Development of this quiz is in progress.
PM - Cost Management
Start
Congratulations - you have completed PM - Cost Management.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
Your project has a cost of $280,000, an expense of $170,000 and a markup of 1.35. What is the revenue?
A | $607.5 |
B | $548 |
C | $148.5 |
D | $509.5 |
Question 1 Explanation:
The correct answer is now shown. Revenue = (Cost + Expense) x Markup.
Question 2 |
Output of which process the quantitative assessment of probable costs is?
A | Estimate costs. |
B | Estimate cost of resources. |
C | Estimate quality costs. |
D | Estimate resources requirements. |
Question 2 Explanation:
Quantitative assessment of probable costs that required to complete a project is and output of the Estimate Costs.
[1 - 7.1.3 Estimate Costs: Output]
Question 3 |
During the application development a project manager performs control costs. What process group is used?
A | Initiating. |
B | Executing. |
C | Monitoring an controlling. |
D | Planning. |
Question 3 Explanation:
Control Costs is a part of Monitoring an Controlling process Group.
[1 - 7. Project Cost Management]
Question 4 |
The CPI of the project is 1.23, the SPI is 07, the SV is -90,000, and the PV is $550,000. How to find Cost Variance on the project?
A | 147,200 |
B | -105,800 |
C | 146,300 |
D | -104,600 |
Question 4 Explanation:
CV = EV - AC. Based on given data, EV can be found from SV = EV - PV; EV = SV - PV = -90,000 - 550,000 = -640,000
AC can be found from CPI = EV / AC; AC = CPI * EV = 1.23 * (-640,000) = -787,200. Finally, CV = 640,000 - 787,200 = 147,200
Question 5 |
What of the following describes the required level of accuracy in cost estimates, control thresholds, and rules of performance measurement.
A | Work performance plan. |
B | Cost management plan. |
C | Cost management processes. |
D | Control account plan. |
Question 5 Explanation:
Cost management plan describes the level of accuracy of cost estimates, control thresholds and rules of performance measurement.
[1 - 7. Project Cost Management]
Question 6 |
Who takes cost risk on fixed-price contracts?
A | Equally both vendor and buyer. |
B | Vendor. |
C | Buyer. |
D | User. |
Question 6 Explanation:
Vendor has more risk on fixed price contract. The risk is reduces when the scope and requirements are documented in more details.
[1 - Scope, Cost, Procurement project management knowledge areas]
Question 7 |
Amount that vendor received for conducting a project called _____.
A | Expense. |
B | Net income. |
C | Gross Profit. |
D | Revenue. |
Question 7 Explanation:
Revenue is the total amount of funds a vendor receives for its product or service.
Question 8 |
How to calculate Variance at Completion (VAC)?
A | A quotient of Earned Value on Actual Cost
CV = EV / AC |
B | A difference between Earned Value and Present Value
CV = EV - PV |
C | A quotient of the remaining work to residual of money.
(BAC - EV) / (BAC - AC) |
D | Variance at Completion is a difference between Budget at Completion and Estimation at Completion
VAC = BAC - EAC |
Question 8 Explanation:
Variance at Completion is a difference between Budget at Completion and Estimation at Completion
VAC = BAC - EAC
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 9 |
A company's analysis and decision to purchase a product or service instead of producing the service or product itself is called _____.
A | Life cycle costing. |
B | Make-or-buy decision. |
C | Cost accounting. |
D | Variable costing. |
Question 9 Explanation:
A make-or-buy decision is made by a company when selecting between making a product or service or buying it. Such decision is based internal rate of return IRR, and other factors, ROI, Payback Period, Present Value, Net Present Value, Benefit Ratio.
Question 10 |
Which of the following sources provides estimate costs with human resource plan?
A | Scope statement. |
B | Cost estimate. |
C | Risk register. |
D | Develop human resource plan. |
Question 10 Explanation:
Human Resource Plan feeds Estimate Costs, but produced by Develop Human Resource Plan process.
[1 - 7.1 Estimate Costs]
Question 11 |
How to calculate Estimation to Complete (ETC)?
A | A quotient of the remaining work to residual of money.
(BAC - EV) / (BAC - AC) |
B | A difference between Earned Value and Present Value
CV = EV - PV |
C | A quotient of Earned Value on Actual Cost
CV = EV / AC |
D | Estimation to Complete is a difference between Estimation at Completion and Actual Cost.
ETC = EAC - AC |
Question 11 Explanation:
Estimation to Complete is a difference between Estimation at Completion and Actual Cost. This defines how much more money needs to complete the project.
ETC = EAC - AC.
Question 12 |
During project execution, a project manager performs control costs. What process group is used?
A | Executing. |
B | Planning. |
C | Monitoring an controlling. |
D | Initiating. |
Question 12 Explanation:
Control Costs is a part of Monitoring an Controlling process Group.
[1 - 7. Project Cost Management]
Question 13 |
The schedule variance (SV) of your project shows that the project is likely to have a schedule overrun. You know this because the budget is much:
A | Higher than the actual cost (AC). |
B | Lower than the actual cost (AC). |
C | Higher than the value of Earned Value (EV). |
D | Lower than the Earned Value (EV). |
Question 13 Explanation:
If the budget is higher than the Earned Value, more work is scheduled than has been completed. Therefore, the Schedule Variance SV is negative.
Question 14 |
How to calculate Cost Variance (CV)?
A | Cost Variance equals a difference between Earned Value and Present Value
CV = EV - PV |
B | Cost Variance equals a difference between Earned Value and Actual Cost
CV = EV - AC |
C | Cost Variance is a quotient of Earned Value on Present Value
CV = EV / PV |
D | Cost Variance is a quotient of Earned Value on Actual Cost
CV = EV / AC |
Question 14 Explanation:
Cost Variance equals difference between Earned Value and Actual Cost (CV = EV - AC). Results: NEGATIVE is OVER BUDGET, POSITIVE is UNDER BUDGET.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 15 |
What is the planned value?
A | A planned budget assigned to complete the work. |
B | The allocated amount of money, plus management reserves. |
C | An authorized budget assigned to complete the work. |
D | The allocated amount of money, plus contingency reserves and management reserves. |
Question 15 Explanation:
planned value is an authorized budget assigned to complete the work.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 16 |
Calculation To Complete Performance Index (TCPI)?
A | A quotient of Earned Value on Actual Cost
CV = EV / AC |
B | To Complete Performance Index (TCPI) is a quotient of the remaining work to residual of money.
(BAC - EV) / (BAC - AC) |
C | A difference between Earned Value and Present Value
CV = EV - PV |
D | A difference between Earned Value and Actual Cost
CV = EV - AC |
Question 16 Explanation:
To Complete Performance Index (TCPI) is a quotient of the remaining work to residual of money.
TCPI = (BAC - EV) / (BAC - AC)
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 17 |
How to calculate Schedule Variance (SV)?
A | Schedule Variance equals a difference between Earned Value and Present Value
CV = EV - PV |
B | Schedule Variance is a quotient of Earned Value on Actual Cost
CV = EV / AC |
C | Schedule Variance is a quotient of Earned Value on Present Value
CV = EV / PV |
D | Schedule Variance equals a difference between Earned Value and Actual Cost
CV = EV - AC |
Question 17 Explanation:
Schedule Variance equals a difference between Earned Value and Present Value(CV = EV - PV). Results: NEGATIVE is BEHIND schedule, POSITIVE is AHEAD of schedule.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 18 |
A project manager concerns about increasing of productivity and saving money. What of the following may help in estimating costs process?
A | Human resources plan. |
B | Scope baseline. |
C | Policies on estimating, processes, templates, company culture and existing systems. |
D | Project schedule. |
Question 18 Explanation:
All listed choices are inputs to the Estimating Costs process; however, the Human Resources Plan provides information about the resources rates, as well as rewarding expenses, which important in estimating costs.
[1 - 7.1.1 Estimate Costs: Inputs]
Question 19 |
What project manager should concern about when receives estimates?
A | Time and cost thresholds. |
B | Costs of efforts rather than duration. |
C | Padding and risks. |
D | Assumptions and constrains. |
Question 19 Explanation:
Estimates should be checked for padding and risks.
[1 - 7.1 Estimate Costs]
Question 20 |
What parts of the estimated budget are included to cost baseline?
A | Project estimate, contingency reserves, and management reserves. |
B | Control account estimate, contingency, and management reserves. |
C | Project estimate and contingency reserves. |
D | Project estimate and management reserves. |
Question 20 Explanation:
Project estimate and contingency reserves. The hierarchy of estimated budget is the following: Activities, Work Package, Control Account, Project, Contingency, Cost Baseline, Cost Budget.
[1 - 7.2 Determine Budget]
Question 21 |
What is actual cost (total cost) (AC)?
A | The total cost of accomplished work at its current stage. |
B | Cost of the work to complete the work. |
C | A planned budget assigned to complete the work. |
D | Current estimated and authorized budget assigned to complete the work. |
Question 21 Explanation:
The total cost of accomplished work at its current stage.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 22 |
How to calculate Estimate At Completion (EAC)?
A | All choices are right. |
B | Actual cost plus difference between Budget at Completion (BAC) and Earned Value.
EAC = AC + (BAC - EV) |
C | Actual cost plus estimate for the remaining work.
EAC = AC + ETC |
D | Actual cost plus is a quotient of Budget at Completion to Cost Performance Index.
EAC = BAC / Cumulative CPI |
Question 22 Explanation:
All choices are right, in addition,
AC + [(BAC-EV) / CPI * SPI)]. This formula calculates actual to date, plus remaining budget modified by performance.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 23 |
Which process monitors the status of the project and keeps updated the information about the project budget and manages changes to the cost baseline?
A | Estimate costs. |
B | Control account. |
C | Determine Budget. |
D | Control costs. |
Question 23 Explanation:
Control costs is the process that monitors the status of the project and keeps updated the information about the project budget and manages changes to the cost baseline.
[1 - 7. Project Cost Management]
Question 24 |
Which process aggregates the estimated expenses for work items to determine an authorized cost baseline?
A | Estimate costs. |
B | Determine Budget. |
C | Perform control costs. |
D | Create control account. |
Question 24 Explanation:
Determine Budget is the process that aggregates the estimated costs of work items to determine an authorized cost baseline.
[1 - 7. Project Cost Management]
Question 25 |
A project management team is working on the reduction of project overall cost without changing scope. What of the following techniques would be suitable for this efforts?
A | Monte Carlo method. |
B | Delphi method. |
C | Value analysis. |
D | Cost control. |
Question 25 Explanation:
Value Analysis, in other words Value Engineering, is a methodology to finding more economical way to reach the project objectives. It is the same as improving the value of product without increasing costs.
[1 - 7. Project Cost Management] [http://en.wikipedia.org/wiki/Value_engineering]
Question 26 |
Which term refers to the money it takes to sell a product after it is made?
A | Cost. |
B | Expence. |
C | Gross income. |
D | Revenue. |
Question 26 Explanation:
Expenses are the funds used to sell products or services.
Question 27 |
The project sponsor determined a cost constrain that does not seem to cover the project's objectives. What project manager needs to do to provide realistic project plan?
A | Not to engage the project. |
B | Let the sponsor know about the risk and continue project while budget is available. |
C | Ask other project manager for advise. |
D | Analyze the scope and requirements and come up with options to cut scope or reduce quality. |
Question 27 Explanation:
All choices may make sense, but first you need to analyze are the reasons, and come up with the options.
[1 - 7.1 Estimate Costs]
Question 28 |
What is the process by which the cost of an asset is written off over the life of the asset?
A | Amortization |
B | Matriculation |
C | Depreciation |
D | Recision |
Question 28 Explanation:
Depreciation is, for example, when the cost of a computer is written off over a 3-year period.
Question 29 |
How 20/80 Rule is used for project reporting?
A | Status of an activity is judged by each 20% (20x5=100%) of completeness. |
B | Status of an activity is judged for its 20% and then 80% of completeness. |
C | Status of an activity is judged for each half (50%) of completeness. |
D | Status of an activity is judged by completeness of 50% of the work. |
Question 29 Explanation:
Status of an activity is judged for its 20% and then 80% of completeness.
[1 - 7.2 Determine Budget]
Question 30 |
Which output of the estimating costs process explains the approach of applied estimating method?
A | Activity costs estimates. |
B | Basis of Estimates. |
C | Estimation management plan. |
D | Procurement plan. |
Question 30 Explanation:
Basis of Estimates explains the applied approach of the estimate.
[1 - 7.1.3 Estimate Costs: Output]
Question 31 |
How 50/50 Rule is used for project reporting?
A | Status of an activity is judged by completeness of 50% of the work. |
B | Status of an activity is judged by each 20% (20x5=100%) of completeness. |
C | Status of an activity is judged for 100% completed work. |
D | Status of an activity is judged for each half (50%) of completeness. |
Question 31 Explanation:
Status of an activity is judged for each half (50%) of completeness.
[1 - 7.2 Determine Budget]
Question 32 |
What advantages creates the bottom-up estimating?
A | Obtains buy-in from the team and stakeholders. |
B | All choices are right. |
C | Provides more accurate estimation that based on detailed analysis. |
D | Provides detailed references for monitoring and controlling, performance management, and management. |
Question 32 Explanation:
All choices are right.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 33 |
What earned value management is?
A | Management methodology for measuring the expense again planned values to identify project progress in an object manner. |
B | Financial method to identify project performance by measuring actual costs against planned costs. |
C | Project management technique for measuring project performance and progress in an object manner. |
D | Project management techniques for measuring of spent costs and time to identify project performance in an object manner. |
Question 33 Explanation:
Earned Value Management is a project management technique for measuring project performance and progress in an object manner.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 34 |
What is the Planned Value (performance measurement baseline or total planned value - Budget at Completion)?
A | Current estimate of authorized budget assigned to complete the work. |
B | A budget that left after the work is complete. |
C | The allocated amount of money, plus management reserves. |
D | The allocated amount of money, plus contingency reserves and management reserves. |
Question 34 Explanation:
Planned value (budget) that authorized assigned to complete the work.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 35 |
Which process develops an approximation of the monetary resources needed to complete project activities?
A | Estimate costs. |
B | Determine Budget. |
C | Control account. |
D | Control costs. |
Question 35 Explanation:
Estimate costs is the process that develops an adequate numbers for expenses related to resources needed to complete project activities.
[1 - 7. Project Cost Management]
Question 36 |
How to calculate Schedule Performance Index (SPI)?
A | Schedule Performance Index is a quotient of Earned Value on Present Value
CV = EV / PV |
B | Schedule Performance Index is a quotient of Earned Value on Actual Cost
CV = EV / AC |
C | Schedule Performance Index equals a difference between Earned Value and Actual Cost
CV = EV - AC |
D | Schedule Performance Index equals a difference between Earned Value and Present Value
CV = EV - PV |
Question 36 Explanation:
Schedule Performance Index is a quotient of Earned Value on Present Value (CV = EV / PV). Result means percentage of progress: >1 - good, <1 bad.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 37 |
What tools and techniques are used to determine budget?
A | Expert judgement and historical relationships. |
B | Funding limit reconciliation. |
C | All choices are right. |
D | Cost aggregation and reserve analysis. |
Question 37 Explanation:
All choices are right.
[1 - 7.2 Determine Budget]
Question 38 |
Why the cost of quality should be added to project costs?
A | Because the cost of quality is a contingency part of budget. |
B | It may take considerable time and efforts to provided accurate estimation. |
C | Such costs should be assumed in the project charter. |
D | Because the cost of quality if a part of management reserve. |
Question 38 Explanation:
An accurate estimation may take considerable time, efforts, and costs to provide accurate estimation.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 39 |
What disadvantages of the analogous estimating?
A | Counts only similarities, not differences in the comparing projects. |
B | All choices are right. |
C | Risk to gain bigger estimation without justification. |
D | May required considerable experience for complete, especially for cases with uncertainty. |
Question 39 Explanation:
All choices are right.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 40 |
Which document provides estimating cost process with information about the activities, type and quantity of resources?
A | Scope baseline. |
B | Project management costs. |
C | Risk register.. |
D | Project schedule. |
Question 40 Explanation:
Project schedule provides costs estimating with information about the activities, type and quantity of resources.
[1 - 7.1.1 Estimate Cost:s Inputs]
Question 41 |
Which estimation is more accurate?
A | Budget estimate. |
B | Rough order of magnitude. |
C | Estimate of external design. |
D | Definitive estimate. |
Question 41 Explanation:
Definitive estimate is usually done with +/-10% accuracy, budget estimate as +/-10% - 25%, and ROM can be done with +/-50%-300%; all depends on the available information about the project.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 42 |
What parts of the estimated budget included to control account?
A | Activities and work packages. |
B | Project estimate, contingency estimate. |
C | Cost baseline, plus management reserves. |
D | Contingency and management reserves. |
Question 42 Explanation:
Control Account includes Activity Estimates and Work Packages Estimates. The hierarchy of estimated budget is the following: activity, Work Package, Control Account, Project, Contingency, Cost Baseline, Cost Budget.
[1 - 7.2 Determine Budget]
Question 43 |
What disadvantages of the bottom-up estimating?
A | All choices are right. |
B | Requires deep understanding and detailed breakdown of the project. |
C | This is one of the most expensive types of estimation because of it detailed level. |
D | Padding may happen because of complexity of the work, if no reserve was considered. |
Question 43 Explanation:
All choices are right.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 44 |
What criterion influences the project costs and after implementation product maintenance costs?
A | Allocated budget. |
B | Project duration. |
C | Quality. |
D | Unknown risks. |
Question 44 Explanation:
Quality is the criterion that effects both costs of the project and after implementation product maintenance expenses. Poor quality may save some funds of the project, but become times more expensive to maintain. So along with other selection criteria, the costs throughout product life cycle need to be considered, when determine the product quality.
[1 - 7. Project Cost Management]
Question 45 |
A project manager is working on determining budget of the project. What of the following information is missing?
A | All choices are right. |
B | Activity cost estimates, basis of estimates, basis of estimates, scope baseline. |
C | Contracts, organizational process assets. |
D | Project schedule, resources calendars. |
Question 45 Explanation:
All choices are right. All the listed here documents are input to the Determine Budget process.
[1 - 7.2 Determine Budget]
Question 46 |
A project manager uses parametric and analogous methods for estimating the cost. In what type of processes he is currently involved?
A | Cost management. |
B | Planning. |
C | Control cost. |
D | Executing. |
Question 46 Explanation:
Project manager is doing planning.
[1 - 7. Project Cost Management]
Question 47 |
What criterion makes you increase pessimistic estimation?
A | Funding constrains determined by sponsor. |
B | Risks identified during planning. |
C | Quality requirements provided by stakeholders. |
D | Time constrains specified by customer. |
Question 47 Explanation:
Risks increase pessimistic estimation cost (time) and make influence in PERT. Here also another logic that leads to the right answer. Estimating process belongs to the planning process group, Risks also identified during planning. Wrong answers belong to initiating process group.
Question 48 |
While determining budget a project manager uses _____ processes.
A | Executing. |
B | Controlling. |
C | Planning. |
D | Communication. |
Question 48 Explanation:
Determine Budget is one of the processes of planning process group.
[1 - 7. Project Cost Management]
Question 49 |
The project budget _____.
A | Is changing no matter what. |
B | Can change through the change management process. |
C | Never change. |
D | There is always deviation between budget and actual cost, what needs to be corrected through the change management. |
Question 49 Explanation:
Budget can be change using management process, some tasks or activities can be added to or removed from the scope of a project and thus affect the project budget.
Question 50 |
A project manager is working with scope baseline, project schedule human resources plan and risk register. What process the project manager performs?
A | Estimate costs. |
B | Develop schedule. |
C | Create WBS and WBS dictionary. |
D | Estimate resource requirements. |
Question 50 Explanation:
Along with enterprise environmental factors and organizational process assets, all these are inputs to Estimate Costs process.
[1 - 7.1 Estimate Costs]
Question 51 |
What describes the format and sets the criteria for planning, structuring, estimating, budgeting, and controlling project costs?
A | Cost management processes. |
B | Control account plan. |
C | Cost management plan. |
D | Work performance plan. |
Question 51 Explanation:
Cost management plan describes the format and sets the criteria for planning, structuring, estimating, budgeting, and controlling project costs.
[1 - 7. Project Cost Management]
Question 52 |
How to calculate Cost Performance Index (CPI)?
A | Cost Performance Index equals a difference between Earned Value and Present Value
CV = EV - PV |
B | Cost Performance Index is a quotient of Earned Value on Present Value
CV = EV / PV |
C | Cost Performance Index is a quotient of Earned Value on Actual Cost
CV = EV / AC |
D | Cost Performance Index equals a difference between Earned Value and Actual Cost
CV = EV - AC |
Question 52 Explanation:
Cost Performance Index is a quotient of Earned Value on Actual Cost )CV = EV / AC). Results: earning per $1 spent. >1 - effective use of funds, <1 not effective use of funds.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 53 |
At the start of a project, the Budget at Completion (BAC) and the Project Budget have the same values.
A | True. |
B | These terms are not related. |
C | These are the same terms. |
D | False. |
Question 53 Explanation:
Before any changes are made to a project, the BAC and the Project Budget have the same value. A change in project scope might change the Project Budget, but it does not change the original BAC, with also called Planned Value (PV) or Original Cost Estimate (OCE).
Question 54 |
How the vendor's estimation may help project performing organization in estimating costs?
A | The outsourced estimation is the most accurate because it presents an existing project team. |
B | Assumption of the costs for outsourced project cannot be used because it includes planned profit of the seller. |
C | It gives a reference to the costs that associated with the outsources project. This can be used for calculating the internal costs. |
D | Cannot be used because the seller has different enterprise environmental factors and organizational process assets. |
Question 54 Explanation:
Vendor Bid Analysis gives a reference to the costs associated with the outsources project, which can be used for calculating the internal costs.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 55 |
Who is responsible for realistic and accurate estimation of the project?
A | Project manager. |
B | Project team. |
C | Stakeholders. |
D | Project sponsor. |
Question 55 Explanation:
Project manager is responsible for realistic and accurate estimations, and maintain their integrity throughout the project.
[1 - 7.1 Estimate Costs]
Question 56 |
How 0/100 Rule is used for project reporting?
A | Status of an activity is judged for each half (50%) of completeness. |
B | Status of an activity is judged by completeness of 100% of the work. |
C | Status of an activity is judged by completeness of 50% of the work. |
D | Status of an activity is judged for its 20% and then 80% of completeness. |
Question 56 Explanation:
Status of an activity is judged for its 20% and then 100% of completeness.
[1 - 7.2 Determine Budget]
Question 57 |
What set of tools and techniques can be used for estimating costs?
A | Same as used to estimate scope. |
B | Same as used to estimate time. |
C | Same as used to estimate risk. |
D | Same as used to estimate resource requirements. |
Question 57 Explanation:
Same estimation techniques as used to estimate time are applied for estimating costs., while in addition bottom-up estimation is useful.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 58 |
Which of the following terms refers to amount of money required to create a product and put it on the shelf ready for sale?
A | Expense. |
B | Budget to Complete. |
C | Revenue. |
D | Costs. |
Question 58 Explanation:
* Costs are the all expenditures to complete the project and get a product or service ready for sale.
Question 59 |
Which document provides estimating cost process with the details about the estimating subject?
A | Scope baseline. |
B | Human resources plan. |
C | Project schedule. |
D | All choices are right. |
Question 59 Explanation:
Scope baseline provides cost estimating process with the details about estimating subject.
[1 - 7.1.1 Estimate Cost:s Inputs]
Question 60 |
What cost types should be estimated?
A | All choices are right. |
B | Direct and indirect. |
C | Fixed. |
D | Variable. |
Question 60 Explanation:
All choices are right.
[1 - 7.1 Estimate Costs]
Question 61 |
Which of the following sources provides estimate costs with project schedule?
A | Develop schedule. |
B | Cost estimate. |
C | Scope statement. |
D | Risk register. |
Question 61 Explanation:
Project Schedule feeds Estimate Costs, but produced by Develop Schedule process.
[1 - 7.1 Estimate Cost]
Question 62 |
While selecting a project, what of the following financial factors are important?
A | After implementation costs. |
B | Feasibility of stakeholders' expectations. |
C | Project costs and after implementation costs. |
D | Sponsor's constrains. |
Question 62 Explanation:
Project costs and after implementation costs, both needs to be considered during project selection process.
[1 - 7. Project Cost Management]
Question 63 |
What does the Basis of Estimates explain?
A | How the estimates were developed, documentation on all assumptions and constrains. |
B | Indication of the confidence level of the estimate. |
C | All units, references and ranges of estimate. |
D | All answers are right. |
Question 63 Explanation:
All answers are right. The basis of estimate explains how the estimating process work, what sources and methodologies were used, what thresholds are, and what action to be taken when they are reached. An example of such document or even a standard could be found in enter[rise environmental factors or historical records on other projects.
[1 - 7.1.3 Estimate Costs: Output]
Question 64 |
What funds the project budget constitutes?
A | Amount of money to cover the direct costs for planning, execution and closing of the project. The cost of project initiating is covered by company's overhead expenses. |
B | Amount of money to cover direct and indirect costs of the project, plus management reserve. |
C | Amount of money to cover direct and indirect costs of the project, plus contingency and management reserve. |
D | Amount of money that aggregates estimated costs of all project activities authorized to spend on the project. |
Question 64 Explanation:
Determine Budget constitutes amount of money authorized to spend on the project.
[1 - 7.1.3 Estimate Costs]
Question 65 |
What project management knowledge area supports creating cost management plan as a part of project management plan?
A | Planning. |
B | Time management. |
C | Initiation. |
D | Integration management. |
Question 65 Explanation:
Integration management knowledge area supports creation of cost management plan as a part of project management plan.
[1 - 7. Project Cost Management]
Question 66 |
The project has the following numbers: Revenue $2,400,000; Salaries 1,100,000; Sale Commissions: $180,000; Cost of Equipment $280,000; Cost of Software Licenses $120,000; Cost of Advertising $90,000; Travel by Sales and Marketing staff $80,000; Import and Export duties: $30,000. What is the Gross Profit of the Project?
A | $1,020,000 |
B | $810,000 |
C | $720,000 |
D | $900,000 |
Question 66 Explanation:
Gross profit = $2,400,000 revenue - ($1,100,000 salaries + $280,000 equipment + $120,000 software licenses) = $900,000.
Question 67 |
A project manager did good work and prepared an accurate work breakdown structure. What type of techniques is used for detailed estimating of an available activities or work package, which then rolled up into control accounts and after into overall project estimate?
A | Bottom-up estimating. |
B | Parametric estimating. |
C | Analogous estimating. |
D | Top-down estimating. |
Question 67 Explanation:
Bottom-up estimating can be used for detailed estimating of an available activities or work package, which then rolled up into control accounts and after into overall project estimate?
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 68 |
What aggregated parts included in estimated budget?
A | Cost Baseline and management reserves. |
B | Control account estimate, contingency, and management reserves. |
C | Project estimate and management reserves. |
D | Project estimate and contingency reserves. |
Question 68 Explanation:
The hierarchy of estimated budget is the following: Activity, Work Package, Control Account, Project, Contingency, Cost Baseline, Cost Budget.
[1 - 7.2 Determine Budget]
Question 69 |
What level of accuracy provides +/-50% from actual cost?
A | Definitive estimate. |
B | Rough order of magnitude. |
C | Budget estimate. |
D | Estimate of internal design. |
Question 69 Explanation:
Rough order of magnitude is the right answer.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 70 |
The project has the following numbers: Revenue $2,400,000; Salaries 1,100,000; Sale Commissions: $180,000; Cost of Equipment $280,000; Cost of Software Licenses $120,000; Cost of Advertising $90,000; Travel by Sales and Marketing staff $80,000; Import and Export duties: $30,000. What is net income of the project?
A | $920,000 |
B | $520,000 |
C | $630,000 |
D | $810,000 |
Question 70 Explanation:
Net income = $2,400,000 revenue - $1,100,000 salaries - $280,000 equipment - $120,000 software licenses - $90,000 advertising - $180,000 sales commission - $80,000 travel - $30,000 import and export duties = $520,000.
Question 71 |
Your project data shows that the budget is 300, the value of work accomplished is 180, and the actual cost (AC) is 220. What is the efficiency?
A | 1.22 |
B | 0.73 |
C | 0.6 |
D | 0.81 |
Question 71 Explanation:
The efficiency is Earned Value (EV) divided by Actual cost (AC). In this case, Efficiency = 180 / 220 = 0.81.
Question 72 |
What action should try first for decreasing estimation of cost and/or time?
A | Increasing time and budget. |
B | Reducing or eliminating the risks. |
C | Increasing thresholds tolerance. |
D | Reasonable cut of project scope. |
Question 72 Explanation:
Reducing or eliminating the risks may decrease estimation.
[1 - 7.1 Estimate Cost]
Question 73 |
Which estimation is more accurate?
A | Budget estimate. |
B | Estimate of external design. |
C | Definitive estimate. |
D | Rough order of magnitude. |
Question 73 Explanation:
Definitive estimate is usually done with +/-10% accuracy, budget estimate as +/-10% - 25%, and ROM can be done with +/-50%-300%; all depends on the available information about the project.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Question 74 |
What of the following documents are needed to Estimate Costs based on scope baseline with acceptance criteria, key deliverables, project boundaries, assumptions and constrains, as well as the detailed relations between all components of the project and project deliverables?
A | Project scope statement and resource estimate. |
B | Scope statement and project schedule. |
C | Scope statement and work breakdown structure. |
D | Project scope and activity cost estimate. |
Question 74 Explanation:
Scope statement and work breakdown structure are inputs to Scope Baseline, which is used in Estimate Costs process to produce Activity Cost Estimates, along with updating Project Document.
[1 - 7.1 Estimate Costs]
Question 75 |
What measurements earned value management integrates?
A | Scope, cost, schedule, and risks measures. |
B | Scope, cost, and schedule measures. |
C | Scope, cost, schedule, and procurement measures. |
D | Scope, cost, schedule, and communications measures. |
Question 75 Explanation:
Earned Value Management integrates Scope, Cost, and Schedule measures.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 76 |
What process may help keeping estimations realistic through whole project?
A | Periodic re-estimation. |
B | Applying preventive actions. |
C | Supporting changes. |
D | Constant process improvement. |
Question 76 Explanation:
To keep estimations realistic through whole project they need to be refining periodically. So periodic re-estimation would be a suitable process.
[1 - 7.1 Estimate Costs]
Question 77 |
Cost Variance (CV) is a difference between Earned Value (EV) and _____.
A | Present Value (PV) |
B | Budget at Completion (BAC) |
C | Actual Cost (AC) |
D | Estimate at Completion (EAC) |
Question 77 Explanation:
Cost Variance (CV) is a difference between Earned Value (EV) and Actual Cost (AC).
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 78 |
What is the purpose of project cost management?
A | Ensure that project progress is on budget. |
B | Complete project within approved budget. |
C | Provide structured control account for project budget. |
D | Providing structured reporting about project status. |
Question 78 Explanation:
Complete project within approved budget is the right answer.
[1 - 7. Project Cost Management]
Question 79 |
Earned Value (EV) means _____.
A | What is the value of completed work. |
B | How much time is spent. |
C | How much money earned. |
D | How much finds are spent. |
Question 79 Explanation:
Earned Value (EV) means how much work is done.
[1 - 7.3.2 Control Costs: Tools and Techniques]
Question 80 |
What advantages brings the analogous estimating?
A | Provides a reference to a level of the management\s and stakeholder's expectations, similarly as with another project. |
B | Gives an analogous estimation to overall project cost. |
C | Easier to faster to create. |
D | All choices are right. |
Question 80 Explanation:
All choices are right.
[1 - 7.1.2 Estimate Cost:s: Tools and Techniques]
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 80 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
| 1 | 2 | 3 | 4 | 5 |
| 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 |
| 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 |
| 31 | 32 | 33 | 34 | 35 |
| 36 | 37 | 38 | 39 | 40 |
| 41 | 42 | 43 | 44 | 45 |
| 46 | 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 | 55 |
| 56 | 57 | 58 | 59 | 60 |
| 61 | 62 | 63 | 64 | 65 |
| 66 | 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| 76 | 77 | 78 | 79 | 80 |
| End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!