Development of this quiz is in progress.
PM - Time Management
Start
Congratulations - you have completed PM - Time Management.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
Which graphical form of schedule preferably use during presentation to senior management?
A | Project schedule network diagram. |
B | Affinity diagram. |
C | Milestone chart. |
D | Bar chart. |
Question 1 Explanation:
Milestone chart graphically presents only major start and end dates, which usually used for reporting to senior management.
Bar chart is handful for graphically presenting progress of the project activities while discussing with the team.
Project schedule network diagram shows time-scaled logical relations between activities.
[1 - 6.5.3 Develop Schedule: Outputs]
Question 2 |
What information is documented in project schedule management plan?
A | Thresholds that project schedule can reach during planning phase. |
B | Defines the beginning end, and milestone dates of the project. |
C | Project management processes, tools and techniques. |
D | Defined the beginning and end dates of the project. |
Question 2 Explanation:
Project Schedule Management Plan is a part of Project Management Plan and describes the project management processes, tools and techniques to be used on the project.
[1 - 6 Project Time Management]
Question 3 |
How many critical paths a project may have?
A | Maximum one. |
B | Many. |
C | Maximum three. |
D | Maximum two. |
Question 3 Explanation:
A project may have many critical paths.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 4 |
What of the following should be used as a base for accurate estimation?
A | Requirements documentation. |
B | Work breakdown structure. |
C | Project charter. |
D | Project scope. |
Question 4 Explanation:
Work breakdown structure should be used as a base for effective and accurate estimation.
Question 5 |
What effect you need to expect when selected method of schedule compression is cut time?
A | Reduced scope. |
B | Reduced quality. |
C | Increased risks. |
D | Increased costs. |
Question 5 Explanation:
Cut time as a choice of schedule compression usually leads to reduced quality standards.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 6 |
Sequencing of the activities can be performed using _____.
A | Manual optimization method. |
B | Project management hardware. |
C | Only project management software. |
D | Project management software. |
Question 6 Explanation:
Sequencing of the activities can be performed using project management software.
[1 - 6.2 Sequence Activities]
Question 7 |
What type of diagram is created as the result of regression analysis in parametric estimation?
A | Affinity diagram. |
B | Learning curve. |
C | Network diagram. |
D | Scatter diagram. |
Question 7 Explanation:
Scatter diagram is created in parametric estimation where the time measures per action component like per line of code, per meter, or per setup, etc. Learning Curve is another parametric method that states the following similar activity should take less time than previous because of obtained more experience, improved skills and techniques.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques]
Question 8 |
By completion of estimate duration activity project manager has to update project document with _____?
A | Activity duration estimate and schedule baseline. |
B | Activity duration estimate. |
C | Work performance measurements, activity duration estimate. |
D | Project schedule, activity duration estimate. |
Question 8 Explanation:
By completion of estimate duration activity project manager has to update project document with Activity Duration Estimate.
[1 - 6 Project Time Management]
Question 9 |
How the output of estimate activity duration forms?
A | Activity duration can be identified as a firm quantitative period, as well as a period with added probability. |
B | Activity duration can be identified as a firm quantitative period. |
C | Activity duration can be identified buy taking a guess and double it to ensure the activity will be completed. |
D | All activities on the project can be assign with the same period of time as long as the activity takes less than one week. |
Question 9 Explanation:
Activity duration can be identified as a firm quantitative period, as well as a period with added probability.
[1 - 6.4.3 Estimate Activity Duration: Outputs]
Question 10 |
What documents to be delivered by define activities process?
A | Activity list, milestone list, and project schedule. |
B | Activity list, milestone list, and activity resource requirements. |
C | All choices are right. |
D | Activity list, activity attributes, and milestone list. |
Question 10 Explanation:
Activity list, activity attributes, and milestone list are deliverables of define activities process.
[1 - 6 Project Time Management]
Question 11 |
What type of processes use schedule compression?
A | Planning and executing. |
B | Planning and integrated change control. |
C | Executing, and monitoring and controlling.. |
D | Executing and closing. |
Question 11 Explanation:
Schedule compression is used during planning and integrated change control (monitoring and controlling). During planning project manager optimizes the schedule to meet deadlines without changing scope, and in integrated change control, checks if there is any impact to scope, time, cost, risk, resources or customer satisfaction.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 12 |
What needs to be done first to justify project time estimate?
A | Determine critical path. |
B | Collect and combine time estimated for major tasks. |
C | Confirm with a team. |
D | Build a network diagram. |
Question 12 Explanation:
Build a network diagram and then determine critical path.
[1 - 6.2 Sequence Activities]
Question 13 |
Which of the methods refers to progressive elaboration planning?
A | Bottom-up estimation. |
B | Rolling wave. |
C | Waterfall. |
D | Precedence diagramming. |
Question 13 Explanation:
Rolling wave is the method of progressing elaboration planning.
[1 - 6.1.1 Define Activities: Input]
Question 14 |
Precedence diagramming method is used for _____.
A | Constructing a visual diagram that uses nodes to indicate logically related requirements. |
B | Constructing a visual diagram that uses nodes to indicate logically related requirements and risks on the project. |
C | Constructing a visual diagram that uses nodes to indicate logically related communications between project members and stakeholders. |
D | Constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. |
Question 14 Explanation:
Precedence diagramming method is used for constructing a visual project schedule network diagram that uses nodes to indicate logically related activities.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 15 |
How activities and their properties are used on the project?
A | Provide information on how to execute the work packages. |
B | Provide reference to the work planned for completion of the project. |
C | Provide information to measure the project performance in monitoring and controlling processes. |
D | Provide input to estimating, scheduling, executing, and monitoring and controlling of project work. |
Question 15 Explanation:
Provide input to estimating, scheduling, executing, and monitoring and controlling of project work is the most completed answer to the question.
[1 - 6.1 Project Time Management: Define Activities]
Question 16 |
What criteria to be used in the decision of which activity or activities to crash for the purpose of schedule compression?
A | Longest time. |
B | Lowest cost. |
C | Shortest time. |
D | Higher cost. |
Question 16 Explanation:
The crash the activity or activities with lowest cost to be selected for the purpose of schedule compression.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 17 |
What information to be updated at the end of estimate activity resources?
A | Activity resources requirements, resource breakdown structure, and project schedule. |
B | Activity resources requirements and work breakdown structure. |
C | Activity resources requirements and resource breakdown structure. |
D | All choices are right. |
Question 17 Explanation:
Activity resources requirements, resource breakdown structure, and update project document are results of Estimate Activity Resources.
[1 - 6 Project Time Management]
Question 18 |
What are the objectives of schedule compression?
A | Prove the request for using management reserve. |
B | Optimize schedule to meet project or milestone deadline. |
C | Optimize schedule to meet project or milestone deadline without changing project scope. |
D | Prove the request for using contingency reserve. |
Question 18 Explanation:
Optimize schedule to meet project or milestone deadline without changing project scope.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 19 |
Who should participate in estimating process to assure accuracy?
A | Sponsor. |
B | The person who will be executing the work. |
C | Stakeholder. |
D | Functional manager. |
Question 19 Explanation:
The person who will be executing the work can provide more accurate information for estimating the required work efforts and duration.
Question 20 |
How often time management processes can be used during the course of the project?
A | All time management processes to be used through the course of the project. |
B | Only selected time management processes to be selected depending on project needs. |
C | At least ones on the project and project phase, if the project is divided to phases. |
D | Time management processes to be used during project initiation and its planning phase. |
Question 20 Explanation:
Actually, the question is how often a project manager and project team are concern about project schedule - ideally, at least ones on the project and project phase. In reality, time management processes are used quite often in combination with other processes. For example, a number of processes, including time, will be used in managing change requests and controlling schedule during the course of the project.
[PMBOK. Project Time Management]
Question 21 |
What type of dependency called hard logic?
A | External dependency. |
B | Mandatory dependency. |
C | Preferred dependency. |
D | Discretionary dependency. |
Question 21 Explanation:
Mandatory dependency in other words called hard logic and represent the unavoidable dependency from the elated activity. For example, an activity that must be done as per law requirement or corporate SDLC standard.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 22 |
How graphical evaluation and review techniques (GERT) is different from other diagramming methods?
A | Allows conditional nodes. |
B | Indicates only mandatory dependencies. |
C | Connects nodes with arrows that represent activities. |
D | Allows using loops between nodes. |
Question 22 Explanation:
Graphical Evaluation and Review Techniques (GERT) allows using between project activities.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 23 |
What information is missing while activity list, activity attribute, and resource calendar is provided for estimating activity resources process?
A | Activity resource requirements. |
B | Enterprise environmental factors and organizational process assets. |
C | Enterprise environmental factors. |
D | Organizational process assets. |
Question 23 Explanation:
Activity list, activity attribute, resource calendar, enterprise environmental factors and organizational process assets are inputs to estimate activity resources. Other choices whether incomplete while, activity resource requirements is the output of this process.
[1 - 6 Project Time Management]
Question 24 |
A project manager performs define activity process. What information this process delivers?
A | A list of specified activities for implementing change using integrated change control system. |
B | Description of project activities listed in ascending order. |
C | Identified specific actions and their details to produce project deliverables. |
D | Identified specific actions and their details to reach planned quality of project deliverables. |
Question 24 Explanation:
Define activities identifies specific actions and their details to produce project deliverables.
[1 - 6.1 Project Time Management: Define Activities]
Question 25 |
How the contingency plan is different from management reserve?
A | Contingency reserve is calculating to compensate unknown unknowns schedule uncertainty for specific part of the project. |
B | Contingency reserve is calculating to compensate schedule uncertainty for specific part of the project. |
C | Contingency reserve is calculating to compensate schedule uncertainty for overall project, and determined as firm as additional time to be spent for planned changes. |
D | Contingency reserve is calculating to compensate schedule uncertainty for overall project, and can determine the schedule tolerance. |
Question 25 Explanation:
Contingency reserve is calculating to compensate schedule uncertainty for overall project, and can determine the schedule tolerance.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .5 Reserve Analysis]. Contingency reserve discussed mo in Cost Management Chapter.
Question 26 |
What does critical path determine?
A | The shortest path in the network diagram, as well as the latest start and finish dates for project activities. |
B | The longest path in the network diagram, as well as the earliest start and earliest finish dates for project activities. |
C | The longest path in the network diagram, as well as the earliest and latest start and finish dates for project activities. |
D | The shortest path in the network diagram, as well as the earliest and latest start and finish dates for project activities. |
Question 26 Explanation:
The longest path in the network diagram, as well as the earliest and latest start and finish dates for project activities.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 27 |
After coordinating of the activity list, a project manager estimates activity resources. What he needs to complete the work?
A | Resources breakdown structure. |
B | Activity attributes. |
C | Activity resources requirements. |
D | Project document updates. |
Question 27 Explanation:
The Activity Attributes are missing along with resource calendars, enterprise environment factors and organizational process assets. All other choices are deliverables of the same process of Estimate Activity Resources.
[1 - 6.3 Estimate Activity Resources]
Question 28 |
What information to be updated at the end of estimate activity resources?
A | All choices are right. |
B | Activity resources requirements and resource breakdown structure. |
C | Activity resources requirements, resource breakdown structure, and project schedule. |
D | Activity resources requirements and work breakdown structure. |
Question 28 Explanation:
Activity resources requirements, resource breakdown structure, and update project document are results of Estimate Activity Resources.
[1 - 6 Project Time Management]
Question 29 |
A project manager estimates activity duration. What information is needed to make this process effectively?
A | Activity list, activity attributes, and activity resource requirements. |
B | Enterprise environmental factors and organizational process assets. |
C | Resource calendars, project scope statements. |
D | All choices are right. |
Question 29 Explanation:
All choices are right. All these documents are input to the estimate activity duration process.
[1 - 6 Project Time Management]
Question 30 |
How to calculate float?
A | Late Finish - Earlier Start or Late Start - Early Finish. |
B | Late Start - Earlier Finish or Late Start - Early Finish. |
C | Late Start - Earlier Start or Late Finish - Early Finish. |
D | Late Finish - Earlier Start or Late Finish - Early Finish. |
Question 30 Explanation:
Late Start - Earlier Start or Late Finish - Early Finish are the equations to calculate Float (Slack).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 31 |
What type of dependency called external dependency?
A | Dependency outside of the project. |
B | Dependency outside of the project team. |
C | Dependency outside of the country. |
D | Dependency outside of the project organization. |
Question 31 Explanation:
As long as the dependency is outside of the project it called External", regardless of its location or nature.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 32 |
What needs to be done if the project has negative slack?
A | Compress schedule. |
B | Ask for additional time. |
C | Re-estimate activity duration. |
D | Re-estimate resource requirements. |
Question 32 Explanation:
If the project has negative slack (float) it means the project is behind the schedule; compress schedule is the recommended action (fast track, crash, reduction of scope or quality).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 33 |
How near-critical path effect the project?
A | Near-critical path does not have effect to risk? |
B | As near-critical path comes closer to critical path, the project reduces its risk. |
C | As near-critical path closer to critical path, the project has more risk. |
D | As near-critical path closer to critical path, the project has less risk. |
Question 33 Explanation:
As near-critical path closer to critical path, the project has more risk; as identified, both paths needs to be monitored and managed.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 34 |
Project manager should periodically _____ to make sure that adequate time and funds available to complete the project.
A | Run team performance report. |
B | Recalculate estimate to complete. |
C | Discuss the possible risks. |
D | Review plans. |
Question 34 Explanation:
Project manager should periodically recalculate estimate to complete (ETC) to make sure that adequate time and funds available to complete the project.
Question 35 |
What tree-point estimate analyzes and produces?
A | Analyzes risks and produces optimistic, most likely and pessimistic estimates. |
B | Analyzes constrains and produces optimistic, most likely and pessimistic estimates. |
C | Analyzes requirements and produces optimistic, most likely and pessimistic estimates. |
D | Analyzes baselines and produces optimistic, most likely and pessimistic estimates. |
Question 35 Explanation:
Tree-point estimate analyzes risks and produces optimistic, most likely and pessimistic estimates.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 36 |
How does the Start-to-Finish (SF) relations work?
A | The finish of successor depends on start of predecessor. |
B | The start of successor depends on start of predecessor. |
C | The start of successor depends on start of predecessor. |
D | The completion of predecessor depends on completion of successor. |
Question 36 Explanation:
The finish of successor depends on start of predecessor. In other words, the start of activity will allow to finish the next related activity.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 37 |
From which process output the define activities process receives scope baseline?
A | Develop activity list. |
B | Work breakdown structure. |
C | Develop scope management plan. |
D | Project scope statement. |
Question 37 Explanation:
Scope baseline is one of the results of create work breakdown structure process.
[1 - 6.1.1 Define Activities: Input]
Question 38 |
What method is used to avoid not linear (up-and-down) use of resources?
A | Calendar stabilizing. |
B | Economic model. |
C | Activity crashing. |
D | Resource leveling. |
Question 38 Explanation:
Resource leveling technique is used to stabilize use of resources. The longer project duration is an option to stabilize usage of resources on the project, instead hiring resources for shorter periods, releasing them and hiring back, when needed. This also may save cost of procurement and reduce risk for spending extra effort for training and/or knowledge transfer.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 39 |
A project team agreed with project schedule network diagram after _____?
A | Stakeholders determined project constrains. |
B | Received sponsor's approval. |
C | Project document was updated. |
D | Estimating activity resources was completed. |
Question 39 Explanation:
Project schedule network diagram and updated project document are results of sequence activities process.
[PMBOK. Project Time Management.]
Question 40 |
What sequence activities is?
A | Process of identifying and documenting the thresholds the project activities. |
B | Process of identifying and documenting physical relationship between the project activities. |
C | Process of identifying and documenting logical relationship between the project activities. |
D | Process of identifying and documenting the interface properties between the project activities. |
Question 40 Explanation:
Process of identifying and documenting relationship between the project activities.
[1 - 6.2 Sequence Activities]
Question 41 |
How does the Start-to-Start (SS) relations work?
A | The start of successor depends on finish of predecessor. |
B | The completion of successor depends on completion of predecessor. |
C | The start of successor depends on start of predecessor. |
D | The finish of successor depends on start of predecessor. |
Question 41 Explanation:
The start of successor depends on start of predecessor.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 42 |
What type of dependency called soft logic?
A | Discretionary dependency. |
B | External dependency. |
C | Preferred dependency. |
D | All choices are right. |
Question 42 Explanation:
Mandatory dependency in other words called had logic and represent the unavoidable dependency from the related activity. For example, an activity that must be done as per law requirement or corporate SDLC standard.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 43 |
A project team supports project manager with information to sequence activities. What information is needed to complete the work?
A | List of activities and their attributes. |
B | Organizational process assets. |
C | All choices are right. |
D | Milestones. |
Question 43 Explanation:
to complete sequence activities process project manager needs List of Activities, Activities Attributes, Milestones, and Organizational Process Assets.
[1 - 6 Project Time Management]
Question 44 |
What results of the develop schedule should be updated when the process is complete?
A | Project schedule, schedule baseline, schedule data |
B | All choices are right. |
C | Project schedule, schedule baseline, work breakdown structure. |
D | Project schedule, schedule baseline, activity list. |
Question 44 Explanation:
Project schedule, schedule baseline, schedule data and project document update are deliverables of the develop schedule.
[1 - 6 Project Time Management]
Question 45 |
What process is planning the scheduling methodology applied to the project?
A | Develop project charter. |
B | Develop procurement plan. |
C | Develop project management plan. |
D | Develop time constrains and assumptions. |
Question 45 Explanation:
Develop project management plan that produces a schedule management plan is the process that defines project scheduling methodology to be used during the course of the project.
[1 - 6 Project Time Management]
Question 46 |
What tools and techniques project manager uses to define activities?
A | Decomposition. |
B | Rolling wave planning. |
C | Templates and expert judgement. |
D | All choices are right. |
Question 46 Explanation:
All choices are right. Project manager uses Decomposition, Rolling Wave Planning, Templates and Expert Judgement while Defining Activities.
[1 - 6 Project Time Management]
Question 47 |
What can be used to show the interdependency between activities through the whole project?
A | Project scope statement. |
B | Work breakdown structure. |
C | List of activities. |
D | Network diagram. |
Question 47 Explanation:
Network diagram shows interdependency of the activities through the whole project.
[1 - 6.2 Sequence Activities]
Question 48 |
How detailed the project schedule should be?
A | Highly detailed to ensure that all dates for activities and milestones are determined. |
B | Whether highly detailed or broadly framed, depending on needs of the project. |
C | Only major activities need to be scheduled and provide high level of details. |
D | All activities need to be scheduled and provide high level of details to ensure that project is tractable. |
Question 48 Explanation:
Project schedule can be documented with using very detailed information about time or include only mile stones; the level of required details is depending on needs of the project and include appropriate realistic thresholds.
[1 - 6 Project Time Management]
Question 49 |
What technique an be used for schedule network analysis?
A | What-if scenario analysis. |
B | All choices are right. |
C | Critical path and schedule compression. |
D | Resources leveling and critical chain method. |
Question 49 Explanation:
All these techniques are applicable to calculate the early and late start, and finish dates for the project activities.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 50 |
A project manager performs define activity process. What information this process delivers?
A | Identified specific actions and their details to produce project deliverables. |
B | Identified specific actions and their details to produce a realistic project schedule. |
C | A list of specified activities for implementing change using integrated change control system. |
D | Description of project activities listed in ascending order. |
Question 50 Explanation:
Define activities identifies specific actions and their details to produce project deliverables.
[PMBOK. Project Time Management: Define Activities]
Question 51 |
What can be used to support realistic schedule?
A | Lead and lags time between activities can be used to support realistic schedule. |
B | Lead and lags time usually used to leverage the schedule. |
C | Crashing the schedule is the method for realistic planning of schedule. |
D | De-scoping is the method to sequence the project activities for realistic schedule. |
Question 51 Explanation:
Lead and lags time between activities can be used to support realistic schedule.
[1 - 6.2 Sequence Activities]
Question 52 |
What tools and techniques project manager uses to control schedule?
A | Adjusting leads and lags, schedule compression, scheduling tool. |
B | Resource leveling, what-if scenario analysis. |
C | Performance reviews, variance analysis, project management software. |
D | All choices are right. |
Question 52 Explanation:
All choices are right; all listed tools and techniques are used to Control Schedule.
[1 - 6 Project Time Management]
Question 53 |
How time management processes interact with other project processes?
A | Can be used in different sequence without overlap of each other. |
B | Can be used with different processes and overlap each other. |
C | Can be used only with planning process group during process initiation. |
D | Cannot overlap each other, but used one after another with planning processes only. |
Question 53 Explanation:
Time management processes can be used with different processes and overlap each other during the course of the project.
[PMBOK. Project Time Management.]
Question 54 |
What relation between create work breakdown structure and define activities processes?
A | Work breakdown structure identifies the methods how the to be executed, while define activities process identifies the activities to deliver those packages. |
B | Work breakdown structure describes the way how to deliver the project results, while define activities process identifies the activities to deliver those packages. |
C | Work breakdown structure proved a sequence of activities, while define activities process identifies the activities to deliver those packages. |
D | Work breakdown structure identifies the deliverables at their lowest level, which called packages, while define activities process decomposes work packages into smaller components identified as activities to deliver those packages. |
Question 54 Explanation:
Work breakdown structure identifies the deliverables at their lowest level, which called packages, while define activities process decomposes work packages into smaller components identified as activities to deliver those packages. Other choices are made up.
[1 - 6.1 Project Time Management: Define Activities]
Question 55 |
Activity-on-the-node is the method of _____.
A | Constructing a visual diagram that uses nodes to indicate logically related communications between project members and stakeholders. In other words, this called rolling wave planning. |
B | Constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. In other words, this called precedence diagramming method. |
C | Constructing a visual diagram that uses nodes to indicate logically related requirements and risks on the project. In other words, this called bottom-up estimation. |
D | Constructing a visual diagram that uses nodes to indicate logically related requirements. In other words, this called relational arrowing method. |
Question 55 Explanation:
Activity-on-the-node is the method of constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. In other words, this called precedence diagramming method.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 56 |
What tools and techniques to be used by project manager while defining sequence activities?
A | Precedence diagramming method. |
B | All choices are right. |
C | Dependency determination. |
D | Applying leads and lags, and schedule network templates. |
Question 56 Explanation:
Precedence diagramming method, Precedence diagramming method, applying leads and lags, and schedule network templates are tools and techniques to be used while defining sequence activities.
[1 - 6 Project Time Management]
Question 57 |
What information needs to be updated that resulted by control schedule process?
A | Project management plan and change requests. |
B | All choices are right. |
C | Organizational process assets. |
D | Work performance measurements. |
Question 57 Explanation:
All choices are right. All listed here information needs to be updated when Control Schedule is completed.
[1 - 6 Project Time Management]
Question 58 |
What rules are used in heuristic technique?
A | General of luck. |
B | Law Murphy. |
C | God's wish. |
D | Rule of thumb. |
Question 58 Explanation:
Rule of thumb is a heuristic technique. An example is rule 80/20, which states that 80% of problems come from 20% of sources. Another example... 10 per cent of project time should be allocated to project closing. Such parametric estimation may become heuristic.
Question 59 |
What range of the estimate for an activity with expected duration at least 10 days, the worse 18 days, but more likely 15 days to complete?
A | 14,0
+/- 1.33 |
B | 15.97
+/- 1.78 |
C | 14.67
+/- 1.33 |
D | 5.97
+/- 1.23 |
Question 59 Explanation:
PERT uses the following formulas and calculations...
Expected Activity Duration
(P+4M+O) / 6 = (18+4*15+10) / 6 = 14.666;
Activity Standard Deviation
P-O / 6 = 18-10 / 6 = 1.333;
Activity Variance
(P-O)**2 / 6 = 1.777 (wasn't asked in this question)
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 60 |
What tools and techniques to be used for effective estimate activity duration?
A | Decomposition, rolling wave planning, analogous, parametric, three point estimates, and reserve analysis. |
B | Expert judgement, analogous, parametric, three point estimates, and reserve analysis. |
C | All choices are right. |
D | Expert judgement, peer review, Delphi method, five point estimates, and reverse analysis. |
Question 60 Explanation:
Expert judgement, analogous, parametric, three point estimates, and reserve analysis are tools and techniques that used for Estimate Activity Duration.
Question 61 |
What process approves or rejects changes?
A | Integrated change management system. |
B | Integrated change control. |
C | Change management plan. |
D | Configuration management process. |
Question 61 Explanation:
Integrated change control process approvals or rejects for changes.
Question 62 |
What is the most common method of network diagramming used these days?
A | Dependency determination. |
B | Graphic evaluation and review technique (GERT). |
C | Arrow diagramming method (ADM). |
D | Precedence diagramming method (PDM) or Activity-on-Node (AON). |
Question 62 Explanation:
Precedence diagramming method (PDM) or Activity-on-Node (AON) is the right answer.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 63 |
What is the primary task of a project manager before project execution?
A | Create a realistic project plan. |
B | Create project charter. |
C | Ensure all efforts will be paid. |
D | Receive budget to cover project's expenses. |
Question 63 Explanation:
All choices are right in general, but the PRIMARY role of a project manager is create a REALISTIC project management plan PRIOR to project execution.
[PMBOK. Project Time Management.]
Question 64 |
What project scheduling methodology defines?
A | Thresholds that project schedule can reach at the end of the project. |
B | Defines the beginning end, and milestone dates of the project. |
C | Defines the beginning and end dates of the project. |
D | Rules and approaches for scheduling process. |
Question 64 Explanation:
Scheduling methodology defines rules and approaches for scheduling process.
[1 - 6 Project Time Management]
Question 65 |
A new project manager just joint a company and wonders what scheduling tool to be used. What is the best place to find this information?
A | Enterprise environment factors. |
B | PMO. |
C | Ask other project managers. |
D | Technical department. |
Question 65 Explanation:
Scheduling tool that used in the company is usually listed in the enterprise environment factors that need to be obtained in the project initiation.
[1 - 6 Project Time Management]
Question 66 |
What part of organizational process assets can help in improving estimates?
A | Industry standards. |
B | Historical information. |
C | Templates. |
D | Processes. |
Question 66 Explanation:
Historical information is a valuable resource of organizational process assets for estimating, based on experiences on previous projects.
Question 67 |
What a project manager should check regarding schedule when analyses change request?
A | If the requested change impacts scope. |
B | If the change impacts critical path. |
C | How many activities requires impacted the change. |
D | How the change in schedule impacts costs. |
Question 67 Explanation:
While analyzing change request project manager needs to check if the change impacts critical path.
Question 68 |
What negative float indicates?
A | Project has been compressed. |
B | Project is ahead of plan. |
C | Project behinds. |
D | Project is on schedule. |
Question 68 Explanation:
Negative float indicates that project is behind of schedule.
Question 69 |
What you should concern about when applying fast track to selected project activity for the purpose of schedule compression?
A | The selected activity is in preferred logic. |
B | The selected activity has discretionary dependency. |
C | Risks and availability of resources for performing activities concurrently. |
D | All choices are right. |
Question 69 Explanation:
Discretionary dependency, preferred or soft logic all refer to an activity that has options to be performed in different sequences. Also, while the work will be done in parallel with other activity, availability of resources is critical. Accordingly, Fast Track may also add risks and more management efforts to manage parallel tasks.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 70 |
How many types of logical relations the precedence diagramming method has?
A | Six. |
B | Eight. |
C | Four. |
D | Two. |
Question 70 Explanation:
Precedence diagramming method has four logical types of relations between nodes: finish-to-start, finish-to-finish, start-to-start, start-to-finish.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 71 |
What information the activity attributes provide?
A | Activity attributes provide list of components to be implemented with each package. |
B | Activity attributes provide more details for each of multiple components associated with each activity. |
C | Activity attributes provide description of the pack in whole. |
D | Activity attributes provide details for each work package . |
Question 71 Explanation:
Activity attributes provide more details for each of multiple components associated with each activity.
[1 - 6.1.3 Define Activities: Output]
Question 72 |
What you should concern about when an earlier planned activity has been discarded for the purpose of schedule compression?
A | Scope. |
B | Time. |
C | Resource availability. |
D | Cost. |
Question 72 Explanation:
You should concern about Scope, when an earlier planned activity has been cancelled for the purpose of schedule compression. In addition, while this may save time and cost, it possible impacts customer satisfaction.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 73 |
How much float critical paths usually has?
A | Zero. |
B | Maximum two. |
C | One. |
D | Maximum one. |
Question 73 Explanation:
Usually critical paths does not have floats (slacks).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 74 |
What does duration critical path identify?
A | Longest duration path defines longest time to complete project. |
B | Longest duration path defines longest time to complete project. |
C | Shortest duration path defines shortest time to complete project. |
D | Longest duration path defines shortest time to complete project. |
Question 74 Explanation:
Longest duration path defines shortest time to complete project.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 75 |
When control schedule is used?
A | As the project activities are being completed. |
B | As the project activities are being performed. |
C | As the project activities are being rejected. |
D | As the project activities have generated a change request. |
Question 75 Explanation:
Control Schedule process is used when the project activities are being performed to ensure completion of work on planned schedule.
[1 - 6 Project Time Management]
Question 76 |
What needs to be done if it is hard to estimate a work package?
A | Decompose to activities. |
B | Use double numbers and create reserve. |
C | Use analogous estimation to a similar package. |
D | Reserve extra budget for contingency. |
Question 76 Explanation:
Work packages need to be decomposed to activities, which to be estimated. Estimation of smaller work components is more accurate.
Question 77 |
What criteria need to be met for successful crashing selected activities of a project for the purpose of schedule compression?
A | Risks and budget. |
B | Resources and budget. |
C | Quality and resources. |
D | Risks and resources. |
Question 77 Explanation:
Resources and budget are two major concerns when crashing activities of the project for schedule compressing. Crashing always increases costs, whether by adding more resources, more experienced (means more expensive) resources, or purchasing more advanced tools. In addition, more management time may require to manage Crashing.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 78 |
Baselines for scope, cost, and time should not be changed unless _____?
A | Functional manager's request. |
B | Sponsors request. |
C | Approved change. |
D | Stakeholders request. |
Question 78 Explanation:
Baselines for scope, cost, and time should not be changed unless the change is approved?
Question 79 |
What information is required to develop project schedule?
A | List of requirements, work breakdown structure, and estimate activity resources. |
B | Project charter, List of requirements, work breakdown structure, estimate activity resources, and estimate activity duration. |
C | Project scope, finalized requirements, sequence activities, estimate activity resources, and estimate activity duration. |
D | Outputs from processes to define and sequence activities, estimate activity resources, and estimate activity duration. |
Question 79 Explanation:
Outputs from processes to define and sequence activities, estimate activity resources, and estimate activity duration are needed to develop project schedule.
[1 - 6 Project Time Management]
Question 80 |
What information is needed to perform control schedule process?
A | Project schedule that requested by stakeholders. |
B | Project scope time constrains. |
C | Milestone that approved by project sponsor. |
D | Finalized and approved schedule, which is used as a baseline. |
Question 80 Explanation:
Finalized and approved schedule, which is used as a baseline, is needed to perform control schedule process.
[1 - 6 Project Time Management]
Question 81 |
What processes include time management project knowledge area?
A | Develop and control schedule. |
B | Estimate activity resources and activity durations. |
C | All choices are right. |
D | Define and sequence activities. |
Question 81 Explanation:
All the listed processes are the part of the Time Management: define activities, sequence activities, estimate activity resources, estimate activity duration, develop schedule, and control schedule.
[PMBOK. Project Time Management]
Question 82 |
A project manager estimates duration of an activity with a team member. After discussions, they found that an activity with similar complexity and business requirements, was performed on previous project. So they planned the same amount of time for the activity on their project. What method was used?
A | Parametric estimating. |
B | Analogous estimating. |
C | Three-point estimates. |
D | Expert judgement. |
Question 82 Explanation:
Analogous Estimating are usually top-down; although, can be the high-level and definitive. In this situation, the details of the activity were compared, such as complexity, functionality, etc. The Parametric Estimating would be the choice if statistical information from previous projects, as number of time units would be used. Other choices also related to the tool and techniques for Estimate Activity Duration, but not a suitable choice here.
[1 - 6.4.2 Estimate Activity Duration: Tools and
Techniques]
Question 83 |
Project manager starts to develop schedule. What documents needs to be completed for this work?
A | Activity resource requirements, resource calendars, activity duration estimate. |
B | Activity list, activity attributes, project schedule diagram. |
C | Enterprise environmental factors and Organizational process assets. |
D | All choices are right. |
Question 83 Explanation:
All choices are right. All the listed documents are needed to develop schedule.
[1 - 6 Project Time Management]
Question 84 |
What method is used to avoid not linear (up-and-down) use of resources?
A | Economic model. |
B | Calendar stabilizing. |
C | Resource leveling. |
D | Activity crashing. |
Question 84 Explanation:
Resource leveling technique is used to stabilize use of resources. The longer project duration is an option to stabilize usage of resources on the project, instead hiring resources for shorter periods, releasing them and hiring back, when needed. This also may save cost of procurement and reduce risk for spending extra effort for training and/or knowledge transfer.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 85 |
How does the Finish-to-Finish (FF) relations work?
A | The activity must finish before the next predecessor can start. |
B | The completion of successor depends on completion of predecessor. |
C | The activity cannot start before the next activity can finish. |
D | The activity must finish before the next activity can start. |
Question 85 Explanation:
The completion of successor depends on completion of predecessor. In other words, the activity must finish before the related activity finished.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 86 |
How to find project duration using PERT?
A | PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances. |
B | Sum of PERT estimates of all activities, plus or minus square root of the sum of active variances. |
C | PERT estimate for each activity, plus or minus square root of the sum of active variances. |
D | Sum of PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances. |
Question 86 Explanation:
Sum of PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances is a formula for calculate estimate of project duration.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 87 |
To estimate duration of a work package, after discussion with a team, a project manager decided to use the average number of hours spent on similar work in previous projects. What method the project manager used?
A | Expert judgement. |
B | Three-point estimates. |
C | Analogous estimating. |
D | Parametric estimating. |
Question 87 Explanation:
Two signs refer here to Parametric Estimating. Statistical information from previous projects, and especially number of hours per work. The analogous estimating would be the choice if the details of the work would be comparing, such as duration, complexity, etc. Analogous Estimating are usually top-down; although, can be the high-level and definitive. Other choices also related to the tool and techniques for Estimate Activity Duration, but not a suitable choice here.
[1 - 6.4.2 Estimate Activity Duration: Tools and
Techniques]
Question 88 |
What information from similar previous projects usually used with analogous estimating method?
A | Duration, quality, risks, efforts, and complexity. |
B | Duration, budget, size, weight, and complexity. |
C | Costs, budget, time, resource requirements, and organizational assets. |
D | Efforts, costs, location, and customer satisfaction. |
Question 88 Explanation:
Duration, quality, risks, efforts, and complexity - these parameters usually used for analogous estimation (top-down).
[1 - 6.4.2. Estimate Activity Duration: Tools and Techniques]
Question 89 |
A project manager performs control schedule referring to project management plan, project schedule, work performance data, and _____?
A | Enterprise environmental factors and list of activities. |
B | Enterprise environmental factors and organizational process assets. |
C | Project calendars, schedule data and organizational process assets. |
D | Enterprise environmental factors, organizational process assets and requirements documentation. |
Question 89 Explanation:
Project management plan, project schedule, work performance data, project calendars, schedule data, and organizational process assets are inputs to Control Schedule process.
[PMBOK. Project Time Management, Control Schedule]
Question 90 |
A project manager has finalized scope baseline and started to define activities using company's templates and procedures. What is missing to complete the work?
A | Activity list. |
B | Requirements documentation. |
C | Enterprise environmental factors. |
D | Organizational process assets. |
Question 90 Explanation:
Scope Baseline, Organizational Process Assets, and Enterprise Environment Factors are the input to Define Activities process.
[1 - 6 Project Time Management]
Question 91 |
What information the network diagram adds for develop schedule process?
A | The sequence of work will be processed. |
B | Duration of each activity. |
C | Description of work packages to be done. |
D | Detailed description of work to be done. |
Question 91 Explanation:
Network diagram provides the sequence of work will be processed for the develop schedule process.
[1 - 6.5 Develop Schedule]
Question 92 |
Using PERT you have identified 30% of standard deviation in one of the parts on your project. Will you outsource this work with fix-price contract?
A | Yes, the scope clarity an be improves using scope management plan. |
B | No, the scope of work is not clear. |
C | Yes, it is a normal range of standard deviation for fixed-price contracts. |
D | No, work with standard deviation should not be outsources. |
Question 92 Explanation:
This is a cross-knowledge question requires deep understanding of scope, time and procurement areas of project management. The recommenced topic to start is PERT.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 93 |
What tools and techniques to be used by project manager while estimating activity resources?
A | Project management software. |
B | Published estimation data and bottom-up estimation. |
C | All choices are right. |
D | Expert judgement and alternative analysis. |
Question 93 Explanation:
All choices are right. Expert judgement and alternative analysis, published estimation data, bottom-up estimation, and project management software are tolls and techniques used in estimate activity resources.
[1 - 6 Project Time Management]
Question 94 |
What technique applies with three-point estimation?
A | Program evaluation and review technique. |
B | Moving average estimate. |
C | Wave based estimation technique. |
D | Exponential smoothing technique. |
Question 94 Explanation:
Program Evaluation and Review Technique (PERT) is applied with Three_Point Estimate technique.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 95 |
How does the Finish-to-Start (FS) relations work?
A | The activity must finish before the next activity can start. |
B | The activity cannot start before the next activity can finish. |
C | The activity must finish before the next predecessor can start. |
D | The activity cannot finish before the next activity start. |
Question 95 Explanation:
Finish-to-star relations prescribes that the activity must finish before the next activity can start.
Question 96 |
What can be used to show the interdependency between activities through the whole project?
A | Project scope statement. |
B | List of activities. |
C | Work breakdown structure. |
D | Network diagram. |
Question 96 Explanation:
Network diagram shows interdependency of the activities through the whole project.
[1 - 6.2 Sequence Activities]
Question 97 |
What is the role o project manager in estimation process?
A | Verify is the provided estimation is realistic and avoid padding. |
B | Define reserve and document the assumption made during estimation. |
C | Provide the team with enough information and required level of accuracy to provide proper estimation. |
D | All choices are right. |
Question 97 Explanation:
All choices are right, that's what project manager is entitled to do during estimation process.
Question 98 |
Baselines for scope, cost, and time should not be changed unless _____?
A | Functional manager's request. |
B | Sponsors request. |
C | Approved change. |
D | Stakeholders request. |
Question 98 Explanation:
Baselines for scope, cost, and time should not be changed unless the change is approved?
Question 99 |
What tools and techniques project manager should use to develop schedule effectively?
A | Schedule compression and scheduling tool. |
B | All choices are right. |
C | Schedule network analysis, critical path method, critical chain method. |
D | Resource leveling, what-if scenario analysis, applying leads and lags. |
Question 99 Explanation:
All choices are right, as all the listed tools and techniques are needed to develop schedule effectively.
Question 100 |
What you should focus on while re-estimating activities for the purpose of schedule compression?
A | Resource availability. |
B | Quality. |
C | Risks. |
D | Costs. |
Question 100 Explanation:
While re-estimating activities for the purpose of schedule compression you should focus on risks.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 101 |
What needs to be done after a schedule baseline of the project is developed?
A | Develop schedule. |
B | Develop network diagram. |
C | Approved by a project management team. |
D | Approved by customer. |
Question 101 Explanation:
Schedule baseline needs to be accepted and approved by a project management team including both baselines for start and finish dates. The schedule baseline is a part of project management plan.
[1 - 6.5.3 Develop Schedule: Outputs]
Question 102 |
How the total float and free float are different?
A | Total float defines the time that an activity can be delayed without delaying of its predecessor, while free float defines the time and activity can delay without delaying start date of the project. |
B | Total float defines the time that an activity can be delayed without delaying of its successor, while free float defines the time and activity can delay without delaying start date of the project. |
C | Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its predecessor. |
D | Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its successor. |
Question 102 Explanation:
Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its successor. In addition, the project float is the amount of time that project can delay without delaying other related projects.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 102 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
| 1 | 2 | 3 | 4 | 5 |
| 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 |
| 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 |
| 31 | 32 | 33 | 34 | 35 |
| 36 | 37 | 38 | 39 | 40 |
| 41 | 42 | 43 | 44 | 45 |
| 46 | 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 | 55 |
| 56 | 57 | 58 | 59 | 60 |
| 61 | 62 | 63 | 64 | 65 |
| 66 | 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| 76 | 77 | 78 | 79 | 80 |
| 81 | 82 | 83 | 84 | 85 |
| 86 | 87 | 88 | 89 | 90 |
| 91 | 92 | 93 | 94 | 95 |
| 96 | 97 | 98 | 99 | 100 |
| 101 | 102 | End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!