Development of this quiz is in progress.
PM - Scope Management
Start
Congratulations - you have completed PM - Scope Management.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
A project manager is going to meet with customer to obtain acceptance of the deliverable. What needs to be done first?
A | Perform audit. |
B | Perform quality control process to validate deliverable against scope. |
C | Control scope. |
D | Complete validation of the requirements. |
Question 1 Explanation:
Perform quality control process to validate deliverable against scope means verify scope - that what needs to be done prior meeting with customer to obtain deliverable acceptance.
[1 - 5.4 Verify Scope]
Question 2 |
What needs to be done to ensure that project management plan is realistic?
A | Proceed through iterations during planning process group and update all project document while new information become available. |
B | Use the configuration management to ensure that project documentation is constantly updated. |
C | Use appropriate change management process to ensure that all project documentation is updated. |
D | Updating project all documentation after each process in planning process group is completed. |
Question 2 Explanation:
Proceed through iterations during planning process group and update all project document while new information become available.
[1 - 5.2. Define Scope]
Question 3 |
What is the project scope management?
A | A set of processes to ensure successful completion of all the required work on the project. |
B | A list of assumptions and constrains that limit the project work. |
C | A set of documents and processes to ensure that all the requirements that provided by stakeholders are implemented. |
D | A list of activities to be done during the project. |
Question 3 Explanation:
Project Scope Management is a set of processes to ensure that the project includes all and only the required work, for successful completion of the project.
[1 - 5 Project Scope Management]
Question 4 |
What benefits creates the numbering of work breakdown structure?
A | Estimate the duration of project activities. |
B | Sequentially structure the list of work packages. |
C | Determine dependencies. |
D | Identify the item and its level of decomposition. |
Question 4 Explanation:
Numbering items in WBS helps identifying the item and its level of decomposition.
Question 5 |
How the work breakdown structure shows dependencies?
A | In project plan. |
B | In project schedule. |
C | Does not show dependencies. |
D | In work breakdown structure dictionary. |
Question 5 Explanation:
WBS does not show dependencies. Other choices are not related to the matter of specified here question.
[1 - 5.3 Create WBS]
Question 6 |
What process is formalizing acceptance of the completed project deliverables?
A | Verifying assumptions and constrains. |
B | Verify scope. |
C | Verification with scope baseline. |
D | Confirmation of work against requirements. |
Question 6 Explanation:
Verify scope is process that formalizes acceptance of the completed project deliverable.
[1 - 5.4 Verify Scope]
Question 7 |
A project team has completed collecting requirements. What should be done next?
A | Define resource requirements and project schedule. |
B | Create work breakdown structure and work breakdown structure dictionary. |
C | Define activity. |
D | Define scope. |
Question 7 Explanation:
Define scope is following after the requirements are finalized and confirmed.
[1 - 5.2 Define Scope]
Question 8 |
How the verify scope process serves a project manager?
A | Ease evaluation of a project status. |
B | Ease to create a work breakdown structure. |
C | Ease measure a project performance. |
D | Ease preparation for getting acceptance of a deliverable. |
Question 8 Explanation:
Verify Scope eases preparation for acceptance of a deliverable. The output of Verify Scope process are actually accepted deliverables and/or change requests, along with update of project documentation, indicating completion or required change.
[1 - 5.4 Verify Scope]
Question 9 |
What needs to be done if neither project manager or project team cannot solve competing stakeholders' interests?
A | Ask for sponsor's support. |
B | Escalate to management. |
C | Use Delphi technique. |
D | Reject all competing requirements. |
Question 9 Explanation:
The question asks about a situation when all acceptable methods have been used, and only management can resolve a dispute.
[1 - 5. Collect Requirements]
Question 10 |
What output delivers define scope process?
A | Project scope statement and list of requirements. |
B | Project scope and project statement of work. |
C | Project scope statement and project document update. |
D | Project scope statement, and work breakdown structure, and work breakdown structure dictionary. |
Question 10 Explanation:
Project scope statement and project document update are output of define scope process.
Question 11 |
Which process delivers requirements traceability matrix?
A | Develop project traceability plan. |
B | Determine how to control requirements management plan. |
C | Develop project cost management plan. |
D | Collect project requirements. |
Question 11 Explanation:
Requirements traceability matrix is one of the outputs of collect project requirements process.
[1 - 5.1 Collect Requirements]
Question 12 |
What input project manager uses while collects requirements?
A | Business case and project charter. |
B | List of stakeholders and initial requirements. |
C | Project chanter and WBS. |
D | Project charter and stakeholder register. |
Question 12 Explanation:
Project charter and stakeholder register are two documents are required for effectively collect requirements. The initial requirements and business case may not include enough information; some initial requirements or wishes may not be confirmed by project charter. The project stakeholders register will help to identify the right sources for the project or product requirements and their details.
[1 - 5.1.1 Collect Requirements: Input]
Question 13 |
What is primary objection of project scope management?
A | Describes the time, cost and quality constrains of the project. |
B | Defining and controlling what should be included and what should not in the project. |
C | Providing a list of constrains as a part of the project management plan. |
D | Determines the project structure, and management methodology applied to the project. |
Question 13 Explanation:
Project scope management defines and controls what should be included and what should not in the project.
[1 - 5 Project Scope Management]
Question 14 |
How detailed work breakdown structure should be?
A | The level of decomposition should provide enough information that project team could reach project objectives. |
B | The level of decomposition should provide enough information to keep project on schedule. |
C | The level of decomposition should as detailed as possible so the project deliverables could reach customers' satisfaction. |
D | The level of decomposition should provide enough for creating activities list and estimate resource requirements. |
Question 14 Explanation:
The level of decomposition should provide enough information that project team could reach project objectives.
[1 - 5.3 Create WBS]
Question 15 |
What activities include while using inspection for verifying scope?
A | Measuring, examining, and verifying to find if work and deliverables have met the requirements, and other acceptance criteria. |
B | Measuring, examining, and verifying to find if work and deliverables have completed in line with assumptions and constrains. |
C | Measuring, examining, and verifying to find if work and deliverables have met the required quality. |
D | Monitoring the work execution to be sure it its deliverables have met the requirements, and other acceptance criteria. |
Question 15 Explanation:
Measuring, examining, and verifying to find if work and deliverables have met the requirements, and other acceptance criteria is done by inspection of project work deliverables while verifying scope.
[1 - 5.4 Verify Scope]
Question 16 |
What of the following organizational process assets to be used in the process define scope?
A | All choices are right. |
B | Lessons learned, historical information from previous projects and phases. |
C | Templates, standards, subject matter documentation. |
D | Policies procedures processes. |
Question 16 Explanation:
All choices are right. All subject matter documentation, processes, templates and historical information can be valuable while defining project scope.
[1 - 5.2.1.3 Define Scope: Input. Organizational Process Assets]
Question 17 |
What input requires to create work breakdown structure?
A | Project scope statement, list of requirements and organizational process assets. |
B | Project scope statement, requirements documentation and enterprise environmental factors. |
C | Project scope statement, requirements documentation and organizational process assets. |
D | All choices are right. |
Question 17 Explanation:
Project scope statement, requirements documentation and organizational process assets is the right answer.
[1 - 5.3 Create WBS]
Question 18 |
What attributes of the requirements need to be documented?
A | ID, description, targeted objectives, source, initiator. |
B | As much as required to reach project objectives. |
C | ID, description, targeted objectives, source, initiator, date, log of changes. |
D | ID, description, targeted objectives, source. |
Question 18 Explanation:
Project manager and project team need to determine the level of details required for documenting requirements, which may be different for different requirements. All answers are right, while reaching the project objective if the primary target.
Question 19 |
A project manager called a meeting for _____ to clarify requirements related to specific knowledge areas.
A | Project team. |
B | Users group. |
C | Focus group. |
D | Stakeholders group. |
Question 19 Explanation:
Focus group of subject matter experts helps to address specific knowledge areas as issues on the project, including but limited to requirements, technical or business, issues, etc.
[1 - 5.1.2 Collect Requirements: Tool and Techniques]
Question 20 |
What kind of product analysis would be right to provide while defining project scope?
A | All choices are right. |
B | Requirements analysis, system engineering. |
C | Product breakdown and system analysis. |
D | Value engineering, and value analysis. |
Question 20 Explanation:
All choices but not limited to the listed are right depending on application area and type of deliverable, whether a product, process, service or other.
[1 - 5.2 Define Scope: Tools and Techniques]
Question 21 |
What of the following should be done after the project scope is defined?
A | Coordinate with stakeholders. |
B | Reach bought-in by a team. |
C | Coordinate with PMO. |
D | Gain formal approval. |
Question 21 Explanation:
After a scope is defined if must be formally approved before work starts. Other choices to be done before final approval of the project scope.
[1 - 5 Project Scope Management]
Question 22 |
What documents should be updated when project scope statement is complete?
A | Project charter, requirements documentation, and requirements traceability matrix. |
B | Stakeholder register, requirements documentation, and work breakdown structure. |
C | Requirements documentation, requirements traceability matrix. |
D | Stakeholder register, requirements documentation, and requirements traceability matrix. |
Question 22 Explanation:
Stakeholder register, requirements documentation, and requirements traceability matrix must be updated so other team members and stakeholders would use project scope statement in other planning processes.
[1 - 5.2.3 Define Scope: Outputs]
Question 23 |
What information is used for preparation a detailed project scope statement?
A | Product requirements, assumptions, constrains, and project risks that are documented during project initiation. |
B | Project requirements and project risks that are documented during project initiation and described in project statement of work. |
C | Description of major project deliverables, assumptions, and constrains that are documented during project initiation. |
D | Definition of major project deliverables, initial requirements, assumptions, and constrains provided in project charter. |
Question 23 Explanation:
Description of major project deliverables, assumptions, and constrains that are documented during project initiation.
[1 - 5.2 Define Scope]
Question 24 |
A project manager collects requirements using _____.
A | Delhi techniques. |
B | Pareto diagram. |
C | Fish-bone analysis. |
D | Benefit / cost analysis. |
Question 24 Explanation:
Delhi technique is used with a selected group of experts, who provide their feedback on distributed questionnaires through the rounds until a consensus is reached. The facilitator keeps expert's feedback anonymously.
[1 - 5.1.2 Collect Requirements: Tool and Techniques]
Question 25 |
A project manager and project team members are interviewing stakeholders and creating _____.
A | Requirements documentation. |
B | Requirements changes process. |
C | Project scope status. |
D | Project plan. |
Question 25 Explanation:
Interviewing stakeholders is one of collect requirements techniques that delivers requirements documentation.
[1 - 5.1.2 Collect Requirements: Tool and Techniques]
Question 26 |
How alternative identification can be used in define scope process?
A | Indexing project deliverables before archiving. |
B | Defining an alternative product or service and a project deliverable. |
C | Defining different approaches to execute and perform the project work. |
D | Identifying a backup plan if the project deliverable won't satisfy stakeholders' expectations. |
Question 26 Explanation:
Defining different approaches to execute and perform the project work is the right choice for to achieving effective result. A variety of general methods can be applied, such as focus groups, workshops, brainstorming, pair wise comparison, literal thinking.
[1 - 5.2 Define Scope: Tools and Techniques]
Question 27 |
What should a project manager do if competing requirements were identified?
A | Accept and execute. |
B | Negotiate with stakeholders. |
C | Escalate to sponsor. |
D | Generate change request. |
Question 27 Explanation:
Competing requirements need to negotiate back to stakeholders. Project team and project manager need to analyze the influence of competitive requirements, and offer options, like adjust the requirements, change priorities, implement in later releases, initiate a separate project, or drop at all.
[1 - 5. Collect Requirements]
Question 28 |
What may be affected by changing project scope?
A | Time, cost, communications, risk, quality. |
B | Time, cost, risk, quality, customer satisfaction. |
C | Time, cost, risk, quality, procurement. |
D | Time, cost, risk, quality, communications, resources, customer satisfaction. |
Question 28 Explanation:
Time, cost, risk, quality, and customer satisfaction may be effected by change in project scope. These areas of project management should be evaluated against change.
[1 - 5 Project Scope Management]
Question 29 |
A project manager is going to meet with customer to obtain acceptance of the deliverable. What of the following information may be needed for that meeting?
A | Risk management plan and project charter. |
B | Requirements management plan and communication plan. |
C | Scope management plan and change management plan. |
D | Project management plan and scope baseline. |
Question 29 Explanation:
Project management plan and scope baseline are the documents to be present during meeting with customer while discussing acceptance of the deliverable.
[1 - 5.4 Verify Scope]
Question 30 |
How control scope process is used while managing changes?
A | Ensures all corrective and preventive actions have been process through perform integrated change control process. |
B | Measuring performance of the implemented changes in the scope base line. |
C | Ensure all requested changes have been approved through the perform integrated control process. |
D | Monitors whether preventive, corrective actions or defect repair have been taken when change request is approved. |
Question 30 Explanation:
Control scope ensures all corrective and preventive actions have been process through perform integrated change control process.
[1 - 5.5 Control Scope]
Question 31 |
What are product requirements v.s. project requirements?
A | Technical specifications of the project information management system. |
B | Technical specifications of the project deliverable. |
C | Technology requirements to manage changes in the project. |
D | The way how the project will be managed. |
Question 31 Explanation:
Product requirements are more technical and include business specifications of the project deliverable, while project requirements are focused on the way of how to managing project.
[1 - 5.1 Collect Requirements]
Question 32 |
What kind of deliverables are included in work breakdown structure?
A | All deliverables requested by stakeholders. |
B | Only those deliverable listed in project charter. |
C | Only those deliverables requested by sponsor. |
D | Only those deliverables approved for the project. |
Question 32 Explanation:
Only those deliverables approved for the project take place in WBS.
[1 - 5.3 Create WBS]
Question 33 |
What is the output of create work breakdown structure process?
A | WBS and WBS dictionary, scope management plan, project document update. |
B | WBS and WBS dictionary, scope monitoring and control procedure, scope verification. |
C | WBS and WBS dictionary, scope verification, project document update. |
D | WBS and WBS dictionary, scope baseline, project document update. |
Question 33 Explanation:
WBS and WBS dictionary, scope baseline, project document update are the output of create work breakdown structure and work breakdown structure dictionary.
[1 - 5.3 Create WBS]
Question 34 |
What change in project scope should not be approved?
A | Change that does not provide benefits to organization performs the project. |
B | Change that does not reflect company's strategic plan. |
C | Change that does not bring extra revenue. |
D | Change that does not fit within project charter. |
Question 34 Explanation:
Change in project scope that does not fit within project charter should be be accepted.
[1 - 5 Project Scope Management]
Question 35 |
How control scope process is used with other control processes?
A | Measures cost and time required to implement preventive actions and defect repair. |
B | Provides performance measurements of the project through process groups. |
C | Integrated with other control processes to managing actual changes. |
D | Compares changes against scope baseline. |
Question 35 Explanation:
Control Scope process also integrates with other control processes to managing actual changes.
[1 - 5.5 Control Scope]
Question 36 |
Which document provides the detailed description of the work to be done by a project team?
A | Project plan. |
B | WBS dictionary. |
C | Requirements. |
D | Change request. |
Question 36 Explanation:
Detailed description of the work to be done is provided in WBS dictionary.
Question 37 |
What processes project scope management includes?
A | Collect requirements, define scope, create WBS, verify scope, control scope. |
B | Collect requirements, define scope, create WBS, verify scope, control scope, identify risks and risk management strategies. |
C | Collect requirements, define scope, create activities list, create WBS, create network diagram, determine critical path, verify scope, control scope. |
D | Collect requirements, define scope, create WBS, verify scope, control scope, determine quality quality standards, processes and procedures. |
Question 37 Explanation:
Project scope management includes following processes collect requirements, define scope, create WBS, verify scope, control scope.
[1 - 5 Project Scope Management]
Question 38 |
What of the following information needs to be maintained while defining project scope?
A | Assumptions, constrains, risks and scope management plan. |
B | Assumptions, constrains, product quality and project processes. |
C | Assumptions, constrains, and risks. |
D | Assumptions, constrains, risks, and organizational process assets. |
Question 38 Explanation:
Assumptions, constrains, and risks need to be maintained during define scope process. Newly discovered artifacts need to be added.
[1 - 5.2 Define Scope]
Question 39 |
Which process group includes creation the project scope statement?
A | Initiation. |
B | Execution. |
C | Planning. |
D | Closing. |
Question 39 Explanation:
Project Scope Statement is created planning process group.
Question 40 |
What tools and techniques to be used in collect requirements process?
A | Lessons learned. |
B | Interviews, forums, workshops, decision making techniques, surveys, observations, prototypes. |
C | Project charter and stakeholder register. |
D | Change management requests from previous projects. |
Question 40 Explanation:
Interviews, forums, workshops, decision making techniques, surveys, observations, prototypes are used as tools and techniques in collect requirements process.
[1 - 5.1 Collect Requirements]
Question 41 |
What documents are required for defining project scope?
A | Project charter, list of requirements, requirements matrix, requirements organizational process assets. |
B | Project charter, list of requirements, enterprise environment factors. |
C | Project charter, requirements documentation, organizational process assets. |
D | Project charter, requirements documentation, organizational process assets. |
Question 41 Explanation:
Project charter, requirements documentation, organizational process assets are the input to the process of defining of project scope.
[1 - 5.2 Define Scope]
Question 42 |
Collecting requirements is the process of _____.
A | Crating a product scope. |
B | Identifying stakeholders wishes. |
C | Minimizing of efforts to deliver scope specific results. |
D | Defining and managing customer expectations. |
Question 42 Explanation:
Collecting requirements is the process of defining and managing customer expectations.
[1 - 5.1 Collect Requirements]
Question 43 |
Which of the following project management knowledge area is most useful while collecting requirements?
A | Negotiation. |
B | Risks. |
C | Procurement. |
D | Communications. |
Question 43 Explanation:
Effective communications is one of the most useful project management knowledge areas while collecting requirements.
[1 - 5. Collect Requirements]
Question 44 |
How the work breakdown structure is built?
A | From the first line the smallest pieces following by larger components in each next level. |
B | From the first line with largest pieces following by smaller components in each next level. |
C | Schedule driven sequentially divided components from largest to smallest. |
D | Priorities driven sequentially divided components from largest to smallest. |
Question 44 Explanation:
The work breakdown is structure is built as top-down sequence from the first line with largest pieces, following by smaller components in each next level.
[1 - 5.3 Create WBS]
Question 45 |
Who participates in verify scope is process?
A | Project team with sponsor of customer are reviewing completeness of project deliverables and obtaining formal acceptance. |
B | Project team with sponsor of customer are reviewing completeness of project deliverables. |
C | Project team with sponsor of customer are reviewing completeness of project deliverables. |
D | Project team with sponsor of customer are reviewing completeness of project deliverables. |
Question 45 Explanation:
Project team with sponsor of customer are reviewing completeness of project deliverables and obtaining formal ensuring their satisfactory was reached.
[1 - 5.4 Verify Scope]
Question 46 |
What first steps to be taken in the develop requirements.
A | Analysis information in project charter and stakeholder register. |
B | Analysis of the initial requirements. |
C | Analysis of product scope statement. |
D | Analysis of project scope statement. |
Question 46 Explanation:
Analysis information in project charter [1 - 4.1.3.1] and stakeholder register [1 - 10.1.3.1] is the right answer.
[1 - 5.1 Collect Requirements]
Question 47 |
How the nominal group technique is used in collecting requirements process?
A | Enhanced brainstorming. |
B | Prototyping. |
C | Advanced Delphi technique. |
D | Enhanced affinity method. |
Question 47 Explanation:
Nominal group technique is used to enhanced brainstorming by adding voting process to rank the most useful ideas for further brainstorming or for prioritization of requirements.
[1 - 5.1.2.4 Collect Requirements: Tools and Techniques. Group Creativity Techniques.]
Question 48 |
Which of the planning processes used to managing scope?
A | Collect requirements, create WBS and WBS dictionary, develop project management plan.. |
B | Collect requirements, define scope, create WBS and WBS dictionary, determine quality standards. |
C | Collect requirements, define scope, create WBS and WBS dictionary, manage iterations. |
D | Collect requirements, define scope, create WBS and WBS dictionary. |
Question 48 Explanation:
Collect requirements, define scope, create WBS and WBS dictionary are the planning process used in scope management process.
[1 - 5 Project Scope Management]
Question 49 |
What solution would be preferable if competing requirements have been identified?
A | Consider address both interests of all stakeholders and the project. |
B | Accept only those requirements that match project's interests. |
C | Let sponsor deal with stakeholders to determine which of the collect requirements will be accepted to project execution. |
D | Consider only those stakeholders' requirements that match sponsors preferences. |
Question 49 Explanation:
Project needs to address both interests of all stakeholders and the project.
[1 - 5. Collect Requirements]
Question 50 |
What can allow change in project scope statement?
A | Management request. |
B | Stakeholder request. |
C | Approved change request. |
D | Sponsor's request. |
Question 50 Explanation:
Only approved change request may allow change in project scope statement.
[1 - 5 Project Scope Management]
Question 51 |
What techniques to be used if stakeholders requirements are not in balance with project objectives?
A | Escalate. |
B | Ignore. |
C | Reject. |
D | Negotiate. |
Question 51 Explanation:
If stakeholders requirements are not in balance with project objectives, the project team and project manager need to analyze the influence of the requirements, and offer options, like adjust the requirements, change priorities, implement in later releases, initiate a separate project, or drop.
[1 - 5. Collect Requirements]
Question 52 |
How strong a project manager's decision should be when a competitive requirement is identified?
A | Project manager's authority level is determined in project charter. |
B | Negotiate with stakeholders in favor of project. |
C | Reject. |
D | Ignore. |
Question 52 Explanation:
Project manager's authority level is determined in project charter. However, since the project manager is responsible for project success, it should be his or her decision whether accept of reject specific requirements, while negotiation with stakeholders can be a remedy before a decision is made.
[1 - 5. Collect Requirements]
Question 53 |
A project team collects requirements and uses _____.
A | List of priorities. |
B | Mind mapping. |
C | Organizational process assets. |
D | Score matrix. |
Question 53 Explanation:
Mind mapping is an effective tool for creating a view of consolidated ideas generated through brainstorming.
[1 - 5.1.2 Collect Requirements: Tool and Techniques]
Question 54 |
What information project scope statement contains?
A | Project exclusions, constrains, and assumptions. |
B | Project deliverables. |
C | Project scope description, product acceptance criteria.
|
D | All choices are right. |
Question 54 Explanation:
All choices are right.
[1 - 5.2.3 Define Scope: Outputs]
Question 55 |
During what process group the project scope elaborates as more information about the project become available?
A | Monitoring and controlling. |
B | Executing. |
C | Planning. |
D | Initiating. |
Question 55 Explanation:
Project scope elaborates during planning process group. This process may continue through a number of iterations.
[1 - 5.2 Define Scope]
Question 56 |
A project ream has completed the work on project scope statement. What should be done next?
A | Create activities list. |
B | Create network diagram. |
C | Finalize requirements. |
D | Create work breakdown structure. |
Question 56 Explanation:
Create work breakdown structure needs to be created.
[1 - 5.3 Create WBS]
Question 57 |
What is the major role of verify scope process?
A | Measure project performance. |
B | Gain acceptance of the deliverables. |
C | Get acceptance of the project. |
D | Control project scope. |
Question 57 Explanation:
Verify Scope process produces acceptance of the intermediate deliverables of the project.
[1 - 5.4 Verify Scope]
Question 58 |
What benefits brings work breakdown structure to project team?
A | Indicates how work packages are related on the project and helps to specify risks, and identify impact. Links project members with stakeholders, their specific requirements, and help identify missed activities, which also helps preventing further changes. |
B | Eases project management by indicating only those activities that need to be done focusing on team members' expertise. |
C | Helps to identify required time and cost, resources and their skills. Gets the team's by-in and focusing on the project. |
D | All choices are right. |
Question 58 Explanation:
All the listed but not limited to answers are right.
[1 - 5.3 Create WBS]
Question 59 |
What change in project scope should not be approved?
A | Change that does not bring extra revenue. |
B | Change that does not fit within project charter. |
C | Change that does not reflect company's strategic plan. |
D | Change that does not provide benefits to organization performs the project. |
Question 59 Explanation:
Change in project scope that does not fit within project charter should be be accepted.
Question 60 |
Implementation of a change creep the project scope out. What does it mean?
A | Request for implementation of a preventive change has been approved. |
B | Implementation of uncontrolled change. |
C | Request for implementation of a corrective change has been rejected. |
D | Project deliverable has been fixed and checked against scope. |
Question 60 Explanation:
Uncontrolled changes some people call Creep.
[1 - 5.5 Control Scope]
Question 61 |
A project manager is going to meet with customer to obtain acceptance of the deliverable. What of the following information may be needed for that meeting?
A | Risk management plan and project charter. |
B | Scope management plan and change management plan. |
C | Requirements management plan and communication plan. |
D | Project management plan and scope baseline. |
Question 61 Explanation:
Project management plan and scope baseline are the documents to be present during meeting with customer while discussing acceptance of the deliverable.
[1 - 5.4 Verify Scope]
Question 62 |
Which of the structural approach work breakdown structure has?
A | Top-down. |
B | Mesh decomposition. |
C | Horizontal decomposition. |
D | Bottom-up |
Question 62 Explanation:
Work breakdown structure has top-down descending decomposition.
[1 - 5.3 Create WBS]
Question 63 |
What information is needed to perform verify scope process?
A | Project management plan, requirements documentation, requirements traceability matrix, and validated deliverables. |
B | Product scope, project management plan, requirements documentation, requirements traceability matrix and validated deliverables. |
C | Project scope, project management plan, list of requirements, requirements traceability matrix and validated deliverables. |
D | Project charter, project management plan, requirements documentation, requirements traceability matrix and validated deliverables. |
Question 63 Explanation:
Project management plan, requirements documentation, requirements traceability matrix and validated deliverables are inputs to Verify Scope process.
[1 - 5.4 Verify Scope]
Question 64 |
What of the following solutions would acceptable when a stakeholders group is divided to blocks by interests.
A | Plurality. |
B | Minority. |
C | Dictatorship. |
D | Balance. |
Question 64 Explanation:
Plurality is one of the acceptable alternatives to reach a consensus within largest block even if majority within all group was not reached while using group decision making techniques.
[1 - 5.1.2 Collect Requirements: Tool and Techniques]
Question 65 |
What output delivers the collect requirements process?
A | List of requirements, requirements management plan. |
B | List of requirements, traceability matrix. |
C | Requirements documentation, traceability matrix, requirements management plan. |
D | List of requirements, traceability matrix, project scope statement. |
Question 65 Explanation:
Requirements documentation, traceability matrix, requirements management plan are the deliverables of collect requirements process.
[1 - 5.1.3 Collect Requirements: Outputs]
Question 66 |
What kind of work packages should be included to work breakdown structure?
A | Realistically estimated and described in details. |
B | Identified on critical path. |
C | Suggested by PMO. |
D | Assumed to be delivered on time. |
Question 66 Explanation:
Realistically estimated, described in details, delivered quickly, and are ready to be outsourced without additional information should be included in WBS. This means that WBS dictionary has been also developed for each work package.
[1 - 5.3 Create WBS]
Question 67 |
How the scope management process works?
A | Verifies that the work planned in project scope has been completed. |
B | Directs how to measure project deliverables against project charter. |
C | Provides measurements to identify completeness of change. |
D | Refers to the requirements listed in project charter. |
Question 67 Explanation:
Scope management process verifies that the work planned in project scope has been completed.
[1 - 5.1 Collect Requirements]
Question 68 |
Which tool can be used to reaching consensus in the requirements.
A | Benefit-cost analysis. |
B | Fish-bone analysis. |
C | Delhi techniques. |
D | Linear programming. |
Question 68 Explanation:
Delhi technique is used with a selected group of experts, who provide their feedback on distributed questionnaires through the rounds until a consensus is reached. The facilitator keeps expert's feedback anonymously.
[1 - 5.1.2 Collect Requirements: Tool and Techniques]
Question 69 |
What is control account in work breakdown structure?
A | Work packages, execution of which to be monitored. |
B | Work packages estimated on higher level. |
C | Work package, execution of which to be controlled. |
D | Work packages, identified as milestones. |
Question 69 Explanation:
Work packages estimated on higher level.
[1 - 5.3 Create WBS]
Question 70 |
What of the following information from project charter should be used in define scope process?
A | High level project description, specifications of the product and requirements for project approval. |
B | Detailed project description, detailed product requirements and list of people who approve project deliverables, requirements management plan and change management plan. |
C | Detailed project description, detailed product requirements and list of people who approve project deliverables. |
D | Detailed project description, detailed product requirements and list of people who approve project deliverables, requirements management plan. |
Question 70 Explanation:
High level project description, specifications of the product and requirements for project approval from project charter are used in the define scope process.
[1 - 5.2.1.1 Define Scope: Inputs and 4.1.3.1 Project Charter]
Question 71 |
How a project scope statement can benefit from WBS and WBS dictionary?
A | WBS is an input to create activity list which is a part of project scope statement. |
B | WBS is an input to create project scope statement. |
C | Create WBS and WBS dictionary may discover new scope that wasn't identified before. |
D | WBS and activity list help to build network diagram that is a part of project scope statement. |
Question 71 Explanation:
While going through iterations the results of WBS and WBS dictionary can influence the project scope statement as new scope elements can be discovered during this process.
[1 - 5 Project Scope Management]
Question 72 |
What tools and techniques to be used in the define scope process?
A | Expert judgement, product scope, prototypes, and interviewing. |
B | Expert judgement, product analysis, alternative identification and facilitated workshops. |
C | Peer review, product scope, alternative identification and Delphi technique. |
D | Peer review, product analysis, alternative identification and facilitated workshops. |
Question 72 Explanation:
Expert judgement, product analysis, alternative identification and facilitated workshops are the tools that determined to use for define scope process.
[1 - 5.2 Define Scope: Tools and Techniques]
Question 73 |
What processes from monitoring and controlling process group used in scope management process?
A | Perform integrated change control. |
B | Control scope, follow processes. |
C | Communicating with stakeholders and create forecasts. |
D | Verify scope, control scope. |
Question 73 Explanation:
Verify scope, control scope are two processes from monitoring and controlling process group that used in scope management process.
[1 - 5 Project Scope Management]
Question 74 |
What process is dedicated to document how to manage and control project scope?
A | Develop scope monitoring and controlling plan that are realistic. |
B | Develop project management plan and management plan baselines that are realistic. |
C | Document the scope controlling procedures in accordance to project management baselines that are realistic. |
D | Develop project requirements and create project scope statement. |
Question 74 Explanation:
Develop project management plan and management plan baselines that are realistic is the process of creation project scope management plan, along with other management plans.
[1 - 5 Project Scope Management]
Question 75 |
What are the benefits of using work breakdown structure?
A | Al choices are right. |
B | Confirming allocation of project budget. |
C | Helps to identifying influence of change in scope, activities or work packages and entire project. |
D | Ensuring procurements is done on schedule. |
Question 75 Explanation:
WBS helps to identifying influence of change in scope, activities or work packages and entire project.
[1 - 5.3 Create WBS]
Question 76 |
Which document to be used as a reference to identify if stakeholders' requirements are in balance with project objectives?
A | Project management plan. |
B | Initial project and product requirements. |
C | Requirements management plan. |
D | Project charter. |
Question 76 Explanation:
Project charter is the document that describes projects objectives to be used for balancing the requirements. In other words, the project team must assessing stakeholders' requirements and ensure the demands are in balance with project objectives. Any lack of balancing requirements may increase risks, lead to expensive changes, and unsteadiness of scope, schedule, cost, quality, risk, and customer satisfaction. It is a part of project manager's responsibility to balance stakeholders' interests with specific project objectives. Project manager must to ensure professional cooperation of stakeholders with project team.
[1 - 1. Introduction (page 7); 2.3 Stakeholders; 5. Collect Requirements]
Question 77 |
What tool should be used for creating work breakdown structure?
A | Peer review. |
B | Decomposition. |
C | Expert judgement. |
D | Collaboration. |
Question 77 Explanation:
Decomposition is the tool for creating WBS.
[1 - 5.3 Create WBS]
Question 78 |
What does gold plated project mean?
A | Projects that generate extra profit. |
B | Results of two projects delivered by the same team during the same timeframe. |
C | Projects with large revenue. |
D | Project that delivered results not planned in scope. |
Question 78 Explanation:
Project provided additional result not planned in project scope.
[1 - 5 Project Scope Management]
Question 79 |
Project success is directly influences by quality of _____.
A | Selected project resources. |
B | Change management requests. |
C | Gathering and managing project and product requirements. |
D | Feedback provided by stakeholders. |
Question 79 Explanation:
Gathering and managing project and product requirements is the right answer. The other selections are not significant keys in the work and can be replaced, while requirements are the base of the project and their quality is the most influential.
[1 - 5.1 Collect Requirements]
Question 80 |
How stakeholders' needs and expectations have to be defined?
A | Detailed and flexible. |
B | Detailed and final. |
C | Quantitative and measurable. |
D | Measurable and flexible. |
Question 80 Explanation:
The stakeholders requirements must be quantitative and measurable to be referenced in project and product scope and referenced against project deliverables.
[1 - 5.1 Collect Requirements]
Question 81 |
With what group of people the work breakdown structure can help in communications?
A | Customers. |
B | Sponsors. |
C | Users. |
D | Stakeholsers. |
Question 81 Explanation:
WBS may become a perfect tool in communications with stakeholders while working on the requirements and project scope statement.
Question 82 |
Which of the following constrains determined in project scope?
A | Execute any work requested by sponsor. |
B | Keep project scope firm through the course of the project. |
C | No changes should be done to project scope unless project charter is changed. |
D | Execute the only work described in project scope. |
Question 82 Explanation:
This is on of the major constrain of project scope - execute the only work described in project scope. In other words no other work but listed in project scope needs to be done.
[1 - 5 Project Scope Management]
Question 83 |
What status of the collected requirements needs to be reached?
A | Balanced. |
B | All choices are right. |
C | Finalized. |
D | Confirmed. |
Question 83 Explanation:
All choices are right, the requirements need to be balanced, finalized, and confirmed with all stakeholders.
[1 - 5. Collect Requirements]
Question 84 |
How the scope management process works?
A | Refers to the constrain listed in project charter. |
B | Provides measurements to identify gaps in change. |
C | Measures scope performance and corrects when needed. |
D | Directs how to deliver project results and to be measured during project execution. |
Question 84 Explanation:
Scope management process measures the scope performance and corrects it when needed.
[1 - 5.1 Collect Requirements]
Question 85 |
What process should I use to prepare for the meeting with customer?
A | Monitor scope. |
B | Verify scope. |
C | Validate scope. |
D | Control scope. |
Question 85 Explanation:
Verify Scope process is used for verification of deliverable completeness in preparation for acceptance meting or request for acceptance.
[1 - 5.4 Verify Scope]
Question 86 |
What is the purpose of control scope process?
A | Controlling the project scope and ensuring all defects have been fixed. |
B | Measuring performance of the project through its all phases. |
C | Monitoring the project status, its scope and managing changes to the scope baseline. |
D | Controlling changes to the scope through all phases of the project. |
Question 86 Explanation:
Monitoring the project status, its scope and managing changes to the scope baseline.
[1 - 5.5 Control Scope]
Question 87 |
How create WBS uses project requirements?
A | Breaks to smaller easier manageable pieces. |
B | Clarifies requirements on detailed level. |
C | Groups the requirements into larger work packages. |
D | Breaks requirements to the detailed level. |
Question 87 Explanation:
WBS breaks to requirements to smaller easier manageable pieces.
[1 - 5.1 Collect Requirements]
Question 88 |
Output of which process a requirements documentation is?
A | Develop project scope statement. |
B | Develop project management plan. |
C | Determine how to execute and control management plans. |
D | Collect project requirements. |
Question 88 Explanation:
Requirements documentation is one of the outputs of collect project requirements process.
[1 - 5.1 Collect Requirements]
Question 89 |
What information in the process of define scope should be analyzed for completeness?
A | Product description. |
B | Project time. |
C | Assumptions and constrains. |
D | Project costs. |
Question 89 Explanation:
All choices are actually right, while they are summarized as assumptions and constrains.
[1 - 5.2 Define Scope]
Question 90 |
When the problems related to collecting requirements need to be addressed?
A | As soon as arise. |
B | Escalate the problem to management, continue collect requirements and address it after the process is finished. |
C | After the collect requirements process is complete, solve all problems sequentially. |
D | Complete the process, finalize the requirements and generate change request using integrated change management system. |
Question 90 Explanation:
Collect requirements problems need to be sold as soon as arise. Unsolved requirements problems may cause expensive changes or even cancellation of project on its later stages.
[1 - 5. Collect Requirements]
Question 91 |
During which process the deliverables need to be validated?
A | Perform quality control inspection. |
B | Control scope. |
C | Project closing. |
D | Collect requirements. |
Question 91 Explanation:
Deliverables need to be validated during Perform Quality Control Inspection process.
Question 92 |
What information included WBS dictionary?
A | Technical references and contact information related to work package. |
B | Constrains and assumptions for work to complete work package. |
C | Detailed description of the work package. |
D | List of activities to complete work package. |
Question 92 Explanation:
All choices are right, but not limited to the listed here; so, WBS dictionary includes detailed description of the work package.
[1 - 5.3.3 Create WBS: Outputs]
Question 93 |
What work breakdown structure refers to?
A | Sequentially indexed list of the related work packages. |
B | Sequentially indexed list of project activities. |
C | Graphical presentation of the project activities. |
D | Indexed list of activities scheduled on the project. |
Question 93 Explanation:
Work breakdown structure is a graphical presentation of the project activities.
[1 - 5.3 Create WBS]
Question 94 |
Who crates a work breakdown structure?
A | Project manager. |
B | Stakeholders. |
C | PMO. |
D | Project team lead by project manger. |
Question 94 Explanation:
Work breakdown structure should be created with active participation of a project team using various communication and group decision making methods, like meeting, focus group, etc.
Question 95 |
What kind of experts can be invited to discuss project scope?
A | Whether internal or external subject matter experts. |
B | Other departments in the organization, stakeholders and consultants. |
C | All choices are right. |
D | Experts from professional and technical associations. |
Question 95 Explanation:
All choices are right. For the sake of receiving appropriate professional expert judgement all listed but no limited to sources can help.
[1 - 5.2 Define Scope: Tools and Techniques]
Question 96 |
What sources of the requirements should be used for creating project scope?
A | Managers, who assigned you to the project, customers and documents provided by sponsor. |
B | Historical documents. |
C | PMO. |
D | All stakeholders and related documents. |
Question 96 Explanation:
Requirements must be collected from all stakeholders included but limited to all stakeholders, sponsors, customers, users, management, etc.
[1 - 5 Project Scope Management]
Question 97 |
What drives work breakdown structure?
A | Descending hierarchical approach driven by project deliverables. |
B | Ascending hierarchical structure of activities presented as work packages. |
C | Sequential list of project deliverables. |
D | Ascending hierarchical structure of the project deliverables. |
Question 97 Explanation:
Descending hierarchical approach driven by project deliverables drives the work breakdown structure.
[1 - 5.3 Create WBS]
Question 98 |
What information is needed to start collecting requirements?
A | High level project requirements and detailed description of product. |
B | Detailed project requirements and detailed description of product. |
C | High level project requirements and high level description of product. |
D | Detailed level of project requirements and high level description of product. |
Question 98 Explanation:
High level project requirements and high level description of product should be provided in project charter; so this document is needed for collect requirements process.
[1 - 5.1.1 Collect Requirements: Input]
Question 99 |
When the verify scope process should be done?
A | During collecting requirements. |
B | During planning. |
C | At the end of each phase. |
D | At the end of project. |
Question 99 Explanation:
Verify scope process should be done at the end of each phase or when acceptance of an intermediate deliverable is required.
[1 - 5.4 Verify Scope]
Question 100 |
A project team received a large set of requirements from the sponsor. What needs to be done with these requirements?
A | Share the product requirement with all stakeholders. |
B | Identify if similar requirements have been earlier implemented by the company and use historical information as help in planning process. |
C | Archive the document. |
D | Clarify product requirements and determine project requirements. |
Question 100 Explanation:
Clarify product requirements and determine project requirements. The received set of requirements is probably related to the product rather than project. So project requirements need to be determined.
[1 - 5.1 Collect Requirements]
Question 101 |
What components scope baseline includes?
A | Work breakdown structure. |
B | Work breakdown structure dictionary. |
C | All choices are right. |
D | Project scope statement. |
Question 101 Explanation:
Scope baseline includes all project scope statement, work breakdown structure and work breakdown structure dictionary.
[1 - 5.3.3 Create WBS: Outputs]
Question 102 |
Output of which process a requirements documentation is?
A | Develop project management plan. |
B | Develop project scope statement. |
C | Collect project requirements. |
D | Determine how to execute and control management plans. |
Question 102 Explanation:
Requirements documentation is one of the outputs of collect project requirements process.
[1 - 5.1 Collect Requirements]
Question 103 |
At what level of details the work packages need to be described to take place in work breakdown structure?
A | To be estimated during estimate resource requirements process. |
B | Ready for estimation of the required efforts. |
C | Identified duration for execution. |
D | To be executed without additional information. |
Question 103 Explanation:
Realistically estimated, described in details, delivered quickly, and are ready to be outsourced without additional information should be included in WBS. This means that WBS dictionary has been also developed for each work package.
[1 - 5.3 Create WBS]
Question 104 |
What information project scope contains?
A | Detailed description of the project and product. |
B | Detailed description of the project. |
C | Detailed description of the product. |
D | Detailed description of how the requirements to the project and product will be managed during the source of the project. |
Question 104 Explanation:
Project scope contains detailed description of the project and product.
[1 - 5.2 Define Scope]
Question 105 |
A project manager is going to meet with customer to obtain acceptance of the deliverable. What of the following information may be needed for that meeting?
A | Scope management plan and requirements documentation. |
B | Traceability matrix. |
C | Project management plan and scope baseline. |
D | All choices are right. |
Question 105 Explanation:
All choices are right. Scope baseline is the part of project management plan to be used for verifying what has been done to comply with scope and requirements, while requirements documentation may be needed to verify the details. Traceability matrix will refer to the sources of requirement and relations to other requirements, and cope management plan to confirm the agreed list of deliverables.
[1 - 5.4 Verify Scope]
Question 106 |
What project management tool needs to be created after the project scope statement was completed?
A | Create network diagram. |
B | Divide project work to smaller more manageable components. |
C | Develop schedule. |
D | Create activities list. |
Question 106 Explanation:
Create WBS, with means divide project work and project deliverables to smaller more manageable components.
[1 - 5.3 Create WBS]
Question 107 |
What documentation needs to be updated when WBS is complete?
A | Project schedule. |
B | Requirements documentation. |
C | Activity list. |
D | Estimation resource requirements. |
Question 107 Explanation:
Requirements documentation needs to be updated when WBS is completed. Other choices are outputs of the processes that come next.
[1 - 5.3.3 Create WBS: Outputs]
Question 108 |
What of the following processes uses project requirement as a foundation.
A | Prepare procurement documents. |
B | Create WBS and WBS dictionary. |
C | Estimate time and cost. |
D | Plan communications. |
Question 108 Explanation:
Requirements are the foundation to create WBS and WBS process.
[1 - 5.1 Collect Requirements]
Question 109 |
What is advantage of work breakdown structure?
A | Groups project components by complexity. |
B | Diving the project work and its deliverables to smaller more manageable components. |
C | Divides project components by stakeholders' preferences. |
D | Groups project components by knowledge areas. |
Question 109 Explanation:
Diving the project work and its deliverables to smaller more manageable components.
[1 - 5.3 Create WBS]
Question 110 |
How the processes of collecting requirements fits scope project management?
A | Defining and documenting stakeholders requirements that meet project objectives. |
B | Identifying and documenting stakeholders requirements that meet project objectives. |
C | Identifying stakeholders wishes that meet project objectives and documenting them as requirements. |
D | Documenting stakeholders requirements that meet project objectives. |
Question 110 Explanation:
Defining and documenting stakeholders requirements that meet project objectives is the right answer. Here the play of words brings different meaning to project manager's work.
[1 - 5.1 Collect Requirements]
Question 111 |
What needs to be done if during project execution a deviation in the requirements was identified?
A | Issue the change request using integrated change control system. |
B | Allow the deviation if it does not effect scope, schedule, cost and customer satisfaction. |
C | Allow the deviation if it does not effect scope, schedule, cost and quality. |
D | Analyze and fix a cause of the problem. |
Question 111 Explanation:
Analyzing before acting is the rule what any project manger should follow. Fixing a cause of the problem may eliminate new problems and issues.
[1 - 5. Collect Requirements]
Question 112 |
What information requires to perform control scope process?
A | Project management plan and work performance information. |
B | All choices are right. |
C | Organizational process assets. |
D | Requirements documentation, requirements traceability matrix. |
Question 112 Explanation:
All choices in together provide input into Control Scope process.
[1 - 5.5 Control Scope]
Question 113 |
Before continue collecting further demands, what techniques would be useful for braking already documented requirements to suitable groups?
A | Pareto diagram. |
B | Mind maps. |
C | Pareto diagram. |
D | Affinity diagram. |
Question 113 Explanation:
Affinity diagram helps to group already collected requirements by similarity and document new ones. This technique also simplifies identifying additional scope or risks.
[1 - 5.1.2 Collect Requirements: Tool and Techniques]
Question 114 |
What information is needed for collecting requirements?
A | Organizational process assets and requirements management plan. |
B | Contact list of stakeholders, information about their responsibilities and influence to the project. |
C | Enterprise environment factors, including requirements management system. |
D | Project charter and requirements management plan. |
Question 114 Explanation:
Stakeholder register and project charter should include all the require information to start collecting requirements. Other choices may also help; however, the question is about the minimum input to the process of collect requirements.
[1 - 5.1.1 Collect Requirements: Input]
Question 115 |
How the process of verify scope is different from quality control?
A | Concerns cost and schedule constrains for the deliverables rather than their correctness and specified quality. |
B | Concerns scope constrains for the deliverables rather than their correctness and specified quality. |
C | Concerns scope constrains for the deliverables rather than correctness and specified quality. |
D | Concerns acceptance of the deliverables rather than their correctness and specified quality. |
Question 115 Explanation:
Verify scope concerns acceptance of the deliverables rather than their correctness and specified quality. Control quality usually performed before verify scope process but in some cases can be done in parallel.
[1 - 5.4 Verify Scope]
Question 116 |
What tools is used for scope verification?
A | Expert judgement. |
B | Peer review. |
C | Auditing. |
D | Inspection. |
Question 116 Explanation:
Inspection is the tool that used for Verify Scope process.
[1 - 5.4 Verify Scope]
Question 117 |
What of the following media and methods would be useful in collecting and finalizing requirements process?
A | Questionnaires and surveys. |
B | Observations. |
C | All choices are right. |
D | Prototypes. |
Question 117 Explanation:
All choices are right; questionnaires and surveys, observations, and prototypes are useful in collecting and finalizing the requirements.
[1 - 5.1.2.4 Collect Requirements: Tools and Techniques. Group Creativity Techniques.]
Question 118 |
What needs to be done so results in delivery of project work reflect specified product scope?
A | Verify and control scope on timely manner. |
B | Integrate scope management processes with other knowledge areas. |
C | Monitor and control project according to project management plan. |
D | Integrate scope management processes with processes from other process groups. |
Question 118 Explanation:
Integrate scope management processes with other knowledge areas.
[1 - 5 Project Scope Management]
Question 119 |
Which of the following processes complete the deliverables?
A | Closing. |
B | Executing. |
C | Direct and manage project execution. |
D | Monitoring and controlling. |
Question 119 Explanation:
Deliverables are complete using the Direct and Manage Project Execution processes, which are included to all execution, monitoring and controlling, and closing project groups.
Question 120 |
Requirements management plan is output of which process?
A | Develop project management plan. |
B | Determine how to execute and control management plans. |
C | Develop project scope statement. |
D | Collect project requirements. |
Question 120 Explanation:
Requirements management plan is one of the outputs of collect project requirements process.
[1 - 5.1 Collect Requirements]
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 120 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
| 1 | 2 | 3 | 4 | 5 |
| 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 |
| 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 |
| 31 | 32 | 33 | 34 | 35 |
| 36 | 37 | 38 | 39 | 40 |
| 41 | 42 | 43 | 44 | 45 |
| 46 | 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 | 55 |
| 56 | 57 | 58 | 59 | 60 |
| 61 | 62 | 63 | 64 | 65 |
| 66 | 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| 76 | 77 | 78 | 79 | 80 |
| 81 | 82 | 83 | 84 | 85 |
| 86 | 87 | 88 | 89 | 90 |
| 91 | 92 | 93 | 94 | 95 |
| 96 | 97 | 98 | 99 | 100 |
| 101 | 102 | 103 | 104 | 105 |
| 106 | 107 | 108 | 109 | 110 |
| 111 | 112 | 113 | 114 | 115 |
| 116 | 117 | 118 | 119 | 120 |
| End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!