Development of this quiz is in progress.
PM - Time Management
Start
Congratulations - you have completed PM - Time Management.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
What you should focus on while re-estimating activities for the purpose of schedule compression?
A | Costs. |
B | Resource availability. |
C | Quality. |
D | Risks. |
Question 1 Explanation:
While re-estimating activities for the purpose of schedule compression you should focus on risks.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 2 |
Using PERT you have identified 30% of standard deviation in one of the parts on your project. Will you outsource this work with fix-price contract?
A | No, work with standard deviation should not be outsources. |
B | Yes, the scope clarity an be improves using scope management plan. |
C | No, the scope of work is not clear. |
D | Yes, it is a normal range of standard deviation for fixed-price contracts. |
Question 2 Explanation:
This is a cross-knowledge question requires deep understanding of scope, time and procurement areas of project management. The recommenced topic to start is PERT.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 3 |
What type of processes use schedule compression?
A | Executing and closing. |
B | Planning and integrated change control. |
C | Executing, and monitoring and controlling.. |
D | Planning and executing. |
Question 3 Explanation:
Schedule compression is used during planning and integrated change control (monitoring and controlling). During planning project manager optimizes the schedule to meet deadlines without changing scope, and in integrated change control, checks if there is any impact to scope, time, cost, risk, resources or customer satisfaction.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 4 |
Who should participate in estimating process to assure accuracy?
A | Sponsor. |
B | Stakeholder. |
C | Functional manager. |
D | The person who will be executing the work. |
Question 4 Explanation:
The person who will be executing the work can provide more accurate information for estimating the required work efforts and duration.
Question 5 |
How activities and their properties are used on the project?
A | Provide information on how to execute the work packages. |
B | Provide information to measure the project performance in monitoring and controlling processes. |
C | Provide input to estimating, scheduling, executing, and monitoring and controlling of project work. |
D | Provide reference to the work planned for completion of the project. |
Question 5 Explanation:
Provide input to estimating, scheduling, executing, and monitoring and controlling of project work is the most completed answer to the question.
[1 - 6.1 Project Time Management: Define Activities]
Question 6 |
What needs to be done if it is hard to estimate a work package?
A | Reserve extra budget for contingency. |
B | Use double numbers and create reserve. |
C | Use analogous estimation to a similar package. |
D | Decompose to activities. |
Question 6 Explanation:
Work packages need to be decomposed to activities, which to be estimated. Estimation of smaller work components is more accurate.
Question 7 |
What needs to be done if the project has negative slack?
A | Compress schedule. |
B | Ask for additional time. |
C | Re-estimate resource requirements. |
D | Re-estimate activity duration. |
Question 7 Explanation:
If the project has negative slack (float) it means the project is behind the schedule; compress schedule is the recommended action (fast track, crash, reduction of scope or quality).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 8 |
How does the Finish-to-Finish (FF) relations work?
A | The activity must finish before the next activity can start. |
B | The activity cannot start before the next activity can finish. |
C | The completion of successor depends on completion of predecessor. |
D | The activity must finish before the next predecessor can start. |
Question 8 Explanation:
The completion of successor depends on completion of predecessor. In other words, the activity must finish before the related activity finished.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 9 |
How to calculate float?
A | Late Start - Earlier Start or Late Finish - Early Finish. |
B | Late Finish - Earlier Start or Late Finish - Early Finish. |
C | Late Finish - Earlier Start or Late Start - Early Finish. |
D | Late Start - Earlier Finish or Late Start - Early Finish. |
Question 9 Explanation:
Late Start - Earlier Start or Late Finish - Early Finish are the equations to calculate Float (Slack).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 10 |
What tree-point estimate analyzes and produces?
A | Analyzes risks and produces optimistic, most likely and pessimistic estimates. |
B | Analyzes constrains and produces optimistic, most likely and pessimistic estimates. |
C | Analyzes baselines and produces optimistic, most likely and pessimistic estimates. |
D | Analyzes requirements and produces optimistic, most likely and pessimistic estimates. |
Question 10 Explanation:
Tree-point estimate analyzes risks and produces optimistic, most likely and pessimistic estimates.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 11 |
What type of dependency called soft logic?
A | All choices are right. |
B | Preferred dependency. |
C | Discretionary dependency. |
D | External dependency. |
Question 11 Explanation:
Mandatory dependency in other words called had logic and represent the unavoidable dependency from the related activity. For example, an activity that must be done as per law requirement or corporate SDLC standard.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 12 |
What sequence activities is?
A | Process of identifying and documenting logical relationship between the project activities. |
B | Process of identifying and documenting the interface properties between the project activities. |
C | Process of identifying and documenting physical relationship between the project activities. |
D | Process of identifying and documenting the thresholds the project activities. |
Question 12 Explanation:
Process of identifying and documenting relationship between the project activities.
[1 - 6.2 Sequence Activities]
Question 13 |
What a project manager should check regarding schedule when analyses change request?
A | How the change in schedule impacts costs. |
B | How many activities requires impacted the change. |
C | If the change impacts critical path. |
D | If the requested change impacts scope. |
Question 13 Explanation:
While analyzing change request project manager needs to check if the change impacts critical path.
Question 14 |
How many critical paths a project may have?
A | Maximum three. |
B | Many. |
C | Maximum two. |
D | Maximum one. |
Question 14 Explanation:
A project may have many critical paths.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 15 |
How the total float and free float are different?
A | Total float defines the time that an activity can be delayed without delaying of its predecessor, while free float defines the time and activity can delay without delaying start date of the project. |
B | Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its predecessor. |
C | Total float defines the time that an activity can be delayed without delaying of its successor, while free float defines the time and activity can delay without delaying start date of the project. |
D | Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its successor. |
Question 15 Explanation:
Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its successor. In addition, the project float is the amount of time that project can delay without delaying other related projects.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 16 |
What project scheduling methodology defines?
A | Thresholds that project schedule can reach at the end of the project. |
B | Defines the beginning and end dates of the project. |
C | Defines the beginning end, and milestone dates of the project. |
D | Rules and approaches for scheduling process. |
Question 16 Explanation:
Scheduling methodology defines rules and approaches for scheduling process.
[1 - 6 Project Time Management]
Question 17 |
What information is missing while activity list, activity attribute, and resource calendar is provided for estimating activity resources process?
A | Enterprise environmental factors. |
B | Activity resource requirements. |
C | Enterprise environmental factors and organizational process assets. |
D | Organizational process assets. |
Question 17 Explanation:
Activity list, activity attribute, resource calendar, enterprise environmental factors and organizational process assets are inputs to estimate activity resources. Other choices whether incomplete while, activity resource requirements is the output of this process.
[1 - 6 Project Time Management]
Question 18 |
What needs to be done first to justify project time estimate?
A | Build a network diagram. |
B | Collect and combine time estimated for major tasks. |
C | Determine critical path. |
D | Confirm with a team. |
Question 18 Explanation:
Build a network diagram and then determine critical path.
[1 - 6.2 Sequence Activities]
Question 19 |
How near-critical path effect the project?
A | As near-critical path closer to critical path, the project has less risk. |
B | As near-critical path closer to critical path, the project has more risk. |
C | Near-critical path does not have effect to risk? |
D | As near-critical path comes closer to critical path, the project reduces its risk. |
Question 19 Explanation:
As near-critical path closer to critical path, the project has more risk; as identified, both paths needs to be monitored and managed.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 20 |
What information is documented in project schedule management plan?
A | Thresholds that project schedule can reach during planning phase. |
B | Defines the beginning end, and milestone dates of the project. |
C | Project management processes, tools and techniques. |
D | Defined the beginning and end dates of the project. |
Question 20 Explanation:
Project Schedule Management Plan is a part of Project Management Plan and describes the project management processes, tools and techniques to be used on the project.
[1 - 6 Project Time Management]
Question 21 |
What information is needed to perform control schedule process?
A | Finalized and approved schedule, which is used as a baseline. |
B | Project schedule that requested by stakeholders. |
C | Project scope time constrains. |
D | Milestone that approved by project sponsor. |
Question 21 Explanation:
Finalized and approved schedule, which is used as a baseline, is needed to perform control schedule process.
[1 - 6 Project Time Management]
Question 22 |
Sequencing of the activities can be performed using _____.
A | Project management hardware. |
B | Manual optimization method. |
C | Project management software. |
D | Only project management software. |
Question 22 Explanation:
Sequencing of the activities can be performed using project management software.
[1 - 6.2 Sequence Activities]
Question 23 |
What results of the develop schedule should be updated when the process is complete?
A | Project schedule, schedule baseline, activity list. |
B | Project schedule, schedule baseline, work breakdown structure. |
C | Project schedule, schedule baseline, schedule data |
D | All choices are right. |
Question 23 Explanation:
Project schedule, schedule baseline, schedule data and project document update are deliverables of the develop schedule.
[1 - 6 Project Time Management]
Question 24 |
How does the Start-to-Start (SS) relations work?
A | The finish of successor depends on start of predecessor. |
B | The start of successor depends on start of predecessor. |
C | The start of successor depends on finish of predecessor. |
D | The completion of successor depends on completion of predecessor. |
Question 24 Explanation:
The start of successor depends on start of predecessor.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 25 |
What tools and techniques to be used by project manager while defining sequence activities?
A | Precedence diagramming method. |
B | Applying leads and lags, and schedule network templates. |
C | Dependency determination. |
D | All choices are right. |
Question 25 Explanation:
Precedence diagramming method, Precedence diagramming method, applying leads and lags, and schedule network templates are tools and techniques to be used while defining sequence activities.
[1 - 6 Project Time Management]
Question 26 |
What processes include time management project knowledge area?
A | Develop and control schedule. |
B | All choices are right. |
C | Define and sequence activities. |
D | Estimate activity resources and activity durations. |
Question 26 Explanation:
All the listed processes are the part of the Time Management: define activities, sequence activities, estimate activity resources, estimate activity duration, develop schedule, and control schedule.
[PMBOK. Project Time Management]
Question 27 |
A project manager estimates activity duration. What information is needed to make this process effectively?
A | Activity list, activity attributes, and activity resource requirements. |
B | Resource calendars, project scope statements. |
C | All choices are right. |
D | Enterprise environmental factors and organizational process assets. |
Question 27 Explanation:
All choices are right. All these documents are input to the estimate activity duration process.
[1 - 6 Project Time Management]
Question 28 |
What information to be updated at the end of estimate activity resources?
A | Activity resources requirements, resource breakdown structure, and project schedule. |
B | All choices are right. |
C | Activity resources requirements and work breakdown structure. |
D | Activity resources requirements and resource breakdown structure. |
Question 28 Explanation:
Activity resources requirements, resource breakdown structure, and update project document are results of Estimate Activity Resources.
[1 - 6 Project Time Management]
Question 29 |
What does critical path determine?
A | The longest path in the network diagram, as well as the earliest start and earliest finish dates for project activities. |
B | The longest path in the network diagram, as well as the earliest and latest start and finish dates for project activities. |
C | The shortest path in the network diagram, as well as the earliest and latest start and finish dates for project activities. |
D | The shortest path in the network diagram, as well as the latest start and finish dates for project activities. |
Question 29 Explanation:
The longest path in the network diagram, as well as the earliest and latest start and finish dates for project activities.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 30 |
What is the primary task of a project manager before project execution?
A | Create a realistic project plan. |
B | Ensure all efforts will be paid. |
C | Create project charter. |
D | Receive budget to cover project's expenses. |
Question 30 Explanation:
All choices are right in general, but the PRIMARY role of a project manager is create a REALISTIC project management plan PRIOR to project execution.
[PMBOK. Project Time Management.]
Question 31 |
What you should concern about when applying fast track to selected project activity for the purpose of schedule compression?
A | The selected activity is in preferred logic. |
B | All choices are right. |
C | Risks and availability of resources for performing activities concurrently. |
D | The selected activity has discretionary dependency. |
Question 31 Explanation:
Discretionary dependency, preferred or soft logic all refer to an activity that has options to be performed in different sequences. Also, while the work will be done in parallel with other activity, availability of resources is critical. Accordingly, Fast Track may also add risks and more management efforts to manage parallel tasks.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 32 |
What negative float indicates?
A | Project is on schedule. |
B | Project is ahead of plan. |
C | Project behinds. |
D | Project has been compressed. |
Question 32 Explanation:
Negative float indicates that project is behind of schedule.
Question 33 |
Precedence diagramming method is used for _____.
A | Constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. |
B | Constructing a visual diagram that uses nodes to indicate logically related communications between project members and stakeholders. |
C | Constructing a visual diagram that uses nodes to indicate logically related requirements and risks on the project. |
D | Constructing a visual diagram that uses nodes to indicate logically related requirements. |
Question 33 Explanation:
Precedence diagramming method is used for constructing a visual project schedule network diagram that uses nodes to indicate logically related activities.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 34 |
What can be used to show the interdependency between activities through the whole project?
A | Project scope statement. |
B | List of activities. |
C | Network diagram. |
D | Work breakdown structure. |
Question 34 Explanation:
Network diagram shows interdependency of the activities through the whole project.
[1 - 6.2 Sequence Activities]
Question 35 |
What type of dependency called external dependency?
A | Dependency outside of the country. |
B | Dependency outside of the project team. |
C | Dependency outside of the project organization. |
D | Dependency outside of the project. |
Question 35 Explanation:
As long as the dependency is outside of the project it called External", regardless of its location or nature.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 36 |
How graphical evaluation and review techniques (GERT) is different from other diagramming methods?
A | Indicates only mandatory dependencies. |
B | Allows using loops between nodes. |
C | Allows conditional nodes. |
D | Connects nodes with arrows that represent activities. |
Question 36 Explanation:
Graphical Evaluation and Review Techniques (GERT) allows using between project activities.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 37 |
A project manager performs control schedule referring to project management plan, project schedule, work performance data, and _____?
A | Enterprise environmental factors, organizational process assets and requirements documentation. |
B | Enterprise environmental factors and list of activities. |
C | Enterprise environmental factors and organizational process assets. |
D | Project calendars, schedule data and organizational process assets. |
Question 37 Explanation:
Project management plan, project schedule, work performance data, project calendars, schedule data, and organizational process assets are inputs to Control Schedule process.
[PMBOK. Project Time Management, Control Schedule]
Question 38 |
How time management processes interact with other project processes?
A | Can be used with different processes and overlap each other. |
B | Can be used only with planning process group during process initiation. |
C | Can be used in different sequence without overlap of each other. |
D | Cannot overlap each other, but used one after another with planning processes only. |
Question 38 Explanation:
Time management processes can be used with different processes and overlap each other during the course of the project.
[PMBOK. Project Time Management.]
Question 39 |
How does the Finish-to-Start (FS) relations work?
A | The activity must finish before the next activity can start. |
B | The activity cannot finish before the next activity start. |
C | The activity must finish before the next predecessor can start. |
D | The activity cannot start before the next activity can finish. |
Question 39 Explanation:
Finish-to-star relations prescribes that the activity must finish before the next activity can start.
Question 40 |
What is the most common method of network diagramming used these days?
A | Dependency determination. |
B | Precedence diagramming method (PDM) or Activity-on-Node (AON). |
C | Graphic evaluation and review technique (GERT). |
D | Arrow diagramming method (ADM). |
Question 40 Explanation:
Precedence diagramming method (PDM) or Activity-on-Node (AON) is the right answer.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 41 |
Which graphical form of schedule preferably use during presentation to senior management?
A | Project schedule network diagram. |
B | Bar chart. |
C | Affinity diagram. |
D | Milestone chart. |
Question 41 Explanation:
Milestone chart graphically presents only major start and end dates, which usually used for reporting to senior management.
Bar chart is handful for graphically presenting progress of the project activities while discussing with the team.
Project schedule network diagram shows time-scaled logical relations between activities.
[1 - 6.5.3 Develop Schedule: Outputs]
Question 42 |
How detailed the project schedule should be?
A | Whether highly detailed or broadly framed, depending on needs of the project. |
B | All activities need to be scheduled and provide high level of details to ensure that project is tractable. |
C | Highly detailed to ensure that all dates for activities and milestones are determined. |
D | Only major activities need to be scheduled and provide high level of details. |
Question 42 Explanation:
Project schedule can be documented with using very detailed information about time or include only mile stones; the level of required details is depending on needs of the project and include appropriate realistic thresholds.
[1 - 6 Project Time Management]
Question 43 |
A project team supports project manager with information to sequence activities. What information is needed to complete the work?
A | All choices are right. |
B | List of activities and their attributes. |
C | Milestones. |
D | Organizational process assets. |
Question 43 Explanation:
to complete sequence activities process project manager needs List of Activities, Activities Attributes, Milestones, and Organizational Process Assets.
[1 - 6 Project Time Management]
Question 44 |
What part of organizational process assets can help in improving estimates?
A | Templates. |
B | Historical information. |
C | Industry standards. |
D | Processes. |
Question 44 Explanation:
Historical information is a valuable resource of organizational process assets for estimating, based on experiences on previous projects.
Question 45 |
What type of dependency called hard logic?
A | External dependency. |
B | Discretionary dependency. |
C | Mandatory dependency. |
D | Preferred dependency. |
Question 45 Explanation:
Mandatory dependency in other words called hard logic and represent the unavoidable dependency from the elated activity. For example, an activity that must be done as per law requirement or corporate SDLC standard.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 46 |
How often time management processes can be used during the course of the project?
A | Time management processes to be used during project initiation and its planning phase. |
B | Only selected time management processes to be selected depending on project needs. |
C | At least ones on the project and project phase, if the project is divided to phases. |
D | All time management processes to be used through the course of the project. |
Question 46 Explanation:
Actually, the question is how often a project manager and project team are concern about project schedule - ideally, at least ones on the project and project phase. In reality, time management processes are used quite often in combination with other processes. For example, a number of processes, including time, will be used in managing change requests and controlling schedule during the course of the project.
[PMBOK. Project Time Management]
Question 47 |
What are the objectives of schedule compression?
A | Optimize schedule to meet project or milestone deadline without changing project scope. |
B | Prove the request for using contingency reserve. |
C | Optimize schedule to meet project or milestone deadline. |
D | Prove the request for using management reserve. |
Question 47 Explanation:
Optimize schedule to meet project or milestone deadline without changing project scope.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 48 |
Baselines for scope, cost, and time should not be changed unless _____?
A | Approved change. |
B | Functional manager's request. |
C | Sponsors request. |
D | Stakeholders request. |
Question 48 Explanation:
Baselines for scope, cost, and time should not be changed unless the change is approved?
Question 49 |
What needs to be done after a schedule baseline of the project is developed?
A | Approved by a project management team. |
B | Develop schedule. |
C | Approved by customer. |
D | Develop network diagram. |
Question 49 Explanation:
Schedule baseline needs to be accepted and approved by a project management team including both baselines for start and finish dates. The schedule baseline is a part of project management plan.
[1 - 6.5.3 Develop Schedule: Outputs]
Question 50 |
What tools and techniques to be used for effective estimate activity duration?
A | Decomposition, rolling wave planning, analogous, parametric, three point estimates, and reserve analysis. |
B | Expert judgement, peer review, Delphi method, five point estimates, and reverse analysis. |
C | All choices are right. |
D | Expert judgement, analogous, parametric, three point estimates, and reserve analysis. |
Question 50 Explanation:
Expert judgement, analogous, parametric, three point estimates, and reserve analysis are tools and techniques that used for Estimate Activity Duration.
Question 51 |
What information is required to develop project schedule?
A | Outputs from processes to define and sequence activities, estimate activity resources, and estimate activity duration. |
B | List of requirements, work breakdown structure, and estimate activity resources. |
C | Project scope, finalized requirements, sequence activities, estimate activity resources, and estimate activity duration. |
D | Project charter, List of requirements, work breakdown structure, estimate activity resources, and estimate activity duration. |
Question 51 Explanation:
Outputs from processes to define and sequence activities, estimate activity resources, and estimate activity duration are needed to develop project schedule.
[1 - 6 Project Time Management]
Question 52 |
A new project manager just joint a company and wonders what scheduling tool to be used. What is the best place to find this information?
A | PMO. |
B | Technical department. |
C | Ask other project managers. |
D | Enterprise environment factors. |
Question 52 Explanation:
Scheduling tool that used in the company is usually listed in the enterprise environment factors that need to be obtained in the project initiation.
[1 - 6 Project Time Management]
Question 53 |
What process approves or rejects changes?
A | Integrated change management system. |
B | Configuration management process. |
C | Integrated change control. |
D | Change management plan. |
Question 53 Explanation:
Integrated change control process approvals or rejects for changes.
Question 54 |
How many types of logical relations the precedence diagramming method has?
A | Two. |
B | Six. |
C | Four. |
D | Eight. |
Question 54 Explanation:
Precedence diagramming method has four logical types of relations between nodes: finish-to-start, finish-to-finish, start-to-start, start-to-finish.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 55 |
What information from similar previous projects usually used with analogous estimating method?
A | Duration, budget, size, weight, and complexity. |
B | Costs, budget, time, resource requirements, and organizational assets. |
C | Duration, quality, risks, efforts, and complexity. |
D | Efforts, costs, location, and customer satisfaction. |
Question 55 Explanation:
Duration, quality, risks, efforts, and complexity - these parameters usually used for analogous estimation (top-down).
[1 - 6.4.2. Estimate Activity Duration: Tools and Techniques]
Question 56 |
What process is planning the scheduling methodology applied to the project?
A | Develop project charter. |
B | Develop time constrains and assumptions. |
C | Develop project management plan. |
D | Develop procurement plan. |
Question 56 Explanation:
Develop project management plan that produces a schedule management plan is the process that defines project scheduling methodology to be used during the course of the project.
[1 - 6 Project Time Management]
Question 57 |
What you should concern about when an earlier planned activity has been discarded for the purpose of schedule compression?
A | Resource availability. |
B | Time. |
C | Cost. |
D | Scope. |
Question 57 Explanation:
You should concern about Scope, when an earlier planned activity has been cancelled for the purpose of schedule compression. In addition, while this may save time and cost, it possible impacts customer satisfaction.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 58 |
What rules are used in heuristic technique?
A | General of luck. |
B | Rule of thumb. |
C | Law Murphy. |
D | God's wish. |
Question 58 Explanation:
Rule of thumb is a heuristic technique. An example is rule 80/20, which states that 80% of problems come from 20% of sources. Another example... 10 per cent of project time should be allocated to project closing. Such parametric estimation may become heuristic.
Question 59 |
How the output of estimate activity duration forms?
A | All activities on the project can be assign with the same period of time as long as the activity takes less than one week. |
B | Activity duration can be identified buy taking a guess and double it to ensure the activity will be completed. |
C | Activity duration can be identified as a firm quantitative period. |
D | Activity duration can be identified as a firm quantitative period, as well as a period with added probability. |
Question 59 Explanation:
Activity duration can be identified as a firm quantitative period, as well as a period with added probability.
[1 - 6.4.3 Estimate Activity Duration: Outputs]
Question 60 |
After coordinating of the activity list, a project manager estimates activity resources. What he needs to complete the work?
A | Resources breakdown structure. |
B | Activity resources requirements. |
C | Project document updates. |
D | Activity attributes. |
Question 60 Explanation:
The Activity Attributes are missing along with resource calendars, enterprise environment factors and organizational process assets. All other choices are deliverables of the same process of Estimate Activity Resources.
[1 - 6.3 Estimate Activity Resources]
Question 61 |
What of the following should be used as a base for accurate estimation?
A | Requirements documentation. |
B | Project scope. |
C | Project charter. |
D | Work breakdown structure. |
Question 61 Explanation:
Work breakdown structure should be used as a base for effective and accurate estimation.
Question 62 |
What does duration critical path identify?
A | Longest duration path defines longest time to complete project. |
B | Longest duration path defines shortest time to complete project. |
C | Longest duration path defines longest time to complete project. |
D | Shortest duration path defines shortest time to complete project. |
Question 62 Explanation:
Longest duration path defines shortest time to complete project.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 63 |
A project manager performs define activity process. What information this process delivers?
A | Description of project activities listed in ascending order. |
B | Identified specific actions and their details to reach planned quality of project deliverables. |
C | Identified specific actions and their details to produce project deliverables. |
D | A list of specified activities for implementing change using integrated change control system. |
Question 63 Explanation:
Define activities identifies specific actions and their details to produce project deliverables.
[1 - 6.1 Project Time Management: Define Activities]
Question 64 |
What type of diagram is created as the result of regression analysis in parametric estimation?
A | Network diagram. |
B | Affinity diagram. |
C | Learning curve. |
D | Scatter diagram. |
Question 64 Explanation:
Scatter diagram is created in parametric estimation where the time measures per action component like per line of code, per meter, or per setup, etc. Learning Curve is another parametric method that states the following similar activity should take less time than previous because of obtained more experience, improved skills and techniques.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques]
Question 65 |
What documents to be delivered by define activities process?
A | Activity list, milestone list, and activity resource requirements. |
B | Activity list, milestone list, and project schedule. |
C | All choices are right. |
D | Activity list, activity attributes, and milestone list. |
Question 65 Explanation:
Activity list, activity attributes, and milestone list are deliverables of define activities process.
[1 - 6 Project Time Management]
Question 66 |
What method is used to avoid not linear (up-and-down) use of resources?
A | Resource leveling. |
B | Calendar stabilizing. |
C | Economic model. |
D | Activity crashing. |
Question 66 Explanation:
Resource leveling technique is used to stabilize use of resources. The longer project duration is an option to stabilize usage of resources on the project, instead hiring resources for shorter periods, releasing them and hiring back, when needed. This also may save cost of procurement and reduce risk for spending extra effort for training and/or knowledge transfer.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 67 |
What tools and techniques project manager should use to develop schedule effectively?
A | Resource leveling, what-if scenario analysis, applying leads and lags. |
B | Schedule compression and scheduling tool. |
C | All choices are right. |
D | Schedule network analysis, critical path method, critical chain method. |
Question 67 Explanation:
All choices are right, as all the listed tools and techniques are needed to develop schedule effectively.
Question 68 |
How to find project duration using PERT?
A | Sum of PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances. |
B | PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances. |
C | Sum of PERT estimates of all activities, plus or minus square root of the sum of active variances. |
D | PERT estimate for each activity, plus or minus square root of the sum of active variances. |
Question 68 Explanation:
Sum of PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances is a formula for calculate estimate of project duration.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 69 |
What method is used to avoid not linear (up-and-down) use of resources?
A | Activity crashing. |
B | Calendar stabilizing. |
C | Economic model. |
D | Resource leveling. |
Question 69 Explanation:
Resource leveling technique is used to stabilize use of resources. The longer project duration is an option to stabilize usage of resources on the project, instead hiring resources for shorter periods, releasing them and hiring back, when needed. This also may save cost of procurement and reduce risk for spending extra effort for training and/or knowledge transfer.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 70 |
By completion of estimate duration activity project manager has to update project document with _____?
A | Activity duration estimate. |
B | Activity duration estimate and schedule baseline. |
C | Work performance measurements, activity duration estimate. |
D | Project schedule, activity duration estimate. |
Question 70 Explanation:
By completion of estimate duration activity project manager has to update project document with Activity Duration Estimate.
[1 - 6 Project Time Management]
Question 71 |
What information needs to be updated that resulted by control schedule process?
A | Work performance measurements. |
B | Project management plan and change requests. |
C | All choices are right. |
D | Organizational process assets. |
Question 71 Explanation:
All choices are right. All listed here information needs to be updated when Control Schedule is completed.
[1 - 6 Project Time Management]
Question 72 |
How much float critical paths usually has?
A | Maximum one. |
B | Maximum two. |
C | Zero. |
D | One. |
Question 72 Explanation:
Usually critical paths does not have floats (slacks).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 73 |
To estimate duration of a work package, after discussion with a team, a project manager decided to use the average number of hours spent on similar work in previous projects. What method the project manager used?
A | Parametric estimating. |
B | Analogous estimating. |
C | Three-point estimates. |
D | Expert judgement. |
Question 73 Explanation:
Two signs refer here to Parametric Estimating. Statistical information from previous projects, and especially number of hours per work. The analogous estimating would be the choice if the details of the work would be comparing, such as duration, complexity, etc. Analogous Estimating are usually top-down; although, can be the high-level and definitive. Other choices also related to the tool and techniques for Estimate Activity Duration, but not a suitable choice here.
[1 - 6.4.2 Estimate Activity Duration: Tools and
Techniques]
Question 74 |
How the contingency plan is different from management reserve?
A | Contingency reserve is calculating to compensate unknown unknowns schedule uncertainty for specific part of the project. |
B | Contingency reserve is calculating to compensate schedule uncertainty for specific part of the project. |
C | Contingency reserve is calculating to compensate schedule uncertainty for overall project, and can determine the schedule tolerance. |
D | Contingency reserve is calculating to compensate schedule uncertainty for overall project, and determined as firm as additional time to be spent for planned changes. |
Question 74 Explanation:
Contingency reserve is calculating to compensate schedule uncertainty for overall project, and can determine the schedule tolerance.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .5 Reserve Analysis]. Contingency reserve discussed mo in Cost Management Chapter.
Question 75 |
What information the network diagram adds for develop schedule process?
A | Detailed description of work to be done. |
B | Description of work packages to be done. |
C | Duration of each activity. |
D | The sequence of work will be processed. |
Question 75 Explanation:
Network diagram provides the sequence of work will be processed for the develop schedule process.
[1 - 6.5 Develop Schedule]
Question 76 |
What relation between create work breakdown structure and define activities processes?
A | Work breakdown structure identifies the methods how the to be executed, while define activities process identifies the activities to deliver those packages. |
B | Work breakdown structure describes the way how to deliver the project results, while define activities process identifies the activities to deliver those packages. |
C | Work breakdown structure identifies the deliverables at their lowest level, which called packages, while define activities process decomposes work packages into smaller components identified as activities to deliver those packages. |
D | Work breakdown structure proved a sequence of activities, while define activities process identifies the activities to deliver those packages. |
Question 76 Explanation:
Work breakdown structure identifies the deliverables at their lowest level, which called packages, while define activities process decomposes work packages into smaller components identified as activities to deliver those packages. Other choices are made up.
[1 - 6.1 Project Time Management: Define Activities]
Question 77 |
How does the Start-to-Finish (SF) relations work?
A | The finish of successor depends on start of predecessor. |
B | The start of successor depends on start of predecessor. |
C | The start of successor depends on start of predecessor. |
D | The completion of predecessor depends on completion of successor. |
Question 77 Explanation:
The finish of successor depends on start of predecessor. In other words, the start of activity will allow to finish the next related activity.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 78 |
Which of the methods refers to progressive elaboration planning?
A | Waterfall. |
B | Rolling wave. |
C | Bottom-up estimation. |
D | Precedence diagramming. |
Question 78 Explanation:
Rolling wave is the method of progressing elaboration planning.
[1 - 6.1.1 Define Activities: Input]
Question 79 |
What range of the estimate for an activity with expected duration at least 10 days, the worse 18 days, but more likely 15 days to complete?
A | 14,0
+/- 1.33 |
B | 14.67
+/- 1.33 |
C | 5.97
+/- 1.23 |
D | 15.97
+/- 1.78 |
Question 79 Explanation:
PERT uses the following formulas and calculations...
Expected Activity Duration
(P+4M+O) / 6 = (18+4*15+10) / 6 = 14.666;
Activity Standard Deviation
P-O / 6 = 18-10 / 6 = 1.333;
Activity Variance
(P-O)**2 / 6 = 1.777 (wasn't asked in this question)
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 80 |
A project manager estimates duration of an activity with a team member. After discussions, they found that an activity with similar complexity and business requirements, was performed on previous project. So they planned the same amount of time for the activity on their project. What method was used?
A | Parametric estimating. |
B | Three-point estimates. |
C | Analogous estimating. |
D | Expert judgement. |
Question 80 Explanation:
Analogous Estimating are usually top-down; although, can be the high-level and definitive. In this situation, the details of the activity were compared, such as complexity, functionality, etc. The Parametric Estimating would be the choice if statistical information from previous projects, as number of time units would be used. Other choices also related to the tool and techniques for Estimate Activity Duration, but not a suitable choice here.
[1 - 6.4.2 Estimate Activity Duration: Tools and
Techniques]
Question 81 |
What technique applies with three-point estimation?
A | Wave based estimation technique. |
B | Exponential smoothing technique. |
C | Moving average estimate. |
D | Program evaluation and review technique. |
Question 81 Explanation:
Program Evaluation and Review Technique (PERT) is applied with Three_Point Estimate technique.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 82 |
Project manager should periodically _____ to make sure that adequate time and funds available to complete the project.
A | Discuss the possible risks. |
B | Recalculate estimate to complete. |
C | Run team performance report. |
D | Review plans. |
Question 82 Explanation:
Project manager should periodically recalculate estimate to complete (ETC) to make sure that adequate time and funds available to complete the project.
Question 83 |
What criteria need to be met for successful crashing selected activities of a project for the purpose of schedule compression?
A | Risks and budget. |
B | Risks and resources. |
C | Resources and budget. |
D | Quality and resources. |
Question 83 Explanation:
Resources and budget are two major concerns when crashing activities of the project for schedule compressing. Crashing always increases costs, whether by adding more resources, more experienced (means more expensive) resources, or purchasing more advanced tools. In addition, more management time may require to manage Crashing.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 84 |
What is the role o project manager in estimation process?
A | All choices are right. |
B | Verify is the provided estimation is realistic and avoid padding. |
C | Define reserve and document the assumption made during estimation. |
D | Provide the team with enough information and required level of accuracy to provide proper estimation. |
Question 84 Explanation:
All choices are right, that's what project manager is entitled to do during estimation process.
Question 85 |
What effect you need to expect when selected method of schedule compression is cut time?
A | Reduced scope. |
B | Reduced quality. |
C | Increased risks. |
D | Increased costs. |
Question 85 Explanation:
Cut time as a choice of schedule compression usually leads to reduced quality standards.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 86 |
Activity-on-the-node is the method of _____.
A | Constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. In other words, this called precedence diagramming method. |
B | Constructing a visual diagram that uses nodes to indicate logically related requirements. In other words, this called relational arrowing method. |
C | Constructing a visual diagram that uses nodes to indicate logically related requirements and risks on the project. In other words, this called bottom-up estimation. |
D | Constructing a visual diagram that uses nodes to indicate logically related communications between project members and stakeholders. In other words, this called rolling wave planning. |
Question 86 Explanation:
Activity-on-the-node is the method of constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. In other words, this called precedence diagramming method.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 87 |
What tools and techniques project manager uses to define activities?
A | Rolling wave planning. |
B | Templates and expert judgement. |
C | All choices are right. |
D | Decomposition. |
Question 87 Explanation:
All choices are right. Project manager uses Decomposition, Rolling Wave Planning, Templates and Expert Judgement while Defining Activities.
[1 - 6 Project Time Management]
Question 88 |
When control schedule is used?
A | As the project activities are being completed. |
B | As the project activities are being performed. |
C | As the project activities have generated a change request. |
D | As the project activities are being rejected. |
Question 88 Explanation:
Control Schedule process is used when the project activities are being performed to ensure completion of work on planned schedule.
[1 - 6 Project Time Management]
Question 89 |
What information the activity attributes provide?
A | Activity attributes provide more details for each of multiple components associated with each activity. |
B | Activity attributes provide description of the pack in whole. |
C | Activity attributes provide list of components to be implemented with each package. |
D | Activity attributes provide details for each work package . |
Question 89 Explanation:
Activity attributes provide more details for each of multiple components associated with each activity.
[1 - 6.1.3 Define Activities: Output]
Question 90 |
What technique an be used for schedule network analysis?
A | All choices are right. |
B | What-if scenario analysis. |
C | Critical path and schedule compression. |
D | Resources leveling and critical chain method. |
Question 90 Explanation:
All these techniques are applicable to calculate the early and late start, and finish dates for the project activities.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 91 |
A project manager has finalized scope baseline and started to define activities using company's templates and procedures. What is missing to complete the work?
A | Organizational process assets. |
B | Requirements documentation. |
C | Activity list. |
D | Enterprise environmental factors. |
Question 91 Explanation:
Scope Baseline, Organizational Process Assets, and Enterprise Environment Factors are the input to Define Activities process.
[1 - 6 Project Time Management]
Question 92 |
What tools and techniques to be used by project manager while estimating activity resources?
A | Expert judgement and alternative analysis. |
B | Published estimation data and bottom-up estimation. |
C | All choices are right. |
D | Project management software. |
Question 92 Explanation:
All choices are right. Expert judgement and alternative analysis, published estimation data, bottom-up estimation, and project management software are tolls and techniques used in estimate activity resources.
[1 - 6 Project Time Management]
Question 93 |
A project manager performs define activity process. What information this process delivers?
A | A list of specified activities for implementing change using integrated change control system. |
B | Description of project activities listed in ascending order. |
C | Identified specific actions and their details to produce a realistic project schedule. |
D | Identified specific actions and their details to produce project deliverables. |
Question 93 Explanation:
Define activities identifies specific actions and their details to produce project deliverables.
[PMBOK. Project Time Management: Define Activities]
Question 94 |
What can be used to support realistic schedule?
A | Crashing the schedule is the method for realistic planning of schedule. |
B | Lead and lags time between activities can be used to support realistic schedule. |
C | De-scoping is the method to sequence the project activities for realistic schedule. |
D | Lead and lags time usually used to leverage the schedule. |
Question 94 Explanation:
Lead and lags time between activities can be used to support realistic schedule.
[1 - 6.2 Sequence Activities]
Question 95 |
Project manager starts to develop schedule. What documents needs to be completed for this work?
A | Activity resource requirements, resource calendars, activity duration estimate. |
B | All choices are right. |
C | Activity list, activity attributes, project schedule diagram. |
D | Enterprise environmental factors and Organizational process assets. |
Question 95 Explanation:
All choices are right. All the listed documents are needed to develop schedule.
[1 - 6 Project Time Management]
Question 96 |
What tools and techniques project manager uses to control schedule?
A | All choices are right. |
B | Resource leveling, what-if scenario analysis. |
C | Performance reviews, variance analysis, project management software. |
D | Adjusting leads and lags, schedule compression, scheduling tool. |
Question 96 Explanation:
All choices are right; all listed tools and techniques are used to Control Schedule.
[1 - 6 Project Time Management]
Question 97 |
Baselines for scope, cost, and time should not be changed unless _____?
A | Stakeholders request. |
B | Approved change. |
C | Sponsors request. |
D | Functional manager's request. |
Question 97 Explanation:
Baselines for scope, cost, and time should not be changed unless the change is approved?
Question 98 |
What can be used to show the interdependency between activities through the whole project?
A | List of activities. |
B | Network diagram. |
C | Project scope statement. |
D | Work breakdown structure. |
Question 98 Explanation:
Network diagram shows interdependency of the activities through the whole project.
[1 - 6.2 Sequence Activities]
Question 99 |
A project team agreed with project schedule network diagram after _____?
A | Received sponsor's approval. |
B | Project document was updated. |
C | Stakeholders determined project constrains. |
D | Estimating activity resources was completed. |
Question 99 Explanation:
Project schedule network diagram and updated project document are results of sequence activities process.
[PMBOK. Project Time Management.]
Question 100 |
From which process output the define activities process receives scope baseline?
A | Project scope statement. |
B | Work breakdown structure. |
C | Develop activity list. |
D | Develop scope management plan. |
Question 100 Explanation:
Scope baseline is one of the results of create work breakdown structure process.
[1 - 6.1.1 Define Activities: Input]
Question 101 |
What criteria to be used in the decision of which activity or activities to crash for the purpose of schedule compression?
A | Longest time. |
B | Shortest time. |
C | Higher cost. |
D | Lowest cost. |
Question 101 Explanation:
The crash the activity or activities with lowest cost to be selected for the purpose of schedule compression.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 102 |
What information to be updated at the end of estimate activity resources?
A | Activity resources requirements, resource breakdown structure, and project schedule. |
B | Activity resources requirements and work breakdown structure. |
C | Activity resources requirements and resource breakdown structure. |
D | All choices are right. |
Question 102 Explanation:
Activity resources requirements, resource breakdown structure, and update project document are results of Estimate Activity Resources.
[1 - 6 Project Time Management]
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 102 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
| 1 | 2 | 3 | 4 | 5 |
| 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 |
| 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 |
| 31 | 32 | 33 | 34 | 35 |
| 36 | 37 | 38 | 39 | 40 |
| 41 | 42 | 43 | 44 | 45 |
| 46 | 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 | 55 |
| 56 | 57 | 58 | 59 | 60 |
| 61 | 62 | 63 | 64 | 65 |
| 66 | 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| 76 | 77 | 78 | 79 | 80 |
| 81 | 82 | 83 | 84 | 85 |
| 86 | 87 | 88 | 89 | 90 |
| 91 | 92 | 93 | 94 | 95 |
| 96 | 97 | 98 | 99 | 100 |
| 101 | 102 | End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!