Development of this quiz is in progress.
PM - Time Management
Start
Congratulations - you have completed PM - Time Management.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
How the contingency plan is different from management reserve?
A | Contingency reserve is calculating to compensate schedule uncertainty for overall project, and can determine the schedule tolerance. |
B | Contingency reserve is calculating to compensate schedule uncertainty for overall project, and determined as firm as additional time to be spent for planned changes. |
C | Contingency reserve is calculating to compensate unknown unknowns schedule uncertainty for specific part of the project. |
D | Contingency reserve is calculating to compensate schedule uncertainty for specific part of the project. |
Question 1 Explanation:
Contingency reserve is calculating to compensate schedule uncertainty for overall project, and can determine the schedule tolerance.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .5 Reserve Analysis]. Contingency reserve discussed mo in Cost Management Chapter.
Question 2 |
What is the role o project manager in estimation process?
A | All choices are right. |
B | Verify is the provided estimation is realistic and avoid padding. |
C | Provide the team with enough information and required level of accuracy to provide proper estimation. |
D | Define reserve and document the assumption made during estimation. |
Question 2 Explanation:
All choices are right, that's what project manager is entitled to do during estimation process.
Question 3 |
After coordinating of the activity list, a project manager estimates activity resources. What he needs to complete the work?
A | Activity resources requirements. |
B | Resources breakdown structure. |
C | Project document updates. |
D | Activity attributes. |
Question 3 Explanation:
The Activity Attributes are missing along with resource calendars, enterprise environment factors and organizational process assets. All other choices are deliverables of the same process of Estimate Activity Resources.
[1 - 6.3 Estimate Activity Resources]
Question 4 |
To estimate duration of a work package, after discussion with a team, a project manager decided to use the average number of hours spent on similar work in previous projects. What method the project manager used?
A | Three-point estimates. |
B | Analogous estimating. |
C | Parametric estimating. |
D | Expert judgement. |
Question 4 Explanation:
Two signs refer here to Parametric Estimating. Statistical information from previous projects, and especially number of hours per work. The analogous estimating would be the choice if the details of the work would be comparing, such as duration, complexity, etc. Analogous Estimating are usually top-down; although, can be the high-level and definitive. Other choices also related to the tool and techniques for Estimate Activity Duration, but not a suitable choice here.
[1 - 6.4.2 Estimate Activity Duration: Tools and
Techniques]
Question 5 |
Using PERT you have identified 30% of standard deviation in one of the parts on your project. Will you outsource this work with fix-price contract?
A | No, the scope of work is not clear. |
B | Yes, the scope clarity an be improves using scope management plan. |
C | No, work with standard deviation should not be outsources. |
D | Yes, it is a normal range of standard deviation for fixed-price contracts. |
Question 5 Explanation:
This is a cross-knowledge question requires deep understanding of scope, time and procurement areas of project management. The recommenced topic to start is PERT.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 6 |
What can be used to support realistic schedule?
A | Crashing the schedule is the method for realistic planning of schedule. |
B | De-scoping is the method to sequence the project activities for realistic schedule. |
C | Lead and lags time between activities can be used to support realistic schedule. |
D | Lead and lags time usually used to leverage the schedule. |
Question 6 Explanation:
Lead and lags time between activities can be used to support realistic schedule.
[1 - 6.2 Sequence Activities]
Question 7 |
What does duration critical path identify?
A | Longest duration path defines shortest time to complete project. |
B | Longest duration path defines longest time to complete project. |
C | Shortest duration path defines shortest time to complete project. |
D | Longest duration path defines longest time to complete project. |
Question 7 Explanation:
Longest duration path defines shortest time to complete project.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 8 |
How activities and their properties are used on the project?
A | Provide information on how to execute the work packages. |
B | Provide information to measure the project performance in monitoring and controlling processes. |
C | Provide input to estimating, scheduling, executing, and monitoring and controlling of project work. |
D | Provide reference to the work planned for completion of the project. |
Question 8 Explanation:
Provide input to estimating, scheduling, executing, and monitoring and controlling of project work is the most completed answer to the question.
[1 - 6.1 Project Time Management: Define Activities]
Question 9 |
What information is documented in project schedule management plan?
A | Defines the beginning end, and milestone dates of the project. |
B | Thresholds that project schedule can reach during planning phase. |
C | Project management processes, tools and techniques. |
D | Defined the beginning and end dates of the project. |
Question 9 Explanation:
Project Schedule Management Plan is a part of Project Management Plan and describes the project management processes, tools and techniques to be used on the project.
[1 - 6 Project Time Management]
Question 10 |
What type of dependency called soft logic?
A | All choices are right. |
B | Discretionary dependency. |
C | Preferred dependency. |
D | External dependency. |
Question 10 Explanation:
Mandatory dependency in other words called had logic and represent the unavoidable dependency from the related activity. For example, an activity that must be done as per law requirement or corporate SDLC standard.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 11 |
A project manager estimates duration of an activity with a team member. After discussions, they found that an activity with similar complexity and business requirements, was performed on previous project. So they planned the same amount of time for the activity on their project. What method was used?
A | Expert judgement. |
B | Analogous estimating. |
C | Three-point estimates. |
D | Parametric estimating. |
Question 11 Explanation:
Analogous Estimating are usually top-down; although, can be the high-level and definitive. In this situation, the details of the activity were compared, such as complexity, functionality, etc. The Parametric Estimating would be the choice if statistical information from previous projects, as number of time units would be used. Other choices also related to the tool and techniques for Estimate Activity Duration, but not a suitable choice here.
[1 - 6.4.2 Estimate Activity Duration: Tools and
Techniques]
Question 12 |
Project manager starts to develop schedule. What documents needs to be completed for this work?
A | Enterprise environmental factors and Organizational process assets. |
B | Activity list, activity attributes, project schedule diagram. |
C | Activity resource requirements, resource calendars, activity duration estimate. |
D | All choices are right. |
Question 12 Explanation:
All choices are right. All the listed documents are needed to develop schedule.
[1 - 6 Project Time Management]
Question 13 |
What technique an be used for schedule network analysis?
A | What-if scenario analysis. |
B | All choices are right. |
C | Critical path and schedule compression. |
D | Resources leveling and critical chain method. |
Question 13 Explanation:
All these techniques are applicable to calculate the early and late start, and finish dates for the project activities.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 14 |
By completion of estimate duration activity project manager has to update project document with _____?
A | Activity duration estimate and schedule baseline. |
B | Activity duration estimate. |
C | Work performance measurements, activity duration estimate. |
D | Project schedule, activity duration estimate. |
Question 14 Explanation:
By completion of estimate duration activity project manager has to update project document with Activity Duration Estimate.
[1 - 6 Project Time Management]
Question 15 |
A project manager performs define activity process. What information this process delivers?
A | Description of project activities listed in ascending order. |
B | Identified specific actions and their details to reach planned quality of project deliverables. |
C | Identified specific actions and their details to produce project deliverables. |
D | A list of specified activities for implementing change using integrated change control system. |
Question 15 Explanation:
Define activities identifies specific actions and their details to produce project deliverables.
[1 - 6.1 Project Time Management: Define Activities]
Question 16 |
How to find project duration using PERT?
A | PERT estimate for each activity, plus or minus square root of the sum of active variances. |
B | PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances. |
C | Sum of PERT estimates of all activities, plus or minus square root of the sum of active variances. |
D | Sum of PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances. |
Question 16 Explanation:
Sum of PERT estimates for each activity on critical path, plus or minus square root of the sum of active variances is a formula for calculate estimate of project duration.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 17 |
What information the activity attributes provide?
A | Activity attributes provide more details for each of multiple components associated with each activity. |
B | Activity attributes provide details for each work package . |
C | Activity attributes provide description of the pack in whole. |
D | Activity attributes provide list of components to be implemented with each package. |
Question 17 Explanation:
Activity attributes provide more details for each of multiple components associated with each activity.
[1 - 6.1.3 Define Activities: Output]
Question 18 |
What are the objectives of schedule compression?
A | Prove the request for using management reserve. |
B | Optimize schedule to meet project or milestone deadline. |
C | Prove the request for using contingency reserve. |
D | Optimize schedule to meet project or milestone deadline without changing project scope. |
Question 18 Explanation:
Optimize schedule to meet project or milestone deadline without changing project scope.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 19 |
How the total float and free float are different?
A | Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its successor. |
B | Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its predecessor. |
C | Total float defines the time that an activity can be delayed without delaying of its successor, while free float defines the time and activity can delay without delaying start date of the project. |
D | Total float defines the time that an activity can be delayed without delaying of its predecessor, while free float defines the time and activity can delay without delaying start date of the project. |
Question 19 Explanation:
Total float defines the time that an activity can be delayed without delaying the project, while free float defines the time and activity can delay without delaying start date of its successor. In addition, the project float is the amount of time that project can delay without delaying other related projects.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 20 |
When control schedule is used?
A | As the project activities are being completed. |
B | As the project activities have generated a change request. |
C | As the project activities are being rejected. |
D | As the project activities are being performed. |
Question 20 Explanation:
Control Schedule process is used when the project activities are being performed to ensure completion of work on planned schedule.
[1 - 6 Project Time Management]
Question 21 |
What needs to be done if it is hard to estimate a work package?
A | Reserve extra budget for contingency. |
B | Use analogous estimation to a similar package. |
C | Use double numbers and create reserve. |
D | Decompose to activities. |
Question 21 Explanation:
Work packages need to be decomposed to activities, which to be estimated. Estimation of smaller work components is more accurate.
Question 22 |
What you should focus on while re-estimating activities for the purpose of schedule compression?
A | Resource availability. |
B | Risks. |
C | Costs. |
D | Quality. |
Question 22 Explanation:
While re-estimating activities for the purpose of schedule compression you should focus on risks.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 23 |
What documents to be delivered by define activities process?
A | Activity list, activity attributes, and milestone list. |
B | Activity list, milestone list, and activity resource requirements. |
C | Activity list, milestone list, and project schedule. |
D | All choices are right. |
Question 23 Explanation:
Activity list, activity attributes, and milestone list are deliverables of define activities process.
[1 - 6 Project Time Management]
Question 24 |
What type of processes use schedule compression?
A | Executing and closing. |
B | Planning and integrated change control. |
C | Executing, and monitoring and controlling.. |
D | Planning and executing. |
Question 24 Explanation:
Schedule compression is used during planning and integrated change control (monitoring and controlling). During planning project manager optimizes the schedule to meet deadlines without changing scope, and in integrated change control, checks if there is any impact to scope, time, cost, risk, resources or customer satisfaction.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 25 |
A project manager has finalized scope baseline and started to define activities using company's templates and procedures. What is missing to complete the work?
A | Enterprise environmental factors. |
B | Requirements documentation. |
C | Organizational process assets. |
D | Activity list. |
Question 25 Explanation:
Scope Baseline, Organizational Process Assets, and Enterprise Environment Factors are the input to Define Activities process.
[1 - 6 Project Time Management]
Question 26 |
What tools and techniques project manager should use to develop schedule effectively?
A | Schedule compression and scheduling tool. |
B | All choices are right. |
C | Schedule network analysis, critical path method, critical chain method. |
D | Resource leveling, what-if scenario analysis, applying leads and lags. |
Question 26 Explanation:
All choices are right, as all the listed tools and techniques are needed to develop schedule effectively.
Question 27 |
How does the Start-to-Finish (SF) relations work?
A | The start of successor depends on start of predecessor. |
B | The completion of predecessor depends on completion of successor. |
C | The start of successor depends on start of predecessor. |
D | The finish of successor depends on start of predecessor. |
Question 27 Explanation:
The finish of successor depends on start of predecessor. In other words, the start of activity will allow to finish the next related activity.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 28 |
What type of dependency called hard logic?
A | Preferred dependency. |
B | External dependency. |
C | Mandatory dependency. |
D | Discretionary dependency. |
Question 28 Explanation:
Mandatory dependency in other words called hard logic and represent the unavoidable dependency from the elated activity. For example, an activity that must be done as per law requirement or corporate SDLC standard.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 29 |
What process is planning the scheduling methodology applied to the project?
A | Develop procurement plan. |
B | Develop time constrains and assumptions. |
C | Develop project management plan. |
D | Develop project charter. |
Question 29 Explanation:
Develop project management plan that produces a schedule management plan is the process that defines project scheduling methodology to be used during the course of the project.
[1 - 6 Project Time Management]
Question 30 |
Which graphical form of schedule preferably use during presentation to senior management?
A | Milestone chart. |
B | Project schedule network diagram. |
C | Affinity diagram. |
D | Bar chart. |
Question 30 Explanation:
Milestone chart graphically presents only major start and end dates, which usually used for reporting to senior management.
Bar chart is handful for graphically presenting progress of the project activities while discussing with the team.
Project schedule network diagram shows time-scaled logical relations between activities.
[1 - 6.5.3 Develop Schedule: Outputs]
Question 31 |
A new project manager just joint a company and wonders what scheduling tool to be used. What is the best place to find this information?
A | PMO. |
B | Ask other project managers. |
C | Technical department. |
D | Enterprise environment factors. |
Question 31 Explanation:
Scheduling tool that used in the company is usually listed in the enterprise environment factors that need to be obtained in the project initiation.
[1 - 6 Project Time Management]
Question 32 |
What negative float indicates?
A | Project has been compressed. |
B | Project is on schedule. |
C | Project is ahead of plan. |
D | Project behinds. |
Question 32 Explanation:
Negative float indicates that project is behind of schedule.
Question 33 |
Project manager should periodically _____ to make sure that adequate time and funds available to complete the project.
A | Review plans. |
B | Discuss the possible risks. |
C | Run team performance report. |
D | Recalculate estimate to complete. |
Question 33 Explanation:
Project manager should periodically recalculate estimate to complete (ETC) to make sure that adequate time and funds available to complete the project.
Question 34 |
What information the network diagram adds for develop schedule process?
A | Duration of each activity. |
B | The sequence of work will be processed. |
C | Detailed description of work to be done. |
D | Description of work packages to be done. |
Question 34 Explanation:
Network diagram provides the sequence of work will be processed for the develop schedule process.
[1 - 6.5 Develop Schedule]
Question 35 |
How many critical paths a project may have?
A | Maximum one. |
B | Maximum three. |
C | Many. |
D | Maximum two. |
Question 35 Explanation:
A project may have many critical paths.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 36 |
How often time management processes can be used during the course of the project?
A | Time management processes to be used during project initiation and its planning phase. |
B | Only selected time management processes to be selected depending on project needs. |
C | All time management processes to be used through the course of the project. |
D | At least ones on the project and project phase, if the project is divided to phases. |
Question 36 Explanation:
Actually, the question is how often a project manager and project team are concern about project schedule - ideally, at least ones on the project and project phase. In reality, time management processes are used quite often in combination with other processes. For example, a number of processes, including time, will be used in managing change requests and controlling schedule during the course of the project.
[PMBOK. Project Time Management]
Question 37 |
What information to be updated at the end of estimate activity resources?
A | Activity resources requirements, resource breakdown structure, and project schedule. |
B | Activity resources requirements and work breakdown structure. |
C | Activity resources requirements and resource breakdown structure. |
D | All choices are right. |
Question 37 Explanation:
Activity resources requirements, resource breakdown structure, and update project document are results of Estimate Activity Resources.
[1 - 6 Project Time Management]
Question 38 |
What information to be updated at the end of estimate activity resources?
A | All choices are right. |
B | Activity resources requirements and work breakdown structure. |
C | Activity resources requirements, resource breakdown structure, and project schedule. |
D | Activity resources requirements and resource breakdown structure. |
Question 38 Explanation:
Activity resources requirements, resource breakdown structure, and update project document are results of Estimate Activity Resources.
[1 - 6 Project Time Management]
Question 39 |
What a project manager should check regarding schedule when analyses change request?
A | If the change impacts critical path. |
B | How many activities requires impacted the change. |
C | How the change in schedule impacts costs. |
D | If the requested change impacts scope. |
Question 39 Explanation:
While analyzing change request project manager needs to check if the change impacts critical path.
Question 40 |
What needs to be done first to justify project time estimate?
A | Collect and combine time estimated for major tasks. |
B | Determine critical path. |
C | Build a network diagram. |
D | Confirm with a team. |
Question 40 Explanation:
Build a network diagram and then determine critical path.
[1 - 6.2 Sequence Activities]
Question 41 |
A project manager performs control schedule referring to project management plan, project schedule, work performance data, and _____?
A | Enterprise environmental factors, organizational process assets and requirements documentation. |
B | Project calendars, schedule data and organizational process assets. |
C | Enterprise environmental factors and list of activities. |
D | Enterprise environmental factors and organizational process assets. |
Question 41 Explanation:
Project management plan, project schedule, work performance data, project calendars, schedule data, and organizational process assets are inputs to Control Schedule process.
[PMBOK. Project Time Management, Control Schedule]
Question 42 |
What you should concern about when an earlier planned activity has been discarded for the purpose of schedule compression?
A | Cost. |
B | Time. |
C | Resource availability. |
D | Scope. |
Question 42 Explanation:
You should concern about Scope, when an earlier planned activity has been cancelled for the purpose of schedule compression. In addition, while this may save time and cost, it possible impacts customer satisfaction.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 43 |
A project team supports project manager with information to sequence activities. What information is needed to complete the work?
A | Organizational process assets. |
B | All choices are right. |
C | Milestones. |
D | List of activities and their attributes. |
Question 43 Explanation:
to complete sequence activities process project manager needs List of Activities, Activities Attributes, Milestones, and Organizational Process Assets.
[1 - 6 Project Time Management]
Question 44 |
What information is needed to perform control schedule process?
A | Project schedule that requested by stakeholders. |
B | Finalized and approved schedule, which is used as a baseline. |
C | Project scope time constrains. |
D | Milestone that approved by project sponsor. |
Question 44 Explanation:
Finalized and approved schedule, which is used as a baseline, is needed to perform control schedule process.
[1 - 6 Project Time Management]
Question 45 |
What part of organizational process assets can help in improving estimates?
A | Processes. |
B | Industry standards. |
C | Historical information. |
D | Templates. |
Question 45 Explanation:
Historical information is a valuable resource of organizational process assets for estimating, based on experiences on previous projects.
Question 46 |
How near-critical path effect the project?
A | Near-critical path does not have effect to risk? |
B | As near-critical path closer to critical path, the project has less risk. |
C | As near-critical path closer to critical path, the project has more risk. |
D | As near-critical path comes closer to critical path, the project reduces its risk. |
Question 46 Explanation:
As near-critical path closer to critical path, the project has more risk; as identified, both paths needs to be monitored and managed.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 47 |
A project manager performs define activity process. What information this process delivers?
A | Identified specific actions and their details to produce a realistic project schedule. |
B | A list of specified activities for implementing change using integrated change control system. |
C | Description of project activities listed in ascending order. |
D | Identified specific actions and their details to produce project deliverables. |
Question 47 Explanation:
Define activities identifies specific actions and their details to produce project deliverables.
[PMBOK. Project Time Management: Define Activities]
Question 48 |
What you should concern about when applying fast track to selected project activity for the purpose of schedule compression?
A | Risks and availability of resources for performing activities concurrently. |
B | The selected activity is in preferred logic. |
C | The selected activity has discretionary dependency. |
D | All choices are right. |
Question 48 Explanation:
Discretionary dependency, preferred or soft logic all refer to an activity that has options to be performed in different sequences. Also, while the work will be done in parallel with other activity, availability of resources is critical. Accordingly, Fast Track may also add risks and more management efforts to manage parallel tasks.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 49 |
What information needs to be updated that resulted by control schedule process?
A | Project management plan and change requests. |
B | Work performance measurements. |
C | All choices are right. |
D | Organizational process assets. |
Question 49 Explanation:
All choices are right. All listed here information needs to be updated when Control Schedule is completed.
[1 - 6 Project Time Management]
Question 50 |
What is the primary task of a project manager before project execution?
A | Ensure all efforts will be paid. |
B | Create project charter. |
C | Receive budget to cover project's expenses. |
D | Create a realistic project plan. |
Question 50 Explanation:
All choices are right in general, but the PRIMARY role of a project manager is create a REALISTIC project management plan PRIOR to project execution.
[PMBOK. Project Time Management.]
Question 51 |
What of the following should be used as a base for accurate estimation?
A | Project charter. |
B | Requirements documentation. |
C | Work breakdown structure. |
D | Project scope. |
Question 51 Explanation:
Work breakdown structure should be used as a base for effective and accurate estimation.
Question 52 |
A project team agreed with project schedule network diagram after _____?
A | Project document was updated. |
B | Received sponsor's approval. |
C | Estimating activity resources was completed. |
D | Stakeholders determined project constrains. |
Question 52 Explanation:
Project schedule network diagram and updated project document are results of sequence activities process.
[PMBOK. Project Time Management.]
Question 53 |
What type of dependency called external dependency?
A | Dependency outside of the project organization. |
B | Dependency outside of the project. |
C | Dependency outside of the project team. |
D | Dependency outside of the country. |
Question 53 Explanation:
As long as the dependency is outside of the project it called External", regardless of its location or nature.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 54 |
How time management processes interact with other project processes?
A | Cannot overlap each other, but used one after another with planning processes only. |
B | Can be used with different processes and overlap each other. |
C | Can be used in different sequence without overlap of each other. |
D | Can be used only with planning process group during process initiation. |
Question 54 Explanation:
Time management processes can be used with different processes and overlap each other during the course of the project.
[PMBOK. Project Time Management.]
Question 55 |
What needs to be done after a schedule baseline of the project is developed?
A | Approved by a project management team. |
B | Develop network diagram. |
C | Approved by customer. |
D | Develop schedule. |
Question 55 Explanation:
Schedule baseline needs to be accepted and approved by a project management team including both baselines for start and finish dates. The schedule baseline is a part of project management plan.
[1 - 6.5.3 Develop Schedule: Outputs]
Question 56 |
Baselines for scope, cost, and time should not be changed unless _____?
A | Approved change. |
B | Functional manager's request. |
C | Stakeholders request. |
D | Sponsors request. |
Question 56 Explanation:
Baselines for scope, cost, and time should not be changed unless the change is approved?
Question 57 |
What tree-point estimate analyzes and produces?
A | Analyzes requirements and produces optimistic, most likely and pessimistic estimates. |
B | Analyzes constrains and produces optimistic, most likely and pessimistic estimates. |
C | Analyzes baselines and produces optimistic, most likely and pessimistic estimates. |
D | Analyzes risks and produces optimistic, most likely and pessimistic estimates. |
Question 57 Explanation:
Tree-point estimate analyzes risks and produces optimistic, most likely and pessimistic estimates.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 58 |
What is the most common method of network diagramming used these days?
A | Dependency determination. |
B | Precedence diagramming method (PDM) or Activity-on-Node (AON). |
C | Arrow diagramming method (ADM). |
D | Graphic evaluation and review technique (GERT). |
Question 58 Explanation:
Precedence diagramming method (PDM) or Activity-on-Node (AON) is the right answer.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 59 |
What tools and techniques to be used by project manager while estimating activity resources?
A | Published estimation data and bottom-up estimation. |
B | Project management software. |
C | All choices are right. |
D | Expert judgement and alternative analysis. |
Question 59 Explanation:
All choices are right. Expert judgement and alternative analysis, published estimation data, bottom-up estimation, and project management software are tolls and techniques used in estimate activity resources.
[1 - 6 Project Time Management]
Question 60 |
How does the Finish-to-Finish (FF) relations work?
A | The activity cannot start before the next activity can finish. |
B | The completion of successor depends on completion of predecessor. |
C | The activity must finish before the next predecessor can start. |
D | The activity must finish before the next activity can start. |
Question 60 Explanation:
The completion of successor depends on completion of predecessor. In other words, the activity must finish before the related activity finished.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 61 |
What criteria need to be met for successful crashing selected activities of a project for the purpose of schedule compression?
A | Risks and budget. |
B | Resources and budget. |
C | Quality and resources. |
D | Risks and resources. |
Question 61 Explanation:
Resources and budget are two major concerns when crashing activities of the project for schedule compressing. Crashing always increases costs, whether by adding more resources, more experienced (means more expensive) resources, or purchasing more advanced tools. In addition, more management time may require to manage Crashing.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 62 |
How many types of logical relations the precedence diagramming method has?
A | Four. |
B | Six. |
C | Two. |
D | Eight. |
Question 62 Explanation:
Precedence diagramming method has four logical types of relations between nodes: finish-to-start, finish-to-finish, start-to-start, start-to-finish.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 63 |
What tools and techniques to be used by project manager while defining sequence activities?
A | Dependency determination. |
B | Precedence diagramming method. |
C | All choices are right. |
D | Applying leads and lags, and schedule network templates. |
Question 63 Explanation:
Precedence diagramming method, Precedence diagramming method, applying leads and lags, and schedule network templates are tools and techniques to be used while defining sequence activities.
[1 - 6 Project Time Management]
Question 64 |
What can be used to show the interdependency between activities through the whole project?
A | Project scope statement. |
B | Network diagram. |
C | List of activities. |
D | Work breakdown structure. |
Question 64 Explanation:
Network diagram shows interdependency of the activities through the whole project.
[1 - 6.2 Sequence Activities]
Question 65 |
How much float critical paths usually has?
A | Maximum two. |
B | Zero. |
C | Maximum one. |
D | One. |
Question 65 Explanation:
Usually critical paths does not have floats (slacks).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 66 |
Baselines for scope, cost, and time should not be changed unless _____?
A | Approved change. |
B | Stakeholders request. |
C | Sponsors request. |
D | Functional manager's request. |
Question 66 Explanation:
Baselines for scope, cost, and time should not be changed unless the change is approved?
Question 67 |
From which process output the define activities process receives scope baseline?
A | Develop scope management plan. |
B | Develop activity list. |
C | Project scope statement. |
D | Work breakdown structure. |
Question 67 Explanation:
Scope baseline is one of the results of create work breakdown structure process.
[1 - 6.1.1 Define Activities: Input]
Question 68 |
Who should participate in estimating process to assure accuracy?
A | Functional manager. |
B | Sponsor. |
C | Stakeholder. |
D | The person who will be executing the work. |
Question 68 Explanation:
The person who will be executing the work can provide more accurate information for estimating the required work efforts and duration.
Question 69 |
Activity-on-the-node is the method of _____.
A | Constructing a visual diagram that uses nodes to indicate logically related requirements. In other words, this called relational arrowing method. |
B | Constructing a visual diagram that uses nodes to indicate logically related communications between project members and stakeholders. In other words, this called rolling wave planning. |
C | Constructing a visual diagram that uses nodes to indicate logically related requirements and risks on the project. In other words, this called bottom-up estimation. |
D | Constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. In other words, this called precedence diagramming method. |
Question 69 Explanation:
Activity-on-the-node is the method of constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. In other words, this called precedence diagramming method.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 70 |
What effect you need to expect when selected method of schedule compression is cut time?
A | Increased costs. |
B | Reduced quality. |
C | Increased risks. |
D | Reduced scope. |
Question 70 Explanation:
Cut time as a choice of schedule compression usually leads to reduced quality standards.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 71 |
What tools and techniques project manager uses to define activities?
A | Rolling wave planning. |
B | All choices are right. |
C | Decomposition. |
D | Templates and expert judgement. |
Question 71 Explanation:
All choices are right. Project manager uses Decomposition, Rolling Wave Planning, Templates and Expert Judgement while Defining Activities.
[1 - 6 Project Time Management]
Question 72 |
What needs to be done if the project has negative slack?
A | Re-estimate resource requirements. |
B | Compress schedule. |
C | Ask for additional time. |
D | Re-estimate activity duration. |
Question 72 Explanation:
If the project has negative slack (float) it means the project is behind the schedule; compress schedule is the recommended action (fast track, crash, reduction of scope or quality).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 73 |
What can be used to show the interdependency between activities through the whole project?
A | Network diagram. |
B | List of activities. |
C | Work breakdown structure. |
D | Project scope statement. |
Question 73 Explanation:
Network diagram shows interdependency of the activities through the whole project.
[1 - 6.2 Sequence Activities]
Question 74 |
What rules are used in heuristic technique?
A | Law Murphy. |
B | God's wish. |
C | Rule of thumb. |
D | General of luck. |
Question 74 Explanation:
Rule of thumb is a heuristic technique. An example is rule 80/20, which states that 80% of problems come from 20% of sources. Another example... 10 per cent of project time should be allocated to project closing. Such parametric estimation may become heuristic.
Question 75 |
What information is required to develop project schedule?
A | Outputs from processes to define and sequence activities, estimate activity resources, and estimate activity duration. |
B | Project scope, finalized requirements, sequence activities, estimate activity resources, and estimate activity duration. |
C | Project charter, List of requirements, work breakdown structure, estimate activity resources, and estimate activity duration. |
D | List of requirements, work breakdown structure, and estimate activity resources. |
Question 75 Explanation:
Outputs from processes to define and sequence activities, estimate activity resources, and estimate activity duration are needed to develop project schedule.
[1 - 6 Project Time Management]
Question 76 |
What information from similar previous projects usually used with analogous estimating method?
A | Duration, budget, size, weight, and complexity. |
B | Costs, budget, time, resource requirements, and organizational assets. |
C | Duration, quality, risks, efforts, and complexity. |
D | Efforts, costs, location, and customer satisfaction. |
Question 76 Explanation:
Duration, quality, risks, efforts, and complexity - these parameters usually used for analogous estimation (top-down).
[1 - 6.4.2. Estimate Activity Duration: Tools and Techniques]
Question 77 |
Precedence diagramming method is used for _____.
A | Constructing a visual project schedule network diagram that uses nodes to indicate logically related activities. |
B | Constructing a visual diagram that uses nodes to indicate logically related requirements and risks on the project. |
C | Constructing a visual diagram that uses nodes to indicate logically related requirements. |
D | Constructing a visual diagram that uses nodes to indicate logically related communications between project members and stakeholders. |
Question 77 Explanation:
Precedence diagramming method is used for constructing a visual project schedule network diagram that uses nodes to indicate logically related activities.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 78 |
What range of the estimate for an activity with expected duration at least 10 days, the worse 18 days, but more likely 15 days to complete?
A | 15.97
+/- 1.78 |
B | 14,0
+/- 1.33 |
C | 5.97
+/- 1.23 |
D | 14.67
+/- 1.33 |
Question 78 Explanation:
PERT uses the following formulas and calculations...
Expected Activity Duration
(P+4M+O) / 6 = (18+4*15+10) / 6 = 14.666;
Activity Standard Deviation
P-O / 6 = 18-10 / 6 = 1.333;
Activity Variance
(P-O)**2 / 6 = 1.777 (wasn't asked in this question)
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 79 |
What sequence activities is?
A | Process of identifying and documenting the interface properties between the project activities. |
B | Process of identifying and documenting physical relationship between the project activities. |
C | Process of identifying and documenting the thresholds the project activities. |
D | Process of identifying and documenting logical relationship between the project activities. |
Question 79 Explanation:
Process of identifying and documenting relationship between the project activities.
[1 - 6.2 Sequence Activities]
Question 80 |
What technique applies with three-point estimation?
A | Moving average estimate. |
B | Program evaluation and review technique. |
C | Exponential smoothing technique. |
D | Wave based estimation technique. |
Question 80 Explanation:
Program Evaluation and Review Technique (PERT) is applied with Three_Point Estimate technique.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques - .4 Three Point Estimates]
Question 81 |
What processes include time management project knowledge area?
A | Define and sequence activities. |
B | Estimate activity resources and activity durations. |
C | All choices are right. |
D | Develop and control schedule. |
Question 81 Explanation:
All the listed processes are the part of the Time Management: define activities, sequence activities, estimate activity resources, estimate activity duration, develop schedule, and control schedule.
[PMBOK. Project Time Management]
Question 82 |
What tools and techniques project manager uses to control schedule?
A | All choices are right. |
B | Resource leveling, what-if scenario analysis. |
C | Performance reviews, variance analysis, project management software. |
D | Adjusting leads and lags, schedule compression, scheduling tool. |
Question 82 Explanation:
All choices are right; all listed tools and techniques are used to Control Schedule.
[1 - 6 Project Time Management]
Question 83 |
What criteria to be used in the decision of which activity or activities to crash for the purpose of schedule compression?
A | Longest time. |
B | Higher cost. |
C | Shortest time. |
D | Lowest cost. |
Question 83 Explanation:
The crash the activity or activities with lowest cost to be selected for the purpose of schedule compression.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 84 |
How graphical evaluation and review techniques (GERT) is different from other diagramming methods?
A | Indicates only mandatory dependencies. |
B | Connects nodes with arrows that represent activities. |
C | Allows using loops between nodes. |
D | Allows conditional nodes. |
Question 84 Explanation:
Graphical Evaluation and Review Techniques (GERT) allows using between project activities.
[1 - 6.2.2 Sequence Activities: Tools and Techniques]
Question 85 |
What project scheduling methodology defines?
A | Thresholds that project schedule can reach at the end of the project. |
B | Defines the beginning and end dates of the project. |
C | Defines the beginning end, and milestone dates of the project. |
D | Rules and approaches for scheduling process. |
Question 85 Explanation:
Scheduling methodology defines rules and approaches for scheduling process.
[1 - 6 Project Time Management]
Question 86 |
What method is used to avoid not linear (up-and-down) use of resources?
A | Calendar stabilizing. |
B | Activity crashing. |
C | Economic model. |
D | Resource leveling. |
Question 86 Explanation:
Resource leveling technique is used to stabilize use of resources. The longer project duration is an option to stabilize usage of resources on the project, instead hiring resources for shorter periods, releasing them and hiring back, when needed. This also may save cost of procurement and reduce risk for spending extra effort for training and/or knowledge transfer.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 87 |
Which of the methods refers to progressive elaboration planning?
A | Rolling wave. |
B | Waterfall. |
C | Bottom-up estimation. |
D | Precedence diagramming. |
Question 87 Explanation:
Rolling wave is the method of progressing elaboration planning.
[1 - 6.1.1 Define Activities: Input]
Question 88 |
What method is used to avoid not linear (up-and-down) use of resources?
A | Resource leveling. |
B | Activity crashing. |
C | Calendar stabilizing. |
D | Economic model. |
Question 88 Explanation:
Resource leveling technique is used to stabilize use of resources. The longer project duration is an option to stabilize usage of resources on the project, instead hiring resources for shorter periods, releasing them and hiring back, when needed. This also may save cost of procurement and reduce risk for spending extra effort for training and/or knowledge transfer.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 89 |
How to calculate float?
A | Late Start - Earlier Start or Late Finish - Early Finish. |
B | Late Start - Earlier Finish or Late Start - Early Finish. |
C | Late Finish - Earlier Start or Late Finish - Early Finish. |
D | Late Finish - Earlier Start or Late Start - Early Finish. |
Question 89 Explanation:
Late Start - Earlier Start or Late Finish - Early Finish are the equations to calculate Float (Slack).
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 90 |
What information is missing while activity list, activity attribute, and resource calendar is provided for estimating activity resources process?
A | Enterprise environmental factors and organizational process assets. |
B | Enterprise environmental factors. |
C | Activity resource requirements. |
D | Organizational process assets. |
Question 90 Explanation:
Activity list, activity attribute, resource calendar, enterprise environmental factors and organizational process assets are inputs to estimate activity resources. Other choices whether incomplete while, activity resource requirements is the output of this process.
[1 - 6 Project Time Management]
Question 91 |
A project manager estimates activity duration. What information is needed to make this process effectively?
A | Activity list, activity attributes, and activity resource requirements. |
B | Resource calendars, project scope statements. |
C | All choices are right. |
D | Enterprise environmental factors and organizational process assets. |
Question 91 Explanation:
All choices are right. All these documents are input to the estimate activity duration process.
[1 - 6 Project Time Management]
Question 92 |
What results of the develop schedule should be updated when the process is complete?
A | All choices are right. |
B | Project schedule, schedule baseline, work breakdown structure. |
C | Project schedule, schedule baseline, schedule data |
D | Project schedule, schedule baseline, activity list. |
Question 92 Explanation:
Project schedule, schedule baseline, schedule data and project document update are deliverables of the develop schedule.
[1 - 6 Project Time Management]
Question 93 |
How the output of estimate activity duration forms?
A | Activity duration can be identified as a firm quantitative period. |
B | All activities on the project can be assign with the same period of time as long as the activity takes less than one week. |
C | Activity duration can be identified as a firm quantitative period, as well as a period with added probability. |
D | Activity duration can be identified buy taking a guess and double it to ensure the activity will be completed. |
Question 93 Explanation:
Activity duration can be identified as a firm quantitative period, as well as a period with added probability.
[1 - 6.4.3 Estimate Activity Duration: Outputs]
Question 94 |
How does the Start-to-Start (SS) relations work?
A | The start of successor depends on finish of predecessor. |
B | The finish of successor depends on start of predecessor. |
C | The completion of successor depends on completion of predecessor. |
D | The start of successor depends on start of predecessor. |
Question 94 Explanation:
The start of successor depends on start of predecessor.
[1 - 6.2.2. Sequence Activities: Tools and Techniques]
Question 95 |
What relation between create work breakdown structure and define activities processes?
A | Work breakdown structure identifies the deliverables at their lowest level, which called packages, while define activities process decomposes work packages into smaller components identified as activities to deliver those packages. |
B | Work breakdown structure describes the way how to deliver the project results, while define activities process identifies the activities to deliver those packages. |
C | Work breakdown structure identifies the methods how the to be executed, while define activities process identifies the activities to deliver those packages. |
D | Work breakdown structure proved a sequence of activities, while define activities process identifies the activities to deliver those packages. |
Question 95 Explanation:
Work breakdown structure identifies the deliverables at their lowest level, which called packages, while define activities process decomposes work packages into smaller components identified as activities to deliver those packages. Other choices are made up.
[1 - 6.1 Project Time Management: Define Activities]
Question 96 |
What does critical path determine?
A | The shortest path in the network diagram, as well as the latest start and finish dates for project activities. |
B | The longest path in the network diagram, as well as the earliest start and earliest finish dates for project activities. |
C | The longest path in the network diagram, as well as the earliest and latest start and finish dates for project activities. |
D | The shortest path in the network diagram, as well as the earliest and latest start and finish dates for project activities. |
Question 96 Explanation:
The longest path in the network diagram, as well as the earliest and latest start and finish dates for project activities.
[1 - 6.5.2 Develop Schedule: Tools and Techniques]
Question 97 |
What type of diagram is created as the result of regression analysis in parametric estimation?
A | Affinity diagram. |
B | Learning curve. |
C | Network diagram. |
D | Scatter diagram. |
Question 97 Explanation:
Scatter diagram is created in parametric estimation where the time measures per action component like per line of code, per meter, or per setup, etc. Learning Curve is another parametric method that states the following similar activity should take less time than previous because of obtained more experience, improved skills and techniques.
[1 - 6.4.2 Estimate Activity Duration: Tools and Techniques]
Question 98 |
How does the Finish-to-Start (FS) relations work?
A | The activity cannot finish before the next activity start. |
B | The activity cannot start before the next activity can finish. |
C | The activity must finish before the next activity can start. |
D | The activity must finish before the next predecessor can start. |
Question 98 Explanation:
Finish-to-star relations prescribes that the activity must finish before the next activity can start.
Question 99 |
What tools and techniques to be used for effective estimate activity duration?
A | Decomposition, rolling wave planning, analogous, parametric, three point estimates, and reserve analysis. |
B | Expert judgement, analogous, parametric, three point estimates, and reserve analysis. |
C | Expert judgement, peer review, Delphi method, five point estimates, and reverse analysis. |
D | All choices are right. |
Question 99 Explanation:
Expert judgement, analogous, parametric, three point estimates, and reserve analysis are tools and techniques that used for Estimate Activity Duration.
Question 100 |
Sequencing of the activities can be performed using _____.
A | Manual optimization method. |
B | Project management hardware. |
C | Project management software. |
D | Only project management software. |
Question 100 Explanation:
Sequencing of the activities can be performed using project management software.
[1 - 6.2 Sequence Activities]
Question 101 |
How detailed the project schedule should be?
A | Highly detailed to ensure that all dates for activities and milestones are determined. |
B | Whether highly detailed or broadly framed, depending on needs of the project. |
C | All activities need to be scheduled and provide high level of details to ensure that project is tractable. |
D | Only major activities need to be scheduled and provide high level of details. |
Question 101 Explanation:
Project schedule can be documented with using very detailed information about time or include only mile stones; the level of required details is depending on needs of the project and include appropriate realistic thresholds.
[1 - 6 Project Time Management]
Question 102 |
What process approves or rejects changes?
A | Integrated change control. |
B | Integrated change management system. |
C | Change management plan. |
D | Configuration management process. |
Question 102 Explanation:
Integrated change control process approvals or rejects for changes.
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 102 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
1 | 2 | 3 | 4 | 5 |
6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 |
26 | 27 | 28 | 29 | 30 |
31 | 32 | 33 | 34 | 35 |
36 | 37 | 38 | 39 | 40 |
41 | 42 | 43 | 44 | 45 |
46 | 47 | 48 | 49 | 50 |
51 | 52 | 53 | 54 | 55 |
56 | 57 | 58 | 59 | 60 |
61 | 62 | 63 | 64 | 65 |
66 | 67 | 68 | 69 | 70 |
71 | 72 | 73 | 74 | 75 |
76 | 77 | 78 | 79 | 80 |
81 | 82 | 83 | 84 | 85 |
86 | 87 | 88 | 89 | 90 |
91 | 92 | 93 | 94 | 95 |
96 | 97 | 98 | 99 | 100 |
101 | 102 | End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!