uses parametric and analogous methods for estimating the cost. In what type of processes he is currently involved?
A | Cost management. |
B | Planning. |
C | Executing. |
D | Control cost. |
Question 49 Explanation:
Project manager is doing planning.
[1 - 7. Project Cost Management]
Question 50 |
How to calculate Schedule Variance (SV)?
A | Schedule Variance equals a difference between Earned Value and Actual Cost
CV = EV - AC |
B | Schedule Variance is a quotient of Earned Value on Actual Cost
CV = EV / AC |
C | Schedule Variance equals a difference between Earned Value and Present Value
CV = EV - PV |
D | Schedule Variance is a quotient of Earned Value on Present Value
CV = EV / PV |
Question 50 Explanation:
Schedule Variance equals a difference between Earned Value and Present Value(CV = EV - PV). Results: NEGATIVE is BEHIND schedule, POSITIVE is AHEAD of schedule.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 51 |
What describes the format and sets the criteria for planning, structuring, estimating, budgeting, and controlling project costs?
A | Cost management plan. |
B | Work performance plan. |
C | Cost management processes. |
D | Control account plan. |
Question 51 Explanation:
Cost management plan describes the format and sets the criteria for planning, structuring, estimating, budgeting, and controlling project costs.
[1 - 7. Project Cost Management]
Question 52 |
Cost Variance (CV) is a difference between Earned Value (EV) and _____.
A | Budget at Completion (BAC) |
B | Present Value (PV) |
C | Estimate at Completion (EAC) |
D | Actual Cost (AC) |
Question 52 Explanation:
Cost Variance (CV) is a difference between Earned Value (EV) and Actual Cost (AC).
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 53 |
What project manager should concern about when receives estimates?
A | Time and cost thresholds. |
B | Assumptions and constrains. |
C | Costs of efforts rather than duration. |
D | Padding and risks. |
Question 53 Explanation:
Estimates should be checked for padding and risks.
[1 - 7.1 Estimate Costs]
Question 54 |
Output of which process the quantitative assessment of probable costs is?
A | Estimate quality costs. |
B | Estimate costs. |
C | Estimate cost of resources. |
D | Estimate resources requirements. |
Question 54 Explanation:
Quantitative assessment of probable costs that required to complete a project is and output of the Estimate Costs.
[1 - 7.1.3 Estimate Costs: Output]
Question 55 |
Your project has a cost of $280,000, an expense of $170,000 and a markup of 1.35. What is the revenue?
A | $607.5 |
B | $548 |
C | $509.5 |
D | $148.5 |
Question 55 Explanation:
The correct answer is now shown. Revenue = (Cost + Expense) x Markup.
Question 56 |
What tools and techniques are used to determine budget?
A | All choices are right. |
B | Funding limit reconciliation. |
C | Expert judgement and historical relationships. |
D | Cost aggregation and reserve analysis. |
Question 56 Explanation:
All choices are right.
[1 - 7.2 Determine Budget]
Question 57 |
A project manager is working with scope baseline, project schedule human resources plan and risk register. What process the project manager performs?
A | Estimate costs. |
B | Create WBS and WBS dictionary. |
C | Develop schedule. |
D | Estimate resource requirements. |
Question 57 Explanation:
Along with enterprise environmental factors and organizational process assets, all these are inputs to Estimate Costs process.
[1 - 7.1 Estimate Costs]
Question 58 |
Which document provides estimating cost process with information about the activities, type and quantity of resources?
A | Project management costs. |
B | Project schedule. |
C | Scope baseline. |
D | Risk register.. |
Question 58 Explanation:
Project schedule provides costs estimating with information about the activities, type and quantity of resources.
[1 - 7.1.1 Estimate Cost:s Inputs]
Question 59 |
What set of tools and techniques can be used for estimating costs?
A | Same as used to estimate resource requirements. |
B | Same as used to estimate risk. |
C | Same as used to estimate scope. |
D | Same as used to estimate time. |
Question 59 Explanation:
Same estimation techniques as used to estimate time are applied for estimating costs., while in addition bottom-up estimation is useful.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 60 |
Which of the following sources provides estimate costs with project schedule?
A | Develop schedule. |
B | Risk register. |
C | Cost estimate. |
D | Scope statement. |
Question 60 Explanation:
Project Schedule feeds Estimate Costs, but produced by Develop Schedule process.
[1 - 7.1 Estimate Cost]
Question 61 |
What parts of the estimated budget are included to cost baseline?
A | Project estimate and management reserves. |
B | Project estimate, contingency reserves, and management reserves. |
C | Project estimate and contingency reserves. |
D | Control account estimate, contingency, and management reserves. |
Question 61 Explanation:
Project estimate and contingency reserves. The hierarchy of estimated budget is the following: Activities, Work Package, Control Account, Project, Contingency, Cost Baseline, Cost Budget.
[1 - 7.2 Determine Budget]
Question 62 |
What criterion makes you increase pessimistic estimation?
A | Risks identified during planning. |
B | Funding constrains determined by sponsor. |
C | Time constrains specified by customer. |
D | Quality requirements provided by stakeholders. |
Question 62 Explanation:
Risks increase pessimistic estimation cost (time) and make influence in PERT. Here also another logic that leads to the right answer. Estimating process belongs to the planning process group, Risks also identified during planning. Wrong answers belong to initiating process group.
Question 63 |
Which process monitors the status of the project and keeps updated the information about the project budget and manages changes to the cost baseline?
A | Determine Budget. |
B | Estimate costs. |
C | Control costs. |
D | Control account. |
Question 63 Explanation:
Control costs is the process that monitors the status of the project and keeps updated the information about the project budget and manages changes to the cost baseline.
[1 - 7. Project Cost Management]
Question 64 |
Which process aggregates the estimated expenses for work items to determine an authorized cost baseline?
A | Perform control costs. |
B | Estimate costs. |
C | Determine Budget. |
D | Create control account. |
Question 64 Explanation:
Determine Budget is the process that aggregates the estimated costs of work items to determine an authorized cost baseline.
[1 - 7. Project Cost Management]
Question 65 |
How to calculate Cost Performance Index (CPI)?
A | Cost Performance Index is a quotient of Earned Value on Actual Cost
CV = EV / AC |
B | Cost Performance Index equals a difference between Earned Value and Actual Cost
CV = EV - AC |
C | Cost Performance Index is a quotient of Earned Value on Present Value
CV = EV / PV |
D | Cost Performance Index equals a difference between Earned Value and Present Value
CV = EV - PV |
Question 65 Explanation:
Cost Performance Index is a quotient of Earned Value on Actual Cost )CV = EV / AC). Results: earning per $1 spent. >1 - effective use of funds, <1 not effective use of funds.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 66 |
During project execution, a project manager performs control costs. What process group is used?
A | Monitoring an controlling. |
B | Executing. |
C | Planning. |
D | Initiating. |
Question 66 Explanation:
Control Costs is a part of Monitoring an Controlling process Group.
[1 - 7. Project Cost Management]
Question 67 |
How to calculate Cost Variance (CV)?
A | Cost Variance is a quotient of Earned Value on Present Value
CV = EV / PV |
B | Cost Variance equals a difference between Earned Value and Actual Cost
CV = EV - AC |
C | Cost Variance is a quotient of Earned Value on Actual Cost
CV = EV / AC |
D | Cost Variance equals a difference between Earned Value and Present Value
CV = EV - PV |
Question 67 Explanation:
Cost Variance equals difference between Earned Value and Actual Cost (CV = EV - AC). Results: NEGATIVE is OVER BUDGET, POSITIVE is UNDER BUDGET.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 68 |
A project management team is working on the reduction of project overall cost without changing scope. What of the following techniques would be suitable for this efforts?
A | Delphi method. |
B | Monte Carlo method. |
C | Cost control. |
D | Value analysis. |
Question 68 Explanation:
Value Analysis, in other words Value Engineering, is a methodology to finding more economical way to reach the project objectives. It is the same as improving the value of product without increasing costs.
[1 - 7. Project Cost Management] [http://en.wikipedia.org/wiki/Value_engineering]
Question 69 |
Your project data shows that the budget is 300, the value of work accomplished is 180, and the actual cost (AC) is 220. What is the efficiency?
A | 0.6 |
B | 1.22 |
C | 0.81 |
D | 0.73 |
Question 69 Explanation:
The efficiency is Earned Value (EV) divided by Actual cost (AC). In this case, Efficiency = 180 / 220 = 0.81.
Question 70 |
A project manager is working on determining budget of the project. What of the following information is missing?
A | Contracts, organizational process assets. |
B | Project schedule, resources calendars. |
C | Activity cost estimates, basis of estimates, basis of estimates, scope baseline. |
D | All choices are right. |
Question 70 Explanation:
All choices are right. All the listed here documents are input to the Determine Budget process.
[1 - 7.2 Determine Budget]
Question 71 |
What is the planned value?
A | The allocated amount of money, plus contingency reserves and management reserves. |
B | A planned budget assigned to complete the work. |
C | An authorized budget assigned to complete the work. |
D | The allocated amount of money, plus management reserves. |
Question 71 Explanation:
planned value is an authorized budget assigned to complete the work.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 72 |
The CPI of the project is 1.23, the SPI is 07, the SV is -90,000, and the PV is $550,000. How to find Cost Variance on the project?
A | 146,300 |
B | -105,800 |
C | 147,200 |
D | -104,600 |
Question 72 Explanation:
CV = EV - AC. Based on given data, EV can be found from SV = EV - PV; EV = SV - PV = -90,000 - 550,000 = -640,000
AC can be found from CPI = EV / AC; AC = CPI * EV = 1.23 * (-640,000) = -787,200. Finally, CV = 640,000 - 787,200 = 147,200
Question 73 |
What funds the project budget constitutes?
A | Amount of money that aggregates estimated costs of all project activities authorized to spend on the project. |
B | Amount of money to cover direct and indirect costs of the project, plus contingency and management reserve. |
C | Amount of money to cover direct and indirect costs of the project, plus management reserve. |
D | Amount of money to cover the direct costs for planning, execution and closing of the project. The cost of project initiating is covered by company's overhead expenses. |
Question 73 Explanation:
Determine Budget constitutes amount of money authorized to spend on the project.
[1 - 7.1.3 Estimate Costs]
Question 74 |
A project manager did good work and prepared an accurate work breakdown structure. What type of techniques is used for detailed estimating of an available activities or work package, which then rolled up into control accounts and after into overall project estimate?
A | Analogous estimating. |
B | Parametric estimating. |
C | Bottom-up estimating. |
D | Top-down estimating. |
Question 74 Explanation:
Bottom-up estimating can be used for detailed estimating of an available activities or work package, which then rolled up into control accounts and after into overall project estimate?
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 75 |
What of the following describes the required level of accuracy in cost estimates, control thresholds, and rules of performance measurement.
A | Cost management processes. |
B | Control account plan. |
C | Cost management plan. |
D | Work performance plan. |
Question 75 Explanation:
Cost management plan describes the level of accuracy of cost estimates, control thresholds and rules of performance measurement.
[1 - 7. Project Cost Management]
Question 76 |
What process may help keeping estimations realistic through whole project?
A | Constant process improvement. |
B | Supporting changes. |
C | Periodic re-estimation. |
D | Applying preventive actions. |
Question 76 Explanation:
To keep estimations realistic through whole project they need to be refining periodically. So periodic re-estimation would be a suitable process.
[1 - 7.1 Estimate Costs]
Question 77 |
The project budget _____.
A | Never change. |
B | There is always deviation between budget and actual cost, what needs to be corrected through the change management. |
C | Is changing no matter what. |
D | Can change through the change management process. |
Question 77 Explanation:
Budget can be change using management process, some tasks or activities can be added to or removed from the scope of a project and thus affect the project budget.
Question 78 |
Which estimation is more accurate?
A | Definitive estimate. |
B | Budget estimate. |
C | Rough order of magnitude. |
D | Estimate of external design. |
Question 78 Explanation:
Definitive estimate is usually done with +/-10% accuracy, budget estimate as +/-10% - 25%, and ROM can be done with +/-50%-300%; all depends on the available information about the project.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 79 |
What is the process by which the cost of an asset is written off over the life of the asset?
A | Amortization |
B | Depreciation |
C | Matriculation |
D | Recision |
Question 79 Explanation:
Depreciation is, for example, when the cost of a computer is written off over a 3-year period.
Question 80 |
How 0/100 Rule is used for project reporting?
A | Status of an activity is judged for its 20% and then 80% of completeness. |
B | Status of an activity is judged for each half (50%) of completeness. |
C | Status of an activity is judged by completeness of 100% of the work. |
D | Status of an activity is judged by completeness of 50% of the work. |
Question 80 Explanation:
Status of an activity is judged for its 20% and then 100% of completeness.
[1 - 7.2 Determine Budget]
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 80 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
| 1 | 2 | 3 | 4 | 5 |
| 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 |
| 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 |
| 31 | 32 | 33 | 34 | 35 |
| 36 | 37 | 38 | 39 | 40 |
| 41 | 42 | 43 | 44 | 45 |
| 46 | 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 | 55 |
| 56 | 57 | 58 | 59 | 60 |
| 61 | 62 | 63 | 64 | 65 |
| 66 | 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| 76 | 77 | 78 | 79 | 80 |
| End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!