PM - Project Management Processes
Project management is the application of knowledge, skills, tools, and techniques to project activities to meet project requirements. This application of knowledge requires the effective management of appropriate processes.
Start
Congratulations - you have completed PM - Project Management Processes.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
The project requirements have been finalized and project manager received sign off for project scope statement. What would be the best to do next?
A | Plan communications. |
B | Determine team. |
C | Create measurable objectives. |
D | Determine what to purchase. |
Question 1 Explanation:
Determine what to purchase.
Question 2 |
Which of the following activities execute in project closing phase?
A | Provide functional manager with team members performance evaluation. |
B | Complete lessons learned knowledge base. |
C | Ask team to complete lessons learned knowledge base. |
D | Ask stakeholder to update lessons learned knowledge base. |
Question 2 Explanation:
Ask stakeholder to update lessons learned knowledge base.
Question 3 |
Project manager completed subdividing project deliverables and project work into smaller, more manageable components. Description of such work components as work packages and control accounts has been finished too. What should be done next to create network diagram.
A | Determine what to purchase. |
B | Create activity list. |
C | Estimate resource requirements. |
D | Determine team. |
Question 3 Explanation:
After create WBS and WBS dictionary but before create network diagram, create activity list should be completed.
Question 4 |
What is the principal objective of the project stakeholder management?
A | Protecting project from unnecessary changes. |
B | Maintain goodwill in case of overrun budget or schedule. |
C | Thwart criticism of the project. |
D | Identifying all potential users. |
Question 4 Explanation:
The project manager must be vigilant in ensuring that stakeholders continuously support the project. The project manager must take quick action to ensure that the project objectives will be met and that a plan is in place to mitigate the influence and actions of negative stakeholders. [Planning]
Question 5 |
Integrated change control is the part of monitoring and controlling process group. What other processes associated with this activity?
A | Acquire approval of change and authorization to perform work. |
B | Influence factors that cause changes, Change request approval, informing stakeholders about changes. |
C | Request change, get approval for work, acquire a team to complete change. |
D | Implement change, perform quality assurance after change is completed, informing stakeholders about changes. |
Question 5 Explanation:
Influence factors that cause changes, change request approval, informing stakeholders about changes are processes associated with change in the monitoring and control process group. Other answers are mixed or related to project executing process group.
Question 6 |
A project manager has determined quality standards, processes, and metrics what would be the next task to do?
A | Create process improvement plan. |
B | Estimate time and cost. |
C | Perform quality assurance. |
D | Develop budget. |
Question 6 Explanation:
The right sequence is: create activity list > develop schedule > develop budget > determine quality standards processes, and metrics. The process of perform quality assurance belongs to executing process group, not to planning.
[2 - Rita's Process Chart]
Question 7 |
Create activity list, create network diagram, estimate resource requirements, estimate time and cost, determine critical path, develop budget. What is missing in this sequence?
A | Develop schedule. |
B | Plan communication. |
C | Determine all roles and responsibilities. |
D | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
Question 7 Explanation:
The right sequence is: create activity list > estimate time and cost > determine critical path > develop schedule > develop budget.
[2 - Rita's Process Chart]
Question 8 |
What of the following processes used during project initiation?
A | Develop project charter, determine quality standards, processes and metrics, determine team. |
B | Create measurable objectives, develop project charter, identify stakeholders, develop stakeholders management strategy. |
C | Select project manager, determine quality standards, processes and metrics, create project scope statement. |
D | Create measurable objectives, develop project charter, identify stakeholders, develop stakeholders management strategy, determine how you will do planning. |
Question 8 Explanation:
Create measurable objectives, develop project charter, identify stakeholders, develop stakeholders management strategy - all the part of the project initiation group.
[2 - Rita's Project Chart]
Question 9 |
What process group looks after informing stakeholders about approved changes?
A | Executing. |
B | Monitoring and controlling |
C | Communicating. |
D | Planning. |
Question 9 Explanation:
Project manager performs monitoring and controlling type of activity when informs stakeholders about approved changes.
Question 10 |
Project manager forecasts the project performance. In which process group this activity is?
A | Planning. |
B | Monitoring and controlling. |
C | Closing. |
D | Executing. |
Question 10 Explanation:
Project manager forecasting is a part of the monitoring and controlling process group.
Question 11 |
What is the last task of in the planning process group?
A | Complete procurement documentation. |
B | Gain formal approval of the plan. |
C | Perform iterations for risk identification. |
D | Hold kickoff meeting. |
Question 11 Explanation:
Hold kickoff meeting.
Question 12 |
Project manager works on change request, manages the reserves of time, cost and contingencies. What type of process the project manager performs?
A | Initiating. |
B | Executing. |
C | Monitoring and controlling. |
D | Planning. |
Question 12 Explanation:
Project manager manages reserves. This type of activities belongs to monitoring and controlling process group.
[1 - Time, Cost and Risk Management - search for "reserve analysis" and "reserves"]
Question 13 |
The project requirements have been finalized. What project manager should do before determining the team?
A | Create project scope statement and determine what to purchase. |
B | Develop schedule. |
C | Create activity list and network diagram. |
D | Estimate resource requirements. |
Question 13 Explanation:
The sequence is the following:
create project scope statement then determine what to purchase, and then determine the team.
[2 - Rita's Process Chart]
Question 14 |
When the product scope should be produced?
A | During project initiation. |
B | During project execution. |
C | Project manager looks after project scope, not product scope. |
D | During project planning. |
Question 14 Explanation:
Product scope produced during project execution.
Question 15 |
Significant change in the product scope has been approved for implementation. What project manager needs to do first?
A | Create implementation plan. |
B | Manage configuration. |
C | Achieve common understanding of the change. |
D | Execute change as approved. |
Question 15 Explanation:
First, project manager needs to ensure common understanding of the change.
Question 16 |
What that means performing the work according to the project management plan?
A | Perform monitoring and controlling. |
B | Closing the project phase or project. |
C | Executing the project. |
D | Initiating the project or phase. |
Question 16 Explanation:
This activity belongs to executing process group; the answer is executing the project.
Question 17 |
During which part of a project the most conflicts usually happen and require resolve?
A | Closing. |
B | Execution. |
C | Planning. |
D | Initiation. |
Question 17 Explanation:
The most conflicts on a project usually happen during project execution and require facilitation.
Question 18 |
When the work authorization system is used?
A | Work authorization system is used when selecting vendors. |
B | During project execution. |
C | Work authorization system is used while monitoring and controlling the project. |
D | When the product scope is authorized. |
Question 18 Explanation:
Work authorization system is used during project execution.
Question 19 |
What reference can be used in project performance measurement?
A | Stakeholder and customer satisfaction. |
B | The metrics determined by customer. |
C | The metrics determined by project manager. |
D | Approved requirements, project and products scope statements. |
Question 19 Explanation:
Project manager may determined the metrics for project performance measurement.
Question 20 |
Estimate resource requirements, estimate time and cost, determine critical path. What task misses in this sequence?
A | Estimate time and cost. |
B | Create process improvement plan. |
C | Determine quality standards, processes, and metrics. |
D | Create activity list. |
Question 20 Explanation:
Estimate time and cost is missing. The right sequence: estimate resource requirements > estimate time and cost > determine critical path, develop budget.
[2 - Rita's Process Chart]
Question 21 |
What task should be done right before estimate time and cost, and determine critical path?
A | Create activity list. |
B | Develop schedule. |
C | Estimate resource requirements |
D | Determine team. |
Question 21 Explanation:
Estimate resource requirements should be done right before the estimate time and cost > determine critical path.
[2 - Rita's Process Chart]
Question 22 |
What input should be used in project initiation processes?
A | Industry standards, list of vendors. |
B | List of risks, risk management plan, risk audit. |
C | Communication plan, stakeholder management plan. |
D | Historical information, company change control system, industry standards. |
Question 22 Explanation:
Historical information, company change control system, industry standards - all are part of Project Initiation Group.
[2 - Rita's Project Chart]
Question 23 |
What project processes group helps to determine variances and may initiate change requests.
A | Planning. |
B | Monitoring and controlling. |
C | Executing. |
D | Closing. |
Question 23 Explanation:
Monitoring and controlling process group is looking after initiation of change requests.
Question 24 |
While executing the work, project manager received three requests. The project sponsor asks for insignificant change that doesn't affect the time or cost, but may significantly enhance user experience. A group of stakeholders requested new functionality that changes business logic of the product, significantly reduces the project cost, brings new opportunities and meets company's strategic plans. Change management committee approved the change originated from customer, although this change does not add much value to the company. Which of these changes have to be implemented?
A | Implement all three changes, because all of them make sense. |
B | Implement only approved changes. |
C | Sponsor pays money so their request has highest priority and has to be implemented. |
D | Request from a group of stakeholders represents the interests of all the company, majority of stakeholders and end users. Also, this group of stakeholders is most influential in the company. |
Question 24 Explanation:
It is project manager's responsibility to implement only approved changes.
Question 25 |
Some project managers complained about issues of managing resources, others mentioned issues to communicate with stakeholders. What advantages brings matrix project organization.
A | Resources assigned full time on the project. |
B | Easier manage communications. |
C | Two bosses accountable for project delivery. |
D | Highly visible project objectives. |
Question 25 Explanation:
Highly visible project objectives is the correct choice. Both functional and project managers have the same objectives to deliver project results. In strong matrix organization project manager has more power on the project, in week - functional manager, and in balanced both are equal. This question also contains distracting information.
Question 26 |
After completing of which planning task it is recommended to perform iterations of the previous tasks?
A | Create measurable objectives. |
B | Prepare procurement documents. |
C | Identify stakeholders. |
D | Perform risk identification. |
Question 26 Explanation:
It is recommended to perform iterations after risk identification, qualitative and quantitative risk analysis, and risk response planning.
[1 - 3.1 Common project management process interactions]
Question 27 |
Which of the following activities belong to project closing phase?
A | User manuals of the product need to be published. |
B | Hand off completed product. |
C | Document all changes done during course of the project. |
D | The product results need to be archived and stored. |
Question 27 Explanation:
Hand off completed product.
Question 28 |
What project manager know before develop schedule?
A | Critical path. |
B | Project budget. |
C | Estimate time and cost. |
D | Determine team. |
Question 28 Explanation:
The right sequence is: create activity list > create network diagram > estimate resource requirements > estimate time and cost > determine critical path > develop schedule.
[2 - Rita's Process Chart]
Question 29 |
What should be used in project initiating?
A | Business case, product description, or known products requirements, product scope. |
B | Requirements for project team. |
C | Stakeholders management strategy. |
D | Project plan. |
Question 29 Explanation:
What is the project being asked to do? Business case, product description, or known products requirements, product scope.
[2 - Rita's Project Chart]
Question 30 |
A project manager determined the longest chain in executing of project packages, while was not able avoid two significant floats. What next should be done?
A | Create activity diagram. |
B | Develop schedule. |
C | Determine team. |
D | Revise requirements. |
Question 30 Explanation:
The right sequence is: create activity list > create network diagram > estimate resource requirements > estimate time and cost > determine critical path > develop schedule.
[2 - Rita's Process Chart]
Question 31 |
A project manager plans communications. What previous task he worked on?
A | Determine all roles and responsibilities. |
B | Determine quality standards, processes, and metrics. |
C | Prepare procurement documents. |
D | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
Question 31 Explanation:
Plan communications is following after determine all roles and responsibilities.
[2 - Rita's Process Chart]
Question 32 |
What follows after create process improvement plan?
A | Determine all roles and responsibilities. |
B | Develop schedule. |
C | Develop budget. |
D | Determine team. |
Question 32 Explanation:
Determine all roles and responsibilities should be done after process improvement plan.
Question 33 |
It is required that project team must..
A | Implement approved changes, defect repair, preventive and corrective actions. |
B | Divide project into more manageable components. |
C | Comply with requirements to meet stakeholder needs and expectations. |
D | Determine variances and of the warrant corrective action o a change. |
Question 33 Explanation:
In order for a project to be successful, the project team must comply with requirements to meet stakeholder needs and expectations.
Question 34 |
What project manger does when generates change requests?
A | Creates project plan. |
B | Executes project. |
C | Uncovers requirements during project initiation. |
D | Performs monitoring and controlling. |
Question 34 Explanation:
Change request usually generate during project execution. It means the planning phase has been completed, the requirements and project plan have been already signed off.
Question 35 |
What project manager should be done before estimate time and cost?
A | Determine critical path. |
B | Create activity list. |
C | Estimate resource requirements. |
D | Determine critical path. |
Question 35 Explanation:
The right sequence is: create activity list > create network diagram > estimate resource requirements > estimate time and cost > determine critical path.
[2 - Rita's Process Chart]
Question 36 |
Which project process group represents the project performance measurement?
A | Executing. |
B | Planning. |
C | Monitoring and controlling. |
D | Closing. |
Question 36 Explanation:
Monitoring and controlling.
Question 37 |
Project manager holds meetings mostly with developers, quality assurance team and customers. What is the current stage of the project?
A | Planning. |
B | Closing. |
C | Execution. |
D | Initiation. |
Question 37 Explanation:
The current stage of the project is execution.
Question 38 |
What would be the best next step after stakeholder management strategy has been developed?
A | Finalize requirements. |
B | Determine how to do planning. |
C | Develop project charter. |
D | Create project scope statement. |
Question 38 Explanation:
Determine how to do planning is the first planning task project manager have to perform in the planning process group. This task delivers a development approach to all management plans.
Question 39 |
Project manager records issues into issues log. What is the current stage of the project?
A | Planning. |
B | Closing. |
C | Execution. |
D | Initiating. |
Question 39 Explanation:
The project is in executing stage, when the most issues are logged.
Question 40 |
What would you use during the project initiation?
A | Contracts, list of stakeholders, industry standards, information about company strategic plan. |
B | Communication plan, procurement plan, |
C | WBS and WBS dictionary. |
D | Project requirements. |
Question 40 Explanation:
Contracts, list of stakeholders, industry standards, information about company strategic plan refer to the input to the initiating process group.
[2 - Rita's Project Chart]
Question 41 |
What is the task following develop schedule?
A | Develop budget. |
B | Determine team. |
C | Determine critical path. |
D | Estimate time and cost. |
Question 41 Explanation:
The right sequence is: estimate time and cost > determine critical path > develop schedule > develop budget.
[2 - Rita's Process Chart]
Question 42 |
What type of activities project manager applies when validates assumptions, verifies if risk management policies been followed, and assesses the risks?
A | Executing. |
B | Monitoring and controlling. |
C | Project audit. |
D | Planning. |
Question 42 Explanation:
The described activity is monitoring and controlling risks that belongs to the monitoring and controlling process group.
[1 - Monitor and Control Risks]
Question 43 |
Administering procurements is the part of which process group?
A | Executing. |
B | Planning. |
C | Monitoring and controlling. |
D | Closing. |
Question 43 Explanation:
Administering procurements is the part of monitoring and controlling process group.
Question 44 |
Which of the following activities belong to project closing process group?
A | Execute project audit. |
B | Complete final report of the project performance. |
C | Reward the project team. |
D | Verify the project results against project charter. |
Question 44 Explanation:
Complete final report of the project performance.
Question 45 |
Project sponsor allocated a special fund for team-building activities. During which phase of the project these activities take place most often?
A | The project planning phase requires more communications with the project members; so, team-building activities the most important during planning period. |
B | It is important the most to support team at the end of the project. During the closing process it is required that the team will stay till to end to ensure all project activities have been completed. |
C | During project initiation, the team as getting together most often; so this is most important to support these activities from start. |
D | Most of the team-building activities happen during project execution. |
Question 45 Explanation:
Most of the team-building activities happen during project execution.
Question 46 |
Which of the following activities to be done in project closing?
A | Verify with stakeholders if all the project requirements have been addressed. |
B | Hold final meeting with the team. |
C | Release resources. |
D | Give recognitions and rewards. |
Question 46 Explanation:
Project resources have to be released at the end of the project.
Question 47 |
Which of the following activities belong to project closing process group?
A | Hold a final meeting with project team. |
B | Facilitate conflict resolution. |
C | Index and archive the project records. |
D | Inform stakeholders about project completion. |
Question 47 Explanation:
Index and archive the project records.
Question 48 |
Perform risk identification, qualitative and quantitative risk analysis, and risk response planning is one of the most important tasks. To which process group this task belongs?
A | Initiating. |
B | Executing. |
C | Planning. |
D | Monitoring and Controlling. |
Question 48 Explanation:
Planning.
[2 - Rita's Process Chart]
Question 49 |
Continuously improve project processes is the project management responsibility. When the project improvement takes place?
A | During project execution. |
B | Project improvement is the monitoring and controlling activities. |
C | Project improvement needs to be approached every time when the change is approved. |
D | Improvement of the project processes need to be done during project planning. |
Question 49 Explanation:
Project improvement performs during project execution.
Question 50 |
Project manager have difficulty to create a network diagram based on WBS and WBS dictionary. What activity is missing in this work?
A | Determine a list of work packages. |
B | Estimate time and cost. |
C | Create activity list. |
D | Finalize requirements. |
Question 50 Explanation:
Create WBS and WBS dictionary > Create activity list > Create network diagram
Question 51 |
During which phase of the project the process of managing people is most intensive?
A | During project initiation, because of so many communication required to coordinate all initial requirement between all stakeholders. |
B | During project closing - end users, sponsors and other stakeholders require the most communications and coordination. |
C | The process of managing people is most intensive during project execution. |
D | It is essential that project planning required the most intensive use of resources. There are many processes to be coordinated and so much information to be collected from different parties to ensure that requirements are finalized. |
Question 51 Explanation:
The process of managing people is most intensive during project execution.
Question 52 |
What process in planning group is iterative?
A | Estimate time and cost. |
B | Project management processes are iterative, and many processes are repeated during the project. |
C | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
D | Finalize requirements. |
Question 52 Explanation:
Project management processes are iterative, and many processes are repeated during the project.
[1 - 3.1 Common project management process interactions]
Question 53 |
What reference to be used in project performance evaluation?
A | Approved requirements, project and products scope statements are the references to evaluate project performance. |
B | Measure performance against the performance measurement baseline. |
C | Project quality, standards, processes and metrics to be used as the evaluation references. |
D | Comparing the current status with project schedule and planned budget. |
Question 53 Explanation:
Project performance measures against the performance measurement baseline.
Question 54 |
Ensuring project success and meeting project objectives, the team must..
A | Coordinate project schedule with customer. |
B | Schedule and hold progress meetings. |
C | Create WBS dictionary. |
D | Select appropriate processes required to meet the project objectives. |
Question 54 Explanation:
In order for a project to be successful, the project team must select appropriate processes required to meet project objectives.
Question 55 |
During which part of the project vendors or suppliers should be selected?
A | Planning. |
B | Closing. |
C | Execution. |
D | Initiation. |
Question 55 Explanation:
Sellers should be selected during execution phase of the project.
Question 56 |
When the final team to be acquired?
A | Final team to be acquired after the project scope, project schedule, and all roles and responsibilities have been determined. |
B | During project execution. |
C | Final team to be acquired after the project schedule, and all roles and responsibilities have been determined. |
D | Final team to be acquired after all roles and responsibilities have been determined. |
Question 56 Explanation:
Final team to be acquired during project execution.
Question 57 |
After creating a network diagram and estimating resource requirements, a project manager has found that more information is needed to determine a longest chain of the tasks in the project. What was needed to be done?
A | Create activity list. |
B | Perform quality audit. |
C | Develop schedule. |
D | Estimate time and cost. |
Question 57 Explanation:
The right sequence is: create activity list > create network diagram > estimate time and cost > determine critical path.
Question 58 |
When formal approval of the plan should be received?
A | Before preform quality assurance. |
B | Before produce product scope. |
C | After the project management plan and performance measurement baseline are completed. |
D | After Preparation of procurement documents. |
Question 58 Explanation:
After the project management plan and performance measurement baseline are completed.
[2 - Rita's Process Chart]
Question 59 |
A project manager has completed developing schedule and budget. What needs to be done before determine all roles and responsibilities?
A | Create measurable objectives. |
B | Determine critical path. |
C | Create process improvement plan. |
D | Determine team. |
Question 59 Explanation:
The right sequence is: develop budget > determine quality standards, processes, and metrics > create process improvement plan > determine all roles and responsibilities.
[2 - Rita's Process Chart]
Question 60 |
Project manager analyses change requests. Some changes will be approved while most of them rejected. What type of activity the project manager performs?
A | Planning. |
B | Execute project. |
C | Monitoring and controlling. |
D | Performs project improvement. |
Question 60 Explanation:
Project manager performs monitoring and controlling processes.
Question 61 |
Project manager prepared procurement documents. What needs to be done next?
A | Determine "how to execute and control" parts of all management plans. |
B | Acquire resources. |
C | Plan communications. |
D | Develop final project management plan. |
Question 61 Explanation:
Determine "how to execute and control" parts of all management plans.
[2 Rita's Process Planning"
Question 62 |
What should be done next after completion of risk identification, qualitative and quantitative risk analysis, and risk response planning?
A | Prepare procurement documents. |
B | Plan communications. |
C | Perform iterations of previous steps. |
D | Request changes. |
Question 62 Explanation:
After performing risk identification, qualitative and quantitative risk analysis, and risk response planning go back iterations needs to be done in most cases. The identify risk is an iterative process because new risks may evolve or become know as the project progresses through the life cycle. The frequency of iteration and who participates in each cycle will vary by situation.
[1 -11.2 Identify Risks]
Question 63 |
Project manager communicates with customer and hold meeting in order to get approval for interim project deliverable. To which process group this activity belongs?
A | Initiating. |
B | Planning. |
C | Closing. |
D | Monitoring and controlling. |
Question 63 Explanation:
Gaining acceptance of interim project deliverable from the customer belongs to project monitoring and controlling process group.
Question 64 |
Which set of processes belongs to the project initiating group?
A | Determine what to purchase, collect historical information information, select project manager, determine quality standards, determine how you will do planning, create project scope statement. |
B | Select project manager, determine company culture, and existing systems, collect processes, and historical information. |
C | Collect historical information information, select project manager, determine quality standards, evaluate team and project performance, create project scope statement. |
D | Select project manager, determine quality standards, processes and metrics, create project scope statement. |
Question 64 Explanation:
Select project manager, determine company culture, and existing systems, collect processes, and historical information is the part for the initiating process group.
[2 - Rita's Project Chart]
Question 65 |
Which of the following activities execute in project closing phase?
A | Give recognitions and rewards. |
B | Confirm the project scope statement against the project charter. |
C | Update lessons learned. |
D | Hold final meeting with the team. |
Question 65 Explanation:
Update lessons learned is one of the tasks in closing process group.
Question 66 |
What type of processes should be performed to ensure the right version of changes to be implemented?
A | Executing. |
B | Planning. |
C | Monitoring and controlling. |
D | Creating activity list to ensure the right sequence of work. |
Question 66 Explanation:
Version control is the part of configuration management and relates to monitoring and controlling process group.
Question 67 |
Project manager estimates the required type and quantity of materials, people, equipment, or supplies to perform each activity. What process project manager works on?
A | Create procurement plan. |
B | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
C | Estimate Activity Resources. |
D | Determine what to purchase. |
Question 67 Explanation:
Estimate Activity Resources is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. In other words - estimate resource requirements.
[1 - 3.4.7 Estimate Activity Resources]
Question 68 |
Project manager compares the completed work with requirements. What type of process project manager executes?
A | Closing. |
B | Executing. |
C | Monitoring and controlling. |
D | Performing integrated change control. |
Question 68 Explanation:
This is the part of closing process group. The completed work needs to be confirmed against requirements.
Question 69 |
Estimate time and cost, determine critical path, develop schedule. What should be done next?
A | Create activity list. |
B | Determine quality standards, processes, and metrics. |
C | Develop budget. |
D | Determine quality standards, processes, and metrics. |
Question 69 Explanation:
Develop budget would be the next step in Planning Process Group.
[2 - Rita's Process Chart]
Question 70 |
Create network diagram, estimate resource requirements, estimate time and cost, develop schedule. What is missing in this sequence?
A | Develop schedule. |
B | Estimate time and cost. |
C | Develop schedule. |
D | Determine critical path. |
Question 70 Explanation:
The right sequence is create network diagram > estimate resource requirements > estimate time and cost > determine critical path > develop schedule.
Question 71 |
The project requirements have been finalized and project manager received sign off for project scope statement. What would be the best to do next?
A | Plan communications. |
B | Determine team. |
C | Determine what to purchase. |
D | Create measurable objectives. |
Question 71 Explanation:
Determine what to purchase.
Question 72 |
A project manager is going to determine quality standards, processes, and metrics. What task needs to be finished first?
A | Develop budget. |
B | Create WBS and WBS dictionary. |
C | Create process improvement plan. |
D | Estimate time and cost. |
Question 72 Explanation:
The task of develop budget should be completed prior to determine quality standards, processes, and metrics?
[2 - Rita's Process Chart]
Question 73 |
During what part of the work project manager exchanges with communications most often?
A | Initiation. |
B | Execution. |
C | Planning. |
D | Closing. |
Question 73 Explanation:
Most communications usually happen during project execution.
Question 74 |
How often project manager should evaluate the team and project performance?
A | Evaluation of the team and project performance needs to be done at least once per month throughout the project from initiation to closing. |
B | Evaluation of the team and project performance needs to be done throughout the course of the project from initiation to closing. |
C | Evaluation of the team and project performance should be performed during project execution to ensure the project success. |
D | Evaluation of the team and project performance needs to be done on weekly basis. |
Question 74 Explanation:
Evaluation of the team and project performance should be performed during project execution to ensure the project success. The frequency of evaluation depends on the duration, size and complexity of the project.
Question 75 |
Project manager reports the project performance on monthly basis. What type of process project manager performs?
A | Monitoring and controlling. |
B | Planning. |
C | Eecuting. |
D | Closing. |
Question 75 Explanation:
Project performance reporting is a part of the monitoring and controlling process group.
Question 76 |
In order for a project to be successful, the project team must:
A | Use a defined approach that can be adopted to meet requirements. |
B | Provide risk audit and facilitate conflict resolution. |
C | Develop closure procedures. |
D | Document assumptions and constrains. |
Question 76 Explanation:
In order for a project to be successful, the project team must use a defined approach that can be adopted to meet requirements.
Question 77 |
What needs to be done before create network diagram?
A | Finalize requirements. |
B | Create activity list. |
C | Estimate time and cost. |
D | Determine critical path. |
Question 77 Explanation:
The right sequence is: create activity list > create network diagram > estimate resource requirements > estimate time and cost > determine critical path.
[2 - Rita's Process Chart]
Question 78 |
What processes belong to the project initiating group?
A | Perform risk identification, quantitative and qualitative risk analysis, and risk response planning. |
B | Estimate time and costs. |
C | Determine critical path. |
D | Divide large projects into phases, understand business case, determine initial requirements and risks. |
Question 78 Explanation:
Divide large projects into phases, understand business case, determine initial requirements and risks are the part of the initiating process group.
[2 - Rita's Project Chart]
Question 79 |
It is required that project manager perform project audit. When this should be done?
A | Project audit is one of the project closing processes. |
B | It would be right to perform project audit in each phase throughout the project from initiation to closing. |
C | Project audit should be performed during project execution. |
D | Project audit is the part of project monitoring and controlling. |
Question 79 Explanation:
Project audit is the part of project execution.
Question 80 |
What type of activities the quality control is?
A | Quality control is executed to ensure the product or service quality and its metrics determined by the project manager. |
B | Quality control performed during project planning and closing. |
C | Executing. |
D | Monitoring and controlling. |
Question 80 Explanation:
Quality control belongs to monitoring and controlling process group.
Question 81 |
During project initiation project manager collected such project assets as processes, procedures. During the project execution, to expedite vendor selection, project manager whats to ease the process, but there is not enough time left to coordinate it with management. What project manager needs to do?
A | Follow the old process. |
B | Coordinate new idea with legal department. |
C | Discuss the new idea with technical leads and use it if they agree. |
D | Coordinate the new idea with potential vendors. |
Question 81 Explanation:
Use the old process until the new idea is well coordinated with subject mater specialists, legal department if needed and management.
Question 82 |
What does it mean perform control of the project?
A | Execute project auditing, maintaining issues log, and reporting status to the management. |
B | Keep team on short leash and communicate with stakeholders to ensure they satisfied with project results. |
C | Measure performance against the project metrics, continuously perform project improvement and evaluate team and project performance. |
D | Execute monitoring and controlling processes. |
Question 82 Explanation:
Execute monitoring and controlling processes.
Question 83 |
What input should be used for project initiating?
A | List of work packages. |
B | Project plan and product requirements. |
C | Project schedule. |
D | Information about company culture, major activities of the company related to the project, list of people who may be good team members. |
Question 83 Explanation:
Information about company culture, major activities of the company related to the project, list of people who may be good team members is a list of inputs for the project initiating group.
Question 84 |
What type of activities the quality assurance is?
A | Quality assurance is executed during measurement of performance against other metrics determined by the project manager. |
B | Monitoring and controlling. |
C | Executing. |
D | Quality assurance performs during project planning and closing. |
Question 84 Explanation:
Quality assurance performs during project execution.
Question 85 |
What should be used as an input in project initiation processes?
A | Stakeholders management strategy. |
B | Configuration plan. |
C | Determine what to purchase. |
D | Templates, historical estimates and WBSs, and communications with stakeholders. |
Question 85 Explanation:
Templates, historical estimates and WBSs, and communications with stakeholders can be a list of inputs for project initiation group.
[2 - Rita's Project Chart]
Question 86 |
Project team revises planning artifacts; determined a new critical path and planned scheduled. What would be the next task?
A | Determine role and responsibilities. |
B | Plan communications. |
C | Identify risks and develop risk response plan. |
D | Create project improvement plan. |
Question 86 Explanation:
Create project improvement plan is the right answer. This would be the next closest task available in the offered list.
Question 87 |
Create network diagram, estimate time and cost, determine critical path, develop schedule. What process is missing in this sequence?
A | Estimate resource requirements. |
B | Determine quality standards, processes, and metrics. |
C | Develop budget. |
D | Create process improvement plan. |
Question 87 Explanation:
The right sequence: create network diagram > estimate resource requirements > estimate time and cost > determine critical path > develop schedule.
Question 88 |
What should be done after develop final project management plan and performance measurement baseline?
A | Gain formal approval of the plan. |
B | Hold kickoff meeting. |
C | Determine what to purchase. |
D | Execute the work according to PM plan. |
Question 88 Explanation:
Formal approval of the plan should be received before providing a kickoff meeting.
Question 89 |
Project manager proceeds with procurement closure. What should be done first?
A | Inform stakeholders that project is completed. |
B | The formal acceptance of the project or phase is received. |
C | Release resources in order to reduce project cost. |
D | Confirm if the work was completed in accordance to the requirements. |
Question 89 Explanation:
Before the procurements will be closed, project manager needs to confirm the work was completed in accordance to the requirements.
Question 90 |
Rewarding motivates project members and increases their performance. During which part of the project motivation is most effective?
A | Motivation of the team is most effective during project closing, so people will stay to the end of the project. |
B | Motivation of the team is most effective during project initiation; so the team would feel appreciation during the rest of the project. |
C | Motivation of the team is most effective during project execution. |
D | Motivation of the team is most effective during project planning. |
Question 90 Explanation:
Motivation of the team is most effective during project execution.
Question 91 |
A project manager has estimated resources requirements and documented all roles and responsibilities. What is the next task?
A | Plan communications. |
B | Perform risk identification, qualitative and quantitative risk analysis, and risk response planning. |
C | Prepare procurement documents. |
D | Determine what to purchase. |
Question 91 Explanation:
Plan communications is the next step.
[2 - Rita's Process Chart]
Question 92 |
A project manager has determined quality standards, processes, and metrics. What would be the nest task?
A | Create activity list. |
B | Determine all oles and responsibilities. |
C | Create process improvement plan. |
D | Create network diagram. |
Question 92 Explanation:
The right sequence is: develop schedule > develop budget > determine quality standards, processes, and metrics > create process improvement plan.
[2 - Rita's Process Chart]
Question 93 |
Which of the following activities belongs to project monitoring and controlling process group?
A | Perform quality control. |
B | Perform quality audit. |
C | Determine quality standards, processes, and metrics. |
D | Perform quality assurance. |
Question 93 Explanation:
Perform quality control belongs to monitoring and controlling process group. The rest choices are from executing or planning process groups.
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 93 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
| 1 | 2 | 3 | 4 | 5 |
| 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 |
| 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 |
| 31 | 32 | 33 | 34 | 35 |
| 36 | 37 | 38 | 39 | 40 |
| 41 | 42 | 43 | 44 | 45 |
| 46 | 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 | 55 |
| 56 | 57 | 58 | 59 | 60 |
| 61 | 62 | 63 | 64 | 65 |
| 66 | 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| 76 | 77 | 78 | 79 | 80 |
| 81 | 82 | 83 | 84 | 85 |
| 86 | 87 | 88 | 89 | 90 |
| 91 | 92 | 93 | End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!