PM - Integration Management
Start
Congratulations - you have completed PM - Integration Management.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
Which of the following refers to project integration management?
A | Execute project improvement plan. |
B | Approve or reject changes. |
C | Monitor and control project work |
D | Support conflict resolution. |
Question 1 Explanation:
Monitor and control project work is the part of the integration management.
[1 - Project Integration Management processes]
Question 2 |
What economic value added term means in term of project selection?
A | The value that adds costs of the projects. |
B | The cost reduction achieved by using integrated quality control. |
C | The value above costs of the project that adds benefits to the company's shareholders. |
D | The value produce by the project. |
Question 2 Explanation:
As higher economic value added the project is more preferable.
Question 3 |
It is a project manager's responsibility to appraise what type and quantities of materials, people, tools, or goods require to perform each project activity. What project manager needs to be done?
A | Estimate activity resources requirements. |
B | Create resource management plan. |
C | Select resource vendors. |
D | Acquire resources. |
Question 3 Explanation:
Estimate activity resources requirements should be performed.
[1 - 3.4.7 Estimate activity resources]
Question 4 |
Which document describes the processes selected by project management team?
A | Communication plan. |
B | Resource management plan. |
C | Project management plan. |
D | Process management plan. |
Question 4 Explanation:
Project management plan describes the processes selected by project management team.
[1 - Develop Project Management Plan: Outputs]
Question 5 |
What is input of the develop project management plan?
A | Enterprise environmental factors, organizational process assets, project charter, communication and procurement plans outputs from planning processes. |
B | Enterprise environmental factors, organizational process assets, project charter, outputs from planning processes. |
C | Business case, list of stakeholders, initial requirements, statement of work. |
D | Project scope, product scope, finalized requirements, communication and procurement plans. |
Question 5 Explanation:
Enterprise environmental factors, organizational process assets, project charter, outputs from planning processes used as input to develop project management plan.
[1 - 4.2 Develop Project Management Plan]
Question 6 |
What type of programming method is used in project selection?
A | Abacus linear programming. |
B | Any type of programming approach that may help in project selection can be used the constrain optimization or mathematical approach. |
C | Arbitrary integer programming method. |
D | Backwards dynamic programming. |
Question 6 Explanation:
Constrain optimization methods or mathematical approach use suitable programming methods in project selection methods.
Question 7 |
What is the project management plan?
A | A schedule of procurements on the project. |
B | A document that integrates all management plans and their baselines. |
C | A collection of management plans for executing a project. |
D | Time and costs schedules integrated to ensure that project needs are met. |
Question 7 Explanation:
A document that integrates all management plans and their baselines.
[1 - 4.2.3 Develop Project Management Plan: Outputs]
Question 8 |
In which process the following economic categories are used: present value, net present value, internal rate of return, payback period, benefit-cost ratio.
A | Project monitoring and controlling. |
B | Project planning. |
C | Project closing. |
D | Project selection. |
Question 8 Explanation:
Present value, net present value, internal rate of return, payback period, benefit-cost ratio are the economic models used in project selection.
Question 9 |
What parts of the project documents may be required update when defect repair is applied?
A | Business plan of the company. |
B | Corporate financial tax reporting. |
C | Project management plan and its subsidiary management plans, forecasts, issues log, reports of project performance. |
D | Corporate marketing strategies. |
Question 9 Explanation:
As a part of monitoring and controlling processes, defect repair may require update of project documentation including but not limited to project management plan, its subsidiary management plans, forecasts, issues log, reports of project performance and other documents.
[1 - 4.4 Monitor and Control Project]
Question 10 |
During executing processes an issue reflected the project scope has been identified. What needs to do next?
A | Generate a change request. |
B | Analysis what influence to the project the issue can make. |
C | Inform management. |
D | Inform stakeholder. |
Question 10 Explanation:
The first action is to identify the influence and risks to the project that identified issue and change can do, then inform management and stakeholder. After that, generate a change request, if a change will be needed. Use an integrated change control process.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 11 |
A part of which document the configuration management is?
A | PMLC implementation plan. |
B | Change management plan. |
C | Project scope management plan. |
D | Project management plan. |
Question 11 Explanation:
Configuration management plan is a part of part of the project management plan and describes how the configuration management on the project will be performed.
[1 - Develop Project Management Plan: Outputs]
Question 12 |
What of the following enterprise environment factors is used as an input to monitor and control work?
A | Work authorization system. |
B | Financial control system. |
C | Resource rating system. |
D | Procurement system. |
Question 12 Explanation:
Work authorization system is a part of enterprise environment factors that used as an input to monitor and control work.
[1 - 4.4.1 Monitoring and Control Project Work: Inputs]
Question 13 |
Which of the following activities include controlling process?
A | Tracking and regulating and reporting project performance activities. |
B | Determining whether corrective, preventive actions to be taken, or re-planning and follow up on action plans is required to determine if the applied actions resolved the issue related to performance. |
C | Determine the project performance trends through the constant measurements in all stages of work. |
D | Planning project changes through the project stages and applying trends. |
Question 13 Explanation:
Controlling activities include determining whether corrective, preventive actions to be taken, or re-planning and follow up on action plans is required to determine if the applied actions resolved the issue related to performance.
Monitoring and controlling Work includes tracking, reviewing, and regulating activities to meet project performance objectives described in project management plan. In other words, this is a process of collecting, measuring, and distributing information related to project performance, and identifying project performance trends.
[1 - 4.4 Monitoring and Control Project Work]
Question 14 |
Which of the following information is usually used during project initiation?
A | Project plan. |
B | WBS glossary. |
C | Lessons learned. |
D | Product scope statement. |
Question 14 Explanation:
Lessons learned is one of the sources of historical information that used during project initiation.
Question 15 |
What of the following activities belong to the direct and manage project execution process?
A | Planning and executing project activities. |
B | Gathering initial requirements and creating project scope statement. |
C | Corrective and preventive actions, and defect repair. |
D | All activities on the project. |
Question 15 Explanation:
Direct and manage project execution also requires implementation of changes that were approves, while addressing the corrective and preventive actions, and defect repair.
[1 - 4.3 Direct and Manage Project Execution]
Question 16 |
What project improvement plan is about?
A | Planning an implementing version control for project documentation. |
B | Setting up an automated document management system through as a part of enterprise environmental factors. |
C | Constantly identifying the exiting and implementing new project processes and organizational process assets. |
D | Plan for improvement of project deliverables. |
Question 16 Explanation:
Project improvement plan oversees the process of constantly identifying suitable processes and organizational assets to be used on the project and improving them in order to reach project objectives with lower costs, shorter time and better quality. For example such improvement can be done on repetitive type of activities.
Question 17 |
How much should you invest targeting $450,000 of return in five years, more or less of this amount?
A | Double. |
B | Equal |
C | More |
D | Less |
Question 17 Explanation:
The investment amount should be less than $450,000 because the investment money should generate the interest and reach at least the invested amount.
Question 18 |
Which process groups are integrated via human resources knowledge area?
A | Execution, monitoring and controlling. |
B | Initiating and closing. |
C | Planning, monitoring and controlling. |
D | Planning and execution. |
Question 18 Explanation:
Planning and execution project process groups are integrated via human resources knowledge area.
[1 - 3.1 Common Project Management Process Interactions]
Question 19 |
What is the role of integration management?
A | Integration management helps to understand the relations between time, cost and risk. |
B | Integration management oversees the relations between the project deliverables and customer's organization. |
C | Integration management links different knowledge areas of project management. |
D | Integration management helps supports the planning and executing processes. |
Question 19 Explanation:
Integration management linked individual processes from different process groups and knowledge areas. For example, the change a new risk may require to revise time, cost, procurement or other management plans and affect customer's expectations and company;s strategic opportunities.
[1 - Project Integration Management processes]
Question 20 |
What parts of the project documents may be updated in monitoring and controlling processes?
A | Business plan of the company. |
B | Project management plan and its subsidiary management plans, forecasts, issues log, reports of project performance. |
C | Corporate financial tax reporting. |
D | Corporate marketing strategies. |
Question 20 Explanation:
Monitoring and controlling processes usually require update of project documentation including but not limited to project management plan, its subsidiary management plans, forecasts, issues log, reports of project performance and other documents.
[1 - 4.4 Monitor and Control Project]
Question 21 |
What tools project manager uses while determines resources and skill level needed to perform project work and documenting it is project management plan?
A | Expert judgement. |
B | Resources costs analysis. |
C | Skills metrics. |
D | Human resources hiring schedule. |
Question 21 Explanation:
Project manager uses expert judgement determines resources and skill level needed to perform project work and documenting it is project management plan.
[1 - Develop Project Management Plan: Tools and Techniques]
Question 22 |
What parts of the project documents may be updated when a preventive action is applied?
A | Corporate financial tax reporting. |
B | Corporate marketing strategies. |
C | Business plan of the company. |
D | Project management plan and its subsidiary management plans and baselines, forecasts, issues log, reports of project performance. |
Question 22 Explanation:
As a part of monitoring and controlling processes, preventive action usually requires update of project documentation including but not limited to project management plan, its subsidiary management plans, forecasts, issues log, reports of project performance and other documents.
[1 - 4.4 Monitor and Control Project]
Question 23 |
When it comes to change what position should take a project manager?
A | Negotiate if change can be done during the next release. |
B | Refuse changes. |
C | Preventing unnecessary changes. |
D | Approve the change as requested. |
Question 23 Explanation:
Preventing unnecessary changes is the primary task of the project manager related to changes.
Question 24 |
What of the following activity better defines corrective action?
A | Addressing and fixing root cause of issues. |
B | Correcting cost and schedule to prevent discrepancy with project management baselines. |
C | Identifying when an issue can happen. |
D | Planning the changes that fixing problems on the project. |
Question 24 Explanation:
Objective of corrective action is to ensure that project issues are fixed in aspect to bring project inline with project management plan and management plan baselines.
[1 - 4.4.3 Monitoring and Control Project Work: Outputs]
Question 25 |
What of the following is the part of organizational process assets as an input to develop project management plan?
A | Integrated change management system. |
B | Infrastructure and existing information management system. |
C | Company's standards and guidelines, processes and procedures, various evaluation criteria and performance measurement approach. |
D | Configuration management and quality control systems. |
Question 25 Explanation:
The standards, procedures, policies, historical information and lessons learned from the past projects, templates and other documents are a part of an organizational processes assets.
[1 - 4.2.1 Develop Project Management Plan: Inputs]
Question 26 |
Who has primary responsibility for changes in project charter?
A | PMO. |
B | Stakeholder. |
C | Sponsor. |
D | Project manager. |
Question 26 Explanation:
Sponsor has primary reproducibility to create or change project charter.
Question 27 |
What needs to be done with the product delivered by a project?
A | It is project manager's responsibility to keep product or service as a prototype for further use as a part of enterprise environment factors. |
B | The complete product or service has to be handed off. |
C | Start using the product or service as it was functional and completed. |
D | The complete product delivered by the project has to be kept for further references. |
Question 27 Explanation:
The complete product or service has to be handed off as one of the final steps in the project closing.
[1 - 4.6 Close Project or Phase]
Question 28 |
What of the following is used as one of economic models for project selection?
A | Net equity value. |
B | Net future value. |
C | Net assets value. |
D | Net present value. |
Question 28 Explanation:
Net present value is one of the economic models for used project selection.
Question 29 |
Which of the following processes perform project integration management?
A | Develop schedule. |
B | Develop project charter. |
C | Identify stakeholders and develop stakeholder management plan. |
D | Manage project reserves. |
Question 29 Explanation:
Develop project charter is a part of project integration management.
Question 30 |
What tools and techniques use in the direct and manage project execution process?
A | Delphi method and qualitative risk analysis. |
B | Expert judgement and structured systems analysis. |
C | Peer review and Integrated change management control. |
D | Expert judgement and project management information system. |
Question 30 Explanation:
Direct and manage project execution process uses expert judgement and project management information system.
[1 - 4.3 Direct and Manage Project Execution]
Question 31 |
Which of the project selection approaches uses a peer review method?
A | Dynamic programming. |
B | Benefit measurement method. |
C | Constrain optimization method. |
D | Mathematical approach. |
Question 31 Explanation:
Peer review in one of the comparative or benefit measurement methods.
Question 32 |
What of the following are considered as organizational process assets?
A | Historical information and lessons learned knowledge base. |
B | Industry standards. |
C | Marketplace conditions. |
D | Contract. |
Question 32 Explanation:
Historical information and lessons learned knowledge database are organizational process assets.
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 33 |
Which of the following processes is a part of project integration management?
A | Execute closing of project or phase. |
B | Manage time and cost reserves. |
C | Understand business case and document initial requirements. |
D | Develop and execute procurement plan. |
Question 33 Explanation:
Closing of project or phase is a part of integration management.. This process finalizes all activities across all project management process groups and complete the project or phase formally.
Question 34 |
Which of the knowledge areas are used in project monitoring and controlling process group?
A | Scope, time, cost, risk, procurement. |
B | Scope, time, cost, communications, risk. |
C | Scope, time, cost, human resources, communications, risk, procurement. |
D | Scope, time, cost, communications, risk, procurement. |
Question 34 Explanation:
Monitoring and controlling process group uses the scope, time, cost, communications, risk, procurement. Understanding of relations between these knowledge areas leads to understanding of integration management.
Question 35 |
Which project to be selected?
A | Lower benefit cost ratio. |
B | Higher budget. |
C | Lower budget. |
D | Higher benefit cost ratio. |
Question 35 Explanation:
A project with higher benefit cost ratio to be selected.
Question 36 |
What is the current (short-term) value of assets minus liabilities?
A | Capital structure. |
B | Capital budgeting. |
C | Equity. |
D | Working capital. |
Question 36 Explanation:
Working capital is the amount of money that available for investment, including the projects.
Question 37 |
Which knowledge areas are used during project closing?
A | Scope, communications, procurement. |
B | Procurement. |
C | Scope, human resources, communications, procurement. |
D | Scope, time, cost, quality, human resources, communications, risk, procurement. |
Question 37 Explanation:
Procurement is the project management knowledge area used in project closing.
Question 38 |
What is accelerated depreciation?
A | Complete reduction of the assets' at the time or purchase. |
B | Progressive reduction of the assets' value. |
C | Complete reduction of the assets' value during reporting period. |
D | Reduction of the assets' value with equal amounts. |
Question 38 Explanation:
Progressive reduction of the assets' value is the accelerated depreciation. This means that booked value of the asset depreciates with different but progressing numbers on yearly basis. This category is also used in project selection.
Question 39 |
What details project management plan should provide?
A | The level of details is determined by PMO. |
B | All subsidiary plans have to be detailed same as project management plan. |
C | All subsidiary plans should be used. |
D | One or more subsidiary plans to be used on summary or detailed level. |
Question 39 Explanation:
Either one or more subsidiary plans to be used on summary or detailed level.
[1 - Develop Project Management Plan: Outputs]
Question 40 |
_____ is one of the most important factors in change management.
A | Dividing a project to smaller phases. |
B | Project definition. |
C | Integration. |
D | WBS and WBS dictionary. |
Question 40 Explanation:
Integration between all project management areas in one of the most important factors in effective change management.
Question 41 |
What process is documenting the necessary project activities that explain, formulate, incorporate, and organize all sub-ordinary plans?
A | Complete articles of incorporation. |
B | Create marketing plan. |
C | Design financial plan. |
D | Develop project plan. |
Question 41 Explanation:
Develop project plan is the process of documenting the necessary project activities that explain, formulate, incorporate, and organize all sub-ordinary plans?
[1 - 4.2 Develop Project Management Plan]
Question 42 |
When the baselines are created?
A | During project executing. |
B | During project closing. |
C | During project planning. |
D | Throughout the whole project. |
Question 42 Explanation:
Baselines are created during project planning.
Question 43 |
All of the following will occur during project closing except _____.
A | Update lessons learned. |
B | Confirm the project work is completed to requirements. |
C | Archive documents and records. |
D | Reward the project team. |
Question 43 Explanation:
Rewarding the project team increases productivity and provided during project execution; although it can be done by the management outside of the project, when it is completed.
Question 44 |
What of the following information project charter contains?
A | Communication plan. |
B | Purpose and justification of the project. |
C | Project cost. |
D | Project schedule. |
Question 44 Explanation:
Project charter contains the purpose and justification of the project, measurable objectives and success criteria, high level descriptions of the project, requirements and risks, summaries of the milestone schedule and budget, project approval requirements, name/role and authority and responsibilities of project manager, name and authority of the authorizing person.
[1 - 4.1.3 Develop Project Charter: Outputs]
Question 45 |
How the internal rate of return influence the project selection decision?
A | A project with lower internal rate of return (IRR) to be selected. |
B | A project with higher internal rate of return (IRR) to be selected. |
C | A project with higher internal rate of return (IRR) and higher duration to be selected. |
D | A project with shorter duration and lower internal rate of return (IRR) to be selected. |
Question 45 Explanation:
A project with higher IRR to be selected.
Question 46 |
What does the work performance information contain?
A | Deviation between planned and actual schedule. |
B | Deviation between planned and actual costs. |
C | Deliverable status, schedule progress, and involved costs. |
D | Deviation between planned and actual costs, schedule and quality. |
Question 46 Explanation:
Work performance information contains, but not limited to the deliverable status, schedule progress, and involved costs.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 47 |
Software developer and quality analyst are assigned to fix a glitch in the product. The company's software development life cycle procedures support the work from collecting requirements to product deployment. To what type of activities the team is assigned?
A | Product development. |
B | Product maintenance. |
C | Project. |
D | SDLC program. |
Question 47 Explanation:
This is a product maintenance work, not a project. It does not require executing the most of project management processes.
Question 48 |
What tools project manager uses while defines the level of configuration management and documents it in project management plan?
A | Pareto diagram. |
B | Expert judgement. |
C | Peer review. |
D | Resource requirements. |
Question 48 Explanation:
Project manager uses expert judgement while defines the level of configuration management and documents it in project management plan.
[1 - Develop Project Management Plan: Tools and Techniques]
Question 49 |
What is a work authorization system?
A | An automated software that allows to start performing a work outside of the company. |
B | A set of signatures that allows to start a project work. |
C | A collection of formal documents, procedures and processes to define how the project work to be authorized. |
D | An automated system that notifies stakeholders about start and end of work packages. |
Question 49 Explanation:
Work authorization system is a project management sub-system that provides a collection of formal documents, procedures and processes to define when, how, and who authorize the project work.
[1 - 4.4.1 Monitoring and Control Project Work: Inputs]
Question 50 |
Who makes a decision whether approve or reject a change?
A | Resource manager. |
B | PMO. |
C | Change control board. |
D | Project manager. |
Question 50 Explanation:
Change control board is responsible for reviewing, analyzing, and them whether approving or rejecting a change.
[1 - 4.5 Perform Integrated Change Control]
Question 51 |
Which document describes how the content of reviews, pending decisions and open issues will be managed?
A | Project management plan. |
B | Stakeholder management plan. |
C | Issue management plan. |
D | Lessons learned. |
Question 51 Explanation:
Project management plan describes how the content of reviews, pending decisions and open issues will be managed.
[1 - 4.2.3 Develop Project Management Plan: Outputs]
Question 52 |
A project manager has completed estimating activity resources and updated project documents with _____.
A | Resources calendar. |
B | Procurement schedule. |
C | Activity resource requirements and resources breakdown structure. |
D | Project schedule network diagram. |
Question 52 Explanation:
Activity resource requirements and resources breakdown structure are outputs of estimate activity resources process, so this information needs to be updated in project documentation.
[1 - 3.4.7 Estimate activity resources]
Question 53 |
Which processes are connected via project integration management?
A | Develop project chapter and project management plan, direct and manage project execution, monitor and control project work, perform integrated change control, close project phase. |
B | Plan quality, perform quality assurance and quality control. |
C | Collect requirements, define scope, create WBS, verify scope, control scope. |
D | Estimate costs, determine budget, control costs. |
Question 53 Explanation:
Project integration management connects all project process groups via the following processes: develop project chapter and project management plan, direct and manage project execution, monitor and control project work, perform integrated change control, close project phase.
[1 - 3.1 Project Management Process Groups and Knowledge Areas]
Question 54 |
What tool the economic model uses for project selection?
A | Extended value. |
B | Future value. |
C | Budget structure. |
D | Present value. |
Question 54 Explanation:
Present value is one of the economic models used for project selection.
Question 55 |
What type of measurements use performance measurement baseline?
A | Planned and actual costs. |
B | Earn value measurements. |
C | Internal rate of return. |
D | Performance index. |
Question 55 Explanation:
Earn value measurements use performance measurement baseline.
[1 - Develop Project Management Plan: Outputs]
Question 56 |
Which document describes the integrity of the performance measurement baselines will be supported on the specific project?
A | Project management plan. |
B | Performance management manual. |
C | Corporate configuration management guide. |
D | Enterprise configuration management system. |
Question 56 Explanation:
Project management plan describes the integrity of the performance measurement baselines will be supported on the specific project.
[1 - Develop Project Management Plan: Outputs]
Question 57 |
How detailed the project subsidiary plans need to be?
A | Subsidiary plans need to be detailed to the extent that needed by a specific project. |
B | Subsidiary plans do not provide details about processes used on the project. |
C | Each subsidiary plan needs to be very detailed. |
D | Subsidiary plans provide only summary of the subject. |
Question 57 Explanation:
Subsidiary plans need to be detailed to the extent that needed by a specific project.
[1 - Develop Project Management Plan: Outputs]
Question 58 |
What the project management plan used for?
A | Execute changes and ensure the right version of the change is applied. |
B | Direct and manage project execution. |
C | Communicate with stakeholders. |
D | Integrate all processes on the project. |
Question 58 Explanation:
Direct and manage project execution means performing the work defined in project management plan to achieve the project's objectives.
[1 - Develop Project Management Plan: Outputs]
Question 59 |
In which process groups the time management knowledge area is most useful?
A | Initiating and Planning |
B | Executing and closing. |
C | Planning, monitoring and controlling. |
D | Initiating and executing. |
Question 59 Explanation:
The project time management knowledge area in mostly used in planning, monitoring and controlling process groups.
[1 - 3.1 Common Project Management Process Interactions]
Question 60 |
What type of change requests generate monitoring and controlling work?
A | Corrective, repetitive, or convention action. |
B | Corrective, preventive, defect repair. |
C | Conventional, budgeting, procurement. |
D | Preventive, progressive, preparative. |
Question 60 Explanation:
Monitoring and controlling work generate the corrective, preventive, defect repair types of change request.
[1 - 4.4 Monitoring and Control Project Work]
Question 61 |
Which document describes the life cycle selected for the project and the processes to be used in each phase?
A | Configuration plan. |
B | Project management plan. |
C | Communication plan. |
D | SDLC implementation plan. |
Question 61 Explanation:
Project management plan describes the life cycle selected for the project and the processes to be used in each phase.
[1 - Develop Project Management Plan: Outputs]
Question 62 |
To ensure a right version of project component is selected, a project management team uses _____ as a part of project management information system.
A | Quality assurance management system. |
B | Change management system. |
C | Risk management system. |
D | Configuration management system. |
Question 62 Explanation:
Configuration management system, the same as other listed here tools are part of the Project Management Information System, while Configuration Management System is responsible foe version control.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 63 |
Which document describes the level of implementation of each process used in the project?
A | Procurement plan. |
B | Configuration plan. |
C | Project management plan. |
D | Communication plan. |
Question 63 Explanation:
Project management plan describes the level of implementation of each process used in the project.
[1 - Develop Project Management Plan: Outputs]
Question 64 |
Which process uses the payback period as one of the economic models?
A | Finalize requirements. |
B | Project selection. |
C | Develop project plan. |
D | Product selection. |
Question 64 Explanation:
Payback period is used in project selection process; as shorter payback period the project is more preferable.
Question 65 |
What type of information describes the organizational structure and culture, infrastructure and administration of human resources system?
A | Business plan. |
B | Organizational process assets. |
C | Change management guidelines. |
D | Enterprise environmental factors. |
Question 65 Explanation:
This information is a part of enterprise environmental factors.
[1 - 4.2.1 Develop Project Management Plan: Inputs]
Question 66 |
A project manager estimates resources activities. What information needs to be used to complete the task?
A | Activity resources requirements. |
B | Project schedule network diagram. |
C | Resource breakdown structure. |
D | Resources calendar. |
Question 66 Explanation:
Resources calendar is the input to estimate activity resources along with activity list, activity attributes, enterprise environmental factors and organizational process assets.
[1 - 3.4.7 Estimate activity resources]
Question 67 |
Which project management knowledge areas are coordinated and unified via project integration management?
A | Time, cost, human resources, communications, procurement. |
B | Quality, procurement, risk, communications. |
C | Scope, time, cost, procurement. |
D | Quality, human resources, communication, procurement. |
Question 67 Explanation:
Project integration management coordinates and unifies the quality, human resources, communication and procurement.
[1 - 3.5 Executing Process Group]
Question 68 |
Which techniques use scoring models for project selection?
A | Benefit measurement methods. |
B | Project categorizing. |
C | Mathematical approach. |
D | Linear programming. |
Question 68 Explanation:
Scoring models is one of the benefit measurement methods used for project selection.
Question 69 |
What baselines are used in project performance measurement?
A | Cost, scope, quality. |
B | Schedule, scope, procurement. |
C | Cost, scope, risk. |
D | Schedule, cost performance, scope. |
Question 69 Explanation:
Schedule, cost performance and scope baselines are called performance measurement baselines.
[1 - 4.2 Develop Project Management Plan]
Question 70 |
Impact to which knowledge area may effect a change?
A | Scope, cost, time and risk. |
B | All knowledge areas may be effected by change. |
C | Initiating, planning, executing, monitoring and controlling, and closing. |
D | Time, communications and procurement. |
Question 70 Explanation:
All knowledge areas may be effected by change. Initiating, planning, executing, monitoring and controlling, and closing are not knowledge areas but process groups.
[1 - 4.5 Perform Integrated Change Control]
Question 71 |
What document describes customer's or sponsor's business needs, future product scope, and how the project fits into their strategic plan?
A | Business Case. |
B | Project statement of work (SOW) |
C | Work brake structure (WBS). |
D | Profit/lost analysis. |
Question 71 Explanation:
Project statement of work (SOW) is the right answer. This document is usually created by customer or sponsor, and
used in project selection and an input to develop project charter.
[1 - 4.1.1.1 Project Statement of Work]
Question 72 |
Which of the following processes execute integration management?
A | Perform team building activities, hold meetings and provide records into issue logs. |
B | Administer procurement. |
C | Acquire formal acceptance of the interim and final project results. |
D | Reviewing and managing change requests to the deliverables, organizational process assets, project documents, and the project management plan. |
Question 72 Explanation:
The right answer means perform integrated change control.
[1 - Project Integration Management processes]
Question 73 |
Risks is the major theme on the project team meetings. Which of the process groups deeply use project risk management knowledge area?
A | Initiating, planning and executing. |
B | Planning, monitoring and controlling. |
C | Planning and executing. |
D | Executing, monitoring and controlling. |
Question 73 Explanation:
Planning, monitoring and controlling are well integrated via project risk management knowledge.
Question 74 |
Which document describes the tools and techniques selected to execute project processes?
A | Project scope. |
B | Project management plan. |
C | Configuration plan. |
D | Project schedule. |
Question 74 Explanation:
Project management plan describes the tools and techniques selected to execute project processes.
[1 - Develop Project Management Plan: Outputs]
Question 75 |
A project manager sequences activities. What needs to be done to complete the work?
A | Determine critical path. |
B | Update project documents. |
C | Complete a list of milestones. |
D | Create WBS and WBS dictionary. |
Question 75 Explanation:
Along with creating a network diagram, the project documents need to be updated.
[1 - 3.4.6 Sequence Activities]
Question 76 |
What type of issues corrective action deal with?
A | Planned deviation with performance management baselines that accrued on the project. |
B | Potential deviation with performance management baselines. |
C | Actual deviation of project performance with performance management baselines. |
D | Potential discrepancy of project performance with project management plan. |
Question 76 Explanation:
Corrective actions deal with actual deviations of project performance with performance management baselines.
[1 - 4.4.3 Monitoring and Control Project Work: Outputs]
Question 77 |
What change management plan describes?
A | How to identify, manage and control changes on the project. |
B | Sources and methods to gather requirements and authorization of their approval. |
C | Work authorization hierarchy. |
D | Timeframe that changes need to be implemented. |
Question 77 Explanation:
Change management plan describes how to identify, manage and control changes on the project. It documents the who and how will be processing the change, the level of approval authorization, how the change control board forms and acts, how to manage and control changes, who should be involved in discussions regarding change, organizational assets to be used in managing,tracking and controlling the change. Change management plan covers whole project as well as each specific knowledge area knowledge area (scope, time, cost, people, and others).
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 78 |
What is the objective of preventive action?
A | Declining the activities that may negatively affect the project cost or schedule. |
B | Executing the project work to reduce probability of negative results associated with project risks. |
C | Executing the project work to ensure the expected future performance is inline with the project management plan. |
D | Implementing formally documented work to compensate the defect component in recommended way whether repair of replacement. |
E | Declining the activities that may negatively affect the project cost or schedule. |
Question 78 Explanation:
The objective of preventive action assures the expected future performance is inline with the project management plan.
[1 - 4.3 Direct and Manage Project Execution]
Question 79 |
Which of the following occurs in all project management knowledge areas?
A | Integration. |
B | Communicaiton. |
C | Monitoring and controlling. |
D | Quality management. |
Question 79 Explanation:
Integration management occurs in all project management knowledge areas.
[1 - Project Integration Management processes]
Question 80 |
Which process delivers a list of milestones?
A | Define activities. |
B | Determine what needs to be purchased. |
C | Create WBS and WBS dictionary. |
D | Create network diagram. |
Question 80 Explanation:
A list of milestones is one of the outputs of define activities process.
[1 - 3.4.5 Define Activities]
Question 81 |
Which processes in the PMBOK Guide should be utilized on the project?
A | Project manager determines which processes to be utilized depends on the project needs. |
B | Project manager selects only those processes in the PMBOK Guide related to procurement to ensure the project meets its objectives. |
C | Only those processes which described in the PMBOK Guide should be utilized on the project. |
D | All processes in the PMBOK Guide should be utilized on the project. |
Question 81 Explanation:
Project manager determines which processes to be implemented depends on the project needs.
Question 82 |
What information contains project charter contains?
A | Project approval requirements, name/role and authority and responsibilities of project manager, name and authority of the signing person, who authorizes the project. |
B | Purpose and justification of the project, measurable objectives and success criteria. |
C | All. |
D | High level descriptions of the project, requirements and risks, summaries of the milestone schedule and budget. |
Question 82 Explanation:
Project charter contains the purpose and justification of the project, measurable objectives and success criteria, high level descriptions of the project, requirements and risks, summaries of the milestone schedule and budget, project approval requirements, name/role and authority and responsibilities of project manager, name and authority of the authorizing person.
[1 - 4.1.3 Develop Project Charter: Outputs]
Question 83 |
All of the following is the part of integrated change control system except _____.
A | Standards and policies. |
B | Meetings and forums. |
C | Historical information. |
D | Processes and plans. |
Question 83 Explanation:
Historical information is the part of enterprise environment factors, that used for improvement of processes and procedures and is not a part of change management system.
Question 84 |
What activities includes project monitoring?
A | Regulating and reporting project performance activities. |
B | Identifying project performance trends through the constant measurements in all stages of work. |
C | Tracking changes through the project stages and applying trends. |
D | Collecting, measuring, distributing information related to project performance, and identifying trends. |
Question 84 Explanation:
While monitoring of the project and controlling work includes tracking, reviewing, and regulating activities to meet project performance objectives described in project management plan, the monitoring activities are collecting, measuring, and distributing information related to project performance, and identifying project performance trends.
[1 - 4.4 Monitoring and Control Project Work]
Question 85 |
What change management plan documents?
A | How changes will be implemented. |
B | How changes will be communicated to the stakeholders. |
C | How changes in the system will be deployed. |
D | How changes will be monitored and controlled. |
Question 85 Explanation:
Change management plan describes how changes will be monitored and controlled. This document is a part of project management plan.
[1 - Develop Project Management Plan: Outputs]
Question 86 |
Which process group uses stakeholder risk tolerances while apprising project performance?
A | Initiating. |
B | Monitoring and Controlling. |
C | Initiating. |
D | Closing. |
Question 86 Explanation:
Stakeholder risk tolerances are used in the monitoring and controlling process group while apprising project performance. The stakeholder tolerances is a part of enterprise environment factors.
[1 - 4.4.1 Monitoring and Control Project Work: Inputs]
Question 87 |
What parts of the project should be monitored and controlled?
A | Planning, executing and closing. |
B | Planning and executing. |
C | All parts from initiating through closing. |
D | Executing and closing. |
Question 87 Explanation:
Monitoring and controlling applies through all phases of the project.
[1 - 4.4 Monitoring and Control Project Work]
Question 88 |
What is the meaning of project monitoring and controlling?
A | Measuring against cost management baseline. |
B | Measuring against cost and time management baselines. |
C | Measuring against project management plan and management baselines. |
D | Measuring against cost management baseline. |
Question 88 Explanation:
Monitoring and controlling a project means measuring against project management plan and management baselines.
[1 - 4.4 Monitoring and Control Project Work]
Question 89 |
A new project manager requests to double a staff on the project to ensure that project performance will rise twice too. What judgement applies to this situation?
A | Logistic function. |
B | Rule 20/80. |
C | Law Murphy. |
D | Law of diminishing returns. |
Question 89 Explanation:
Law of diminishing returns (also called diminishing marginal returns) is the decrease in the marginal (per-unit) output of a production process as the amount of a single factor of production is increased, while the amounts of all other factors of production stay constant. This means that at certain point, the extending a number of resources may not be increasing performance on the project, additional coordination may require.
Question 90 |
Which document provides necessarily information to determine whether or not the project is worth the required investment?
A | Marketing plan. |
B | Financial plan. |
C | Business case. |
D | Project charter. |
Question 90 Explanation:
Business case is the document that provides the necessary information for project investment.
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 91 |
What process identifies the specific actions to deliver project results?
A | Define activities. |
B | Develop schedule. |
C | Create WBS and WBS dictionary. |
D | Create network diagram. |
Question 91 Explanation:
Define activities process identifies the specific actions to deliver project results.
[1 - 3.4.5 Define Activities]
Question 92 |
As an input to project charter, what information is provided in business case?
A | Project and product scope, project plan. |
B | Market demands, organizational needs, customer or user requests, technological advancements, ecological, legal or social needs. |
C | Product quality requirements and project risks. |
D | Project scope management plan, project cost management plan, project communication plan, project improvement plan. |
Question 92 Explanation:
Business case provides the information to justify if the project is worth the required investment. Usually the business need and cost-benefit analysis is the part of business case document.
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 93 |
New software product will be using an application programming interface that already utilized in the company's information system. What type of information is this?
A | Organizational process assets. |
B | Enterprise environmental factors. |
C | Project management training system. |
D | Lessons learned from the knowledge database. |
Question 93 Explanation:
Information about the existing systems is a part of enterprise environmental factors.
Question 94 |
A customer requests change in the scope of the project which also changes the project schedule. What is the next action of the project manager?
A | Formally request approval of change. |
B | Analyze what impact to other project knowledge areas may cause the change. |
C | Implement change. |
D | Evaluate the cost of change. |
Question 94 Explanation:
Project manager must analyze what impact to other project knowledge areas may cause the change.
Question 95 |
Which process groups support project procurement knowledge area?
A | Initiating, planning and executing. |
B | Planning and executing. |
C | Executing, monitoring and controlling, and closing. |
D | Planning, executing, monitoring and controlling, closing. |
Question 95 Explanation:
Procurement knowledge area supports the planning, executing, monitoring and controlling, closing process groups.
[1 - 3.1 Common Project Management Process Interactions]
Question 96 |
What deliverables monitoring and controlling work produces?
A | Executed change, project management plan updates and risk log update. |
B | Complete change, change log update project management document updates. |
C | Change requests, project management plan updates and project management document updates. |
D | Change register log update, project management plan updates and project management updates. |
Question 96 Explanation:
Monitoring and controlling work produces change requests and updates of project management plan and project documents.
[1 - 4.4 Monitoring and Control Project Work]
Question 97 |
What of the following is used as a measuring reference for identifying project status?
A | Time schedule. |
B | Work breakdown structure. |
C | Cost constrains. |
D | Project management plan and base lines. |
Question 97 Explanation:
Project management plan and base lines are used as a reference to identifying project status.
Question 98 |
A project sponsor requested change that does not fit the project scope and requires resources with different skills. Project manager identified that new requirements can be completed separately from this project. What project manager needs to do best?
A | Request the change management board to review and reject the change. |
B | Resing. |
C | Develop a project charter. |
D | Accept the change and initiate new activities within the project. |
Question 98 Explanation:
While the requested new functionality can be done in parallel with existing project an required new resources, initiation a new project would be the best decision. So, create a charter for new project is the right choice.
Question 99 |
A project manager identified that an updated _____ needs to be used for creating a schedule network diagram.
A | Enterprise environmental factors. |
B | Configuration management plan. |
C | Project scope statement. |
D | Resource breakdown structure. |
Question 99 Explanation:
Project scope statement along with lists of activities and milestones, and organizational process assets are used as an input to creating network diagram.
[1 - 3.4.6 Sequence Activities]
Question 100 |
A project team completed implementing a change requested by stakeholders; What needs to be done next?
A | Implement the next change. |
B | Analyze if the change is affected the other parts of the system. |
C | Report the completion of change. |
D | Update project documentation. |
Question 100 Explanation:
One of the outputs of change management process is update project documentation. The influence of change to entire system is a part of implementation process that cannot be completed without such analysis/testing.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 101 |
Which process groups use project quality management knowledge area?
A | Planning and executing. |
B | Initiating, executing, planning. |
C | Planning, executing and closing. |
D | Planning, executing, monitoring and controlling. |
Question 101 Explanation:
Planning, executing, monitoring and controlling are mostly used in project quality management knowledge area.
Question 102 |
What outputs produces the direct and manage project execution process?
A | Deliverables, work performance information, change requests, project management plan and project documents updates. |
B | Deliverables, work performance information, change requests, and project requirements updates. |
C | Deliverables, work performance information, change requests, project communication plan and project guidelines updates. |
D | Deliverables, work performance information, change requests, project management plan, and project scope updates. |
Question 102 Explanation:
Deliverables, work performance information, change requests, project management plan and project documents updates are outputs of the direct and manage project execution process.
[1 - 4.3 Direct and Manage Project Execution]
Question 103 |
What information the historical records usually hold?
A | All and not limited to listed here. |
B | WBSs, benchmarks and reports. |
C | Risks, estimates, required resources, communications. |
D | Project plans, activities and lessons learned. |
Question 103 Explanation:
All but not limited to the mentioned here materials can be stored for future references.
Question 104 |
A project manager completed _____ to ensure the project team uses s right version of project documents.
A | Quality assurance management plan. |
B | Risk management plan. |
C | Configuration management plan. |
D | Change management plan. |
Question 104 Explanation:
Configuration management plan describes the way how version control on the project will work.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 105 |
What should concern a project manager when a few people are signing the project charter?
A | Reporting structure. |
B | Change management. |
C | Communication with larger community. |
D | Configuration management. |
Question 105 Explanation:
A number of people signed the project charter may indicate a number of business areas related to the project. Configuration management becomes more complex when many stakeholders have strong influence on the project. More coordination on the priorities of each stakeholder requires more efforts.
Question 106 |
Which process is used to elaborate, control update and approve the results of project management plan?
A | Perform quality assurance. |
B | Perform integrated change control. |
C | Process quality management procedures. |
D | Execute risk response plan. |
Question 106 Explanation:
The results of project management plan are elaborated through the perform integrated change control.
[1 - 4.2 Develop Project Management Plan]
Question 107 |
Who is using the direct and manage project execution process?
A | Project team. |
B | Project manager. |
C | Stakeholders and management. |
D | Project manager and project team. |
Question 107 Explanation:
Project manager and project team are using the direct and manage project execution process to manage project.
[1 - Direct and Manage Project Execution]
Question 108 |
A project manager works on a large project, and responsible for all stages of the product development from initiation to closing. What of the following describes project manager's activities best?
A | Project manager leads project through its critical path and obtains acceptance by stakeholders. |
B | Project manager follows project management plan to ensure completeness of deliverables on time and schedule. |
C | Project manager manages stakeholders expectations to deliver the product or services that satisfy their interests. |
D | Project manager performs integration management processes. |
Question 108 Explanation:
Project manager performs integration management processes.
[1 - Executing Process Group]
Question 109 |
Which project knowledge areas require management plan?
A | Scope, time, cost, quality, human resources, communications, risk, procurement and customer support require project management plan. |
B | Scope, time, cost, quality, human resources, communications, risk, procurement and product maintenance require project management plan. |
C | Scope, time, cost, quality, human resources, communications, risk, and procurement require project management plan. |
D | Scope, time, cost, quality, human resources, communications, risk, configuration management, operations, and procurement require project management plan. |
Question 109 Explanation:
Scope, time, cost, quality, human resources, communications, risk, and procurement require project management plan.
Question 110 |
What opportunity cost does mean?
A | The cost of a not selected project. |
B | The value of a not selected project(s). |
C | The cost of a selected project. |
D | The value of a selected project. |
Question 110 Explanation:
The value of a not selected project named opportunity cost.
Question 111 |
What of the following are considered as organizational process assets?
A | Organizational standards, processes, policies and procedures. |
B | Project control system and integrated change management system. |
C | Business case and project charter. |
D | Statement of work and business case. |
Question 111 Explanation:
Organizational standard processes and procedures are considered as organizational process assets?
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 112 |
What should be done to project documentation during project closing?
A | Copy all documents and record to your own library for further references. |
B | Index and archive records. |
C | Destroy all records and documents. |
D | Keep the records as is for further use. |
Question 112 Explanation:
Indexing and archiving project records and documents is a mandatory procedure during project closure.
[1 - 4.6 Close Project or Phase]
Question 113 |
To which process group the perform integrated change control belongs?
A | Executing. |
B | Monitoring and controlling. |
C | Closing. |
D | Planning. |
Question 113 Explanation:
Perform integrated change control belongs to monitoring and controlling process group and is a part of the integration management.
[1 - Chapter 3.6.1 Perform Integrated Change Control]
Question 114 |
What information is required to define activities?
A | Project scope baseline, enterprise environment factors, organizational process assets. |
B | Work breakdown structure, enterprise environment factors, organizational process assets. |
C | Finalized project requirements, enterprise environment factors, organizational process assets. |
D | Project schedule, enterprise environment factors, organizational process assets. |
Question 114 Explanation:
Project scope baseline, enterprise environment factors and organizational process assets are inputs to define activities process.
[1 - 3.4.5 Define Activities]
Question 115 |
What tools project manager uses while develops project management plan and adapts processes to meet the project needs?
A | Benefit/cost analysis. |
B | Expert judgement. |
C | Profit/lose analysis. |
D | Murder board. |
Question 115 Explanation:
Project manager uses expert judgement while develops project management plan and adapts processes to meet the project needs.
[1 - Develop Project Management Plan: Tools and Techniques]
Question 116 |
What biggest project manager's effort is required during project integration processes?
A | Implementing changes. |
B | Identifying requirements. |
C | Planning and managing changes. |
D | Communication. |
Question 116 Explanation:
Statistically, project managers spend over 90% of their time on communications.
Question 117 |
What is the purpose of work authorization system?
A | Manage when and who will be doing the project work. |
B | Manage the time and sequence of the work to be done. |
C | Manager what should be done and who will execute the work. |
D | Manage who will be executing the project work. |
Question 117 Explanation:
Manage the time and sequence of the work to be done is the purpose of work authorization system.
Question 118 |
What of the following is one of the economic models used in project selection?
A | Benefit-cost ratio. |
B | Peer review. |
C | Murder board. |
D | Profit lost analysis. |
Question 118 Explanation:
Benefit-cost ratio is one of the economic models used in project selection.
Question 119 |
Which knowledge areas are applied to project execution process group?
A | Scope, time, quality, human resources, communications, risk, procurement. |
B | Scope, time, cost, quality, human resources, communications, risk, procurement. |
C | Quality, human resources, communications, risk, procurements. |
D | Cost, time, quality, communications, risk, procurement. |
Question 119 Explanation:
The following knowledge areas are used during project execution: quality, human resources, communications, risk, and procurements.
Question 120 |
What tools and techniques are used in develop project management plan?
A | Murder board and peer review. |
B | Expert judgement. |
C | Leverage. |
D | Profit and lost analysis. |
Question 120 Explanation:
Expert judgement is used in develop project management plan process.
[1 - 4.2.1 Develop Project Management Plan: Inputs]
Question 121 |
What is sunk cost?
A | Amount of money to be spent on unplanned expenses during the project execution. |
B | Amount of money to be spent on possible changes in the project in other words contingency fund. |
C | Already spent money that do not count in project selection. |
D | Amount of money that spent on previous version of product or service. This amount is taken as a base in project selection. |
Question 121 Explanation:
Sunk cost is the amount of money that already spent on the project, and do not counted in project selection.
Question 122 |
Why iteration process is required?
A | Iteration process helps to identify and execute the required changes. |
B | Iteration process helps to adjust management plans making them more realistic. |
C | Iteration process is the part of integrated configuration management and ensures the right versions of the organizational assets are used. |
D | Iteration process puts together management plans and procurement documents. |
Question 122 Explanation:
Iteration process helps to adjust management plans and make them more realistic. Due to most of planning processes depend on each other, result of one process may effect to results of other processes. That's why the sequence of the processes is important as well as their international revision.
Question 123 |
A project team uses _____ to ensure the project documents are updated.
A | Configuration management plan. |
B | Document management system. |
C | Change management plan. |
D | Communication management plan. |
Question 123 Explanation:
While the other answers also have their place in the process, configuration management plan ensures that all project documentation is updated and the latest version is used.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 124 |
What type of information the governmental or industry standards is?
A | Enterprise environmental factors. |
B | Common understanding of project scope. |
C | Organizational process assets. |
D | Integrated change control. |
Question 124 Explanation:
Government standards can be a part of enterprise environmental factors.
[1 - 4.2.3 Develop Project Management Plan: Inputs]
Question 125 |
During project executions, in order to expedite implementation of a change, project manager is modifying a sequence in communications in the change management process. What the project management is working on?
A | Change management. |
B | Process improvement. |
C | Developing a unique product or services. |
D | Communication management. |
Question 125 Explanation:
This is a project manager's duty to selecting and constantly improving project processes for the sake of time, cost and quality of project deliverables.
Question 126 |
How an expert judgement helps in develop project management plan?
A | Adjust the processes for project needs, uncover technical and management details, identify resources requirements, determine the required level of configuration management and which documents will be under the formal change control process. |
B | Supporting project manager by providing historical information through the corporate knowledge management system. |
C | Assisting project manager in planning, executing and closing of the project. |
D | Provide management leadership on the project. |
Question 126 Explanation:
Expert judgement is used as tools and techniques in develop project management plan.
[1 - 4.2.2 Develop Project Management Plan: Tools and Techniques]
Question 127 |
A project manager is identifying relationship between the project activities. What project process project manager performs?
A | Determine quality requirements. |
B | Create network diagram. |
C | Define activity. |
D | Create WBS and WBS dictionary. |
Question 127 Explanation:
project manager creates network diagram; in other words sequences activities.
[1 - 3.4.6 Sequence Activities]
Question 128 |
What the performance management baseline may combine to measure overall project performance?
A | Scope, cost, and communication baselines. |
B | Cost, schedule, scope and risk management baselines. |
C | Cost, schedule, and procurement baselines. |
D | Scope, cost, and schedule baselines. |
Question 128 Explanation:
Scope, cost, and schedule baselines can be used as a project baseline to measure overall performance.
[1 - 4.2.3 Develop Project Management Plan: Outputs]
Question 129 |
What process is influenced by enterprise environment factors during project initiation?
A | Create product scope statement. |
B | Develop procurement plan. |
C | Develop quality management plan. |
D | Develop project charter. |
Question 129 Explanation:
Enterprise environment factors are the input to develop project charter, and the project charter is developed during project initiation.
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 130 |
Which inputs develop project charter process requires?
A | Project statement of work, business case, contracts, enterprise environmental factors, historical records, list of assumptions and constrains. |
B | Project statement of work, business case, contracts, enterprise environmental factors, historical records, list of assumptions and constrains, list of stakeholders with their roles and influence to the project. |
C | Project statement of work, business case, contracts, enterprise environmental factors, organizational assets. |
D | Project statement of work, business case, contracts, enterprise environmental factors, list of stakeholders. |
Question 130 Explanation:
Project statement of work, business case, contracts, enterprise environmental factors, organizational assets are the required inputs to develop project chapter.
Question 131 |
What are the deliverables of the project?
A | Any results of the phase, or project. |
B | The product, result, or service that accepted by user. |
C | Any approved unique and verifiable products, results, or capabilities of service that produced by a complete process, phase, or project. |
D | Any products, results, or capabilities of service that accepted by stakeholders. |
Question 131 Explanation:
Referring to project definition, any approved unique and verifiable products, results, or capabilities of service that produced by a complete process, phase, or project.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 132 |
Which knowledge area is mostly used when project just starts?
A | Communications. |
B | Procurement. |
C | Quality. |
D | Risk. |
Question 132 Explanation:
During project execution communications process is most useful.
Question 133 |
Expert judgement is one of the assessment tools for inputs to develop project charter. What sources can be used for expert judgement?
A | All choices are right. |
B | Stakeholders, professional and technical associations and industry groups. |
C | Subject matter experts and project management office (PMO). |
D | Other units of the company or organization of the industry. |
Question 133 Explanation:
All choices are right, but not limited to listed here. These sources can be used in assessing the project charter inputs.
[1 - 4.1.2 Develop Project Charter: Tools and Techniques]
Question 134 |
To which process group belongs configuration management system?
A | Executing. |
B | Monitoring and controlling. |
C | Initiating. |
D | Closing, |
Question 134 Explanation:
Configuration management is a part of monitoring and controlling process group and can be a part of the integrated control management system, which belongs to enterprise environment factors.
[1 - 4.4 Monitoring and Control Project Work]
Question 135 |
What is a work authorization?
A | Procedure to select and vendors. |
B | Buyer's direction to a seller on how the work should be executed. |
C | Permission and direction to start a specified work in accordance to specific time and sequence. |
D | Change management. |
Question 135 Explanation:
Work authorization a permission and direction to start a specified work in accordance to specific time and sequence.
[1 - 4.4.1 Monitoring and Control Project Work: Inputs]
Question 136 |
Deliverable of which process provides formal authorization of a project and documents the initial requirements that satisfy the stakeholders' needs and expectations?
A | Create business case. |
B | Develop final project management plan. |
C | Create project scope statement. |
D | Develop project charter. |
Question 136 Explanation:
Develop project charter provides formal authorization of a project and documents initial requirements that satisfy the stakeholders' needs and expectations.
[1 - 4.1 Develop Project Charter]
Question 137 |
Which process is used to make changes in the completed baseline of project management plan?
A | Integrate change management monitoring system. |
B | Change management coordination guide. |
C | Perform integrated change management control. |
D | Execute change management schedule. |
Question 137 Explanation:
Perform integrated change management control to be used to manage changed in the completed project management baseline.
[1 - Develop Project Management Plan: Outputs]
Question 138 |
What information the project statement of work (SOW) refers to as an input to develop project charter?
A | Product description, budget and time constrains, product quality requirements, financial schedule. |
B | Product descriptions, list of stakeholders, quality requirements, budget, marketing schedule. |
C | Business plan, market needs, product description, project budget, time schedule, production plan. |
D | Business need, product scope description, strategic plan. |
Question 138 Explanation:
The project initiator or sponsor provides the statement of work (SOW) based on business need, product or service requirements, and organizational strategic plan. SOW often provided as a part of request for proposal (RFP), request for information (RFI) of other bidding documents or as part of a contract.
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 139 |
What type of project selection technique uses programming methods?
A | Economic models. |
B | Benefit measurement methods. |
C | Constrain optimization method. |
D | Comparative approach. |
Question 139 Explanation:
Constrain optimization method in other words mathematical approach uses programming techniques in project selection.
Question 140 |
A project manager collects documents for creating a schedule network diagram. What is missing?
A | Estimation of resources activities and milestones. |
B | Activity attributes and milestones. |
C | Enterprise environmental factors and activity resource requirements. |
D | Resource breakdown structure and activity list. |
Question 140 Explanation:
Activity attributes and milestones are input to sequence activities process along with activity list project scope statement and organizational process assets.
[1 - 3.4.6 Sequence Activities]
Question 141 |
Project manager uses _____ while developing project management plan?
A | Murder board. |
B | Profit/lose analysis. |
C | Benefit/cost analysis. |
D | Expert judgement. |
Question 141 Explanation:
Expert judgement is the tool for developing project management plan.
[1 - Develop Project Management Plan: Tools and Techniques]
Question 142 |
What input is required to create scope baseline?
A | Project scope statement, requirements, organizational process assets. |
B | Project charter, project scope statement, project requirements, enterprise environmental factors. |
C | Project charter, contracts, project scope statement, project requirements, organizational process assets. |
D | Project scope statement, enterprise environment factors, requirements documentation. |
Question 142 Explanation:
Since the scope baseline is an output of create WBS process, its inputs are applied.
Question 143 |
What project should be selected if the net present value of the first project is $150K for three years and the second project has $250K for five years?
A | First project. |
B | Project with shorter period of time. |
C | Both projects are equal. |
D | Second project. |
Question 143 Explanation:
The second project to be chosen as it's net present value is bigger; duration of the project is not important.
Question 144 |
During what part of a project the perform integrated change control process is performed?
A | Initiation execution and closing. |
B | Through inception to completion. |
C | Planning, execution and closing. |
D | Through execution and closing. |
Question 144 Explanation:
Perform integrated change control process is performed through all stages of the project from inception to completion.
[1 - 4.5 Perform Integrated Change Control]
Question 145 |
What is the purpose of business case?
A | Financial needs for the project. |
B | Marketing plan. |
C | Strategic vision of the company. |
D | Justification of the project. |
Question 145 Explanation:
Typically business case describes business needs and cost-benefits analysis to justifies the project. This document may contain such points as market demands, organizational needs, customer request, technological advantage, legal requirements, ecological impacts or social needs.
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 146 |
How a project management information system is used by the direct and manage project execution process?
A | Financial and human resources management systems that used in planning, executing and closing process groups. |
B | Scheduling, configuration, access to project information. |
C | A collection of tools for using during planning and executing of the project. |
D | Project financial management system that uses throughout all process groups of the project. |
Question 146 Explanation:
Scheduling, configuration, access to project information and other software tools are used by the direct and manage project execution process.
[1 - 4.3 Direct and Manage Project Execution]
Question 147 |
A project manager was assigned to project selection work. It will be needed determine whether continue or not a project that has been interrupted two year ago. All the following will be considered except _____.
A | Net present value. |
B | Pay back period. |
C | Benefit-cost ratio. |
D | Spent funds. |
Question 147 Explanation:
Spent funds, in other words sunk cost, is not considered in project selection.
Question 148 |
A project team is revising requirements during project execution. What document should be used in this work?
A | Communication management plan. |
B | Requirements management plan. |
C | Process improvement plan. |
D | Configuration management plan. |
Question 148 Explanation:
Requirements management plan outlines the way to identify, manage, and control the requirements.
[1 - 5. Cost Management]
Question 149 |
What of the following is used as a measuring reference for identifying project performance?
A | Baseline of the project deliverables. |
B | Baselines of the scope, schedule and cost. |
C | Baseline of the scope and quality requirements. |
D | Baselines of the schedule for processing changes. |
Question 149 Explanation:
Baselines of the scope, schedule and cost are used for identifying and reporting project performance.
[1 - 4.4 Monitoring and Control Project Work]
Question 150 |
What should be done next when all the requirements of the project have been achieved?
A | Report to stakeholders that project is closed. |
B | Hold a team meeting and analyze what records to be provided to lessons learned. |
C | Award project team members. |
D | Close procurements. |
Question 150 Explanation:
After the project deliverables have been verified, the project procurements have to be closed.
[1 - 4.6 Close Project or Phase]
Question 151 |
What would be the last process to be executing on a project?
A | Get sign off on the deliverables. |
B | Confirm that project work is completed against the requirements. |
C | Release resources. |
D | Document lessens learned. |
Question 151 Explanation:
The last process on the project would be release the project resources; you might be needed some of the resources until the product is hand off.
Question 152 |
Communications is one of the key knowledge areas in project management. During which process groups communications occurred the most?
A | Initiation, planning, executing, monitoring and controlling. |
B | Monitoring and controlling. |
C | Executing and closing. |
D | Initiation, planning and closing. |
Question 152 Explanation:
Communications are most used during the initiation, planning, executing, controlling and monitoring process groups.
Question 153 |
Which of the following processes is considered as integration management?
A | Confirm the work is completed to requirements. |
B | Develop project charter. |
C | Develop quality management plan. |
D | Develop procurement plan. |
Question 153 Explanation:
Develop project charger is one of the integration management processes.
[1 - Project Integration Management processes]
Question 154 |
Project management have to decide how to plan; what this means?
A | Gather the project requirements, put together the project management plans as a part of the project integrated framework. |
B | Put together the project scope, product scope, time and cost constrains as preparation for develop management plans. |
C | Identify stakeholders needs and describe them through the series of management plans. |
D | Determine the required processes and standards and templates for creating management plans. |
Question 154 Explanation:
Determine the required processes, standards and templates for creating management plans.
Question 155 |
During what process group the perform integrated change control performed?
A | Monitoring and controlling. |
B | Executing. |
C | Closing. |
D | Planning. |
Question 155 Explanation:
Most activities of integrated change control are performed during monitoring and controlling processes.
[1 - 4.5 Perform Integrated Change Control]
Question 156 |
Project manager completes defining activities. What information needs to be formulated?
A | WBS and WBS dictionary. |
B | Project schedule. |
C | Activity attributes. |
D | List of risks. |
Question 156 Explanation:
Activity attributes is one of the outputs of define activities process among the lists of activities and milestones.
[1 - 3.4.5 Define Activities]
Question 157 |
What inputs uses the direct and manage project execution process?
A | Subsidiary management plan, approve changes, enterprise environment factors, organizational process assets. |
B | Project management plan, approve changes, enterprise environment factors. |
C | Project scope, project management plan, approve changes, enterprise environment factors, organizational process assets. |
D | Project management plan, approve changes, enterprise environment factors, organizational process assets. |
Question 157 Explanation:
The project scope has been used in planning documents; so, direct and manage project execution process uses the following inputs: project management plan, approve changes, enterprise environment factors, organizational process assets.
[1 - 4.3 Direct and Manage Project Execution]
Question 158 |
What is the straight line depreciation?
A | Complete reduction of an asset's value. |
B | Annual reduction of an asset's value by progressive amounts. |
C | Annual reduction of an asset's value by equal amounts. |
D | Complete reduction of the all assets' value. |
Question 158 Explanation:
Straight line depreciation is the annual reduction of an asset's value by equal amounts.
Question 159 |
What of the following is considered as organizational process assets?
A | Business case. |
B | Templates. |
C | Business plan. |
D | Statement of work. |
Question 159 Explanation:
Templates that can be used on the project are considered as organizational process assets.
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 160 |
What tools and techniques is used on monitoring and controlling work?
A | Expert judgement. |
B | Profit lost analysis. |
C | Delphi method. |
D | Peer review. |
Question 160 Explanation:
Project team and project manager use expert judgement for monitoring and controlling work on projects.
[1 - 4.4 Monitoring and Control Project Work]
Question 161 |
What tools project manager uses while develops technical and management details for project management plan?
A | Benefit/cost analysis. |
B | Profit/lose analysis. |
C | Expert judgement. |
D | Murder board. |
Question 161 Explanation:
Project manager uses expert judgement while develops technical and management details for project management plan.
[1 - Develop Project Management Plan: Tools and Techniques]
Question 162 |
What role project manager may play while a customer develops a project charter.
A | Initiating. |
B | All choices are right. |
C | Authorizing. |
D | Assisting. |
Question 162 Explanation:
Issuing and authorizing a project charter is a responsibility of project sponsor. Quite often a project manager supports project sponsor in developing and coordinating the development of this document.
Question 163 |
What knowledge area pf project management leads to realistic project management plan?
A | Work breakdown structure. |
B | Identification of risks and developing risk response plan. |
C | Integration. |
D | Network diagram. |
Question 163 Explanation:
Integration during planning allows to deliver a realistic project management plan.
Question 164 |
Which document outlines how the selected process will be used to on the specific project?
A | Project scope management plan. |
B | Project cost and time management plans. |
C | Procurement management plan. |
D | Project management plan. |
Question 164 Explanation:
Project management plan outlines how the selected process will be used to on the specific project.
[1 - Develop Project Management Plan: Outputs]
Question 165 |
What tools project manager applies to determine which project documents use in the formal change control process?
A | Document management system. |
B | Document routing process. |
C | Expert judgement. |
D | Peer review. |
Question 165 Explanation:
Project manager uses Expert Judgement while determines which project documents will be processed throughout the formal Change Control Process.
[1 - Develop Project Management Plan: Tools and Techniques]
Question 166 |
What input is required to provide project monitoring and closing?
A | Project management plan, performance reports, enterprise environment factors, organizational process assets. |
B | Project management plan, quality plan, risk management plan, enterprise environment factors. |
C | Project management plan, quality plan, risk management plan, enterprise environment factors, organizational process assets. |
D | Project management plan, change management plan, enterprise environment factors, organizational process assets. |
Question 166 Explanation:
Project monitoring and controlling work uses project management plan, performance reports, enterprise environment factors, organizational process assets as input.
[1 - 4.4 Monitoring and Control Project Work]
Question 167 |
What would be the next step after project manager has completed preparation of procurement documents?
A | Select sellers. |
B | Develop project management plan. |
C | Finalize how to execute and control the project. |
D | Plan communications. |
Question 167 Explanation:
Finalize how to execute and control the project is the next process after preparation of the procurement plan.
Question 168 |
Scope management is a part of which process groups?
A | Planning, monitoring and controlling. |
B | Initiating, Planning. |
C | Planning and executing. |
D | Executing and closing. |
Question 168 Explanation:
Scope management knowledge area is used in the planning, monitoring and controlling.
[1 - 3.1 Common Project Management Process Interactions]
Question 169 |
What type of issues prevention action deal with?
A | Occurred discrepancy of project performance with performance management baselines. |
B | Actual deviation of project performance with performance management baselines. |
C | Planned deviation with performance management baselines that accrued on the project. |
D | Anticipated deviation of project performance with performance management baselines. |
Question 169 Explanation:
Prevention action addresses anticipated deviation of project performance with performance management baselines.
[1 - 4.4.3 Monitoring and Control Project Work: Outputs]
Question 170 |
A project team have updated the documents after a change have been implemented. What needs to be done next?
A | Communicate with involved parties (stakeholders and project team) and formally inform about the change and refer to the changed documents. |
B | Analyze how a change affected the scope, schedule and costs of the project. |
C | Analyze and implement the next change. |
D | Inform entire company about the change and refer the changed documents. |
Question 170 Explanation:
The involved parties (stakeholders and project team) need to be formally informed about the change and referred to the changed documents.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 171 |
In which of the following activities a panel of advisers can be used to negatively influence the decisions?
A | Project selection. |
B | Project closing. |
C | Risk identification. |
D | Change management. |
Question 171 Explanation:
Murder boar in other words, a panel of people that used to identify the negative sides of new ideas is used in project selection activities.
Question 172 |
Which of the following processes refers to integration management?
A | Acquire acceptance of the intermediate deliverable from the customer. |
B | Perform integrated change control. |
C | Determine quality standards and performs quality audit. |
D | Plan communications. |
Question 172 Explanation:
Perform integrated change control is one of the integration management processes.
[1 - Project Integration Management processes]
Question 173 |
Who integrates the project?
A | Project team. |
B | Customer. |
C | Stakeholders. |
D | Project manager. |
Question 173 Explanation:
Project manger is responsible for project integration.
Question 174 |
A project manager without previous experience have been assigned to a project. What would help him the best?
A | Historical information. |
B | Dividing project to smaller and easier managed parts. |
C | Create project scope. |
D | Personal experience. |
Question 174 Explanation:
Historical information may contain information on similar project and help to fulfill the gaps.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 175 |
What project documentation needs to be updated after a change has been implemented?
A | Baselines of all management plans. |
B | Requirements, schedule, cost, and procurement management plans. |
C | Project management plan, its subsidiary management plans and other documents that affects by change. |
D | Quality assurance and financial documents. |
Question 175 Explanation:
All project documents affected by change need to be updated.
[1 - 4.3.3 Direct and Manage Project Execution: Outputs]
Question 176 |
What project processes are covered in project management plan?
A | Complete project management life cycle. |
B | Project executing and project closing. |
C | All processes from project initiation to project closing. |
D | Integrated processes in execution, monitoring and controlling, and closing. |
Question 176 Explanation:
Project management plan describes a series of integrated processes in execution, monitoring and controlling, and closing.
[1 - 4.2 Develop Project Management Plan]
Question 177 |
What are the following three major requirements a project management plan has meet?
A | Approved, realistic, formal. |
B | Brief, formal, signed. |
C | Approved, detailed, formal. |
D | Complete, detailed, signed. |
Question 177 Explanation:
A project management plan needs to be approved, realistic and formal. To be bought by a project management team, a project management plan needs to be realistic. To make a project management plan works, it should be well coordinated with stakeholders, resources managers, and the project team, it also needs to be approved and formally accepted by management.
Question 178 |
Cost management is mostly used while performing of which process groups?
A | Planning, monitoring and controlling. |
B | Executing and closing. |
C | Planning and executing. |
D | Initiating, planning, closing. |
Question 178 Explanation:
Cost management knowledge area is used in the planning, monitoring and controlling.
[1 - 3.1 Common Project Management Process Interactions]
Question 179 |
Output of which process scope baseline is created?
A | Create WBS |
B | Develop scope statement. |
C | Determine quality standards, processes and metrics. |
D | Create network diagram. |
Question 179 Explanation:
Scope baseline is created as an output of create WBS, along with WBS, WBS dictionary, and project document updates.
[1 - 3.4.4 Create WBS]
Question 180 |
What process groups are covered with direct and manage project execution process?
A | Monitoring and controlling, and closing. |
B | planning, executing, monitoring and controlling, and closing. |
C | Initiating, planning, executing, monitoring and controlling, and closing. |
D | Executing, monitoring and controlling, and closing. |
Question 180 Explanation:
Direct and manage project execution process belongs to the executing, monitoring and controlling, and closing process groups.
[1 - 4.3 Direct and Manage Project Execution]
Question 181 |
What of the following refers to project integrated management?
A | Perform the work defined in the PM plan to achieve the project's objectives. |
B | Provide integrated quality control. |
C | Develop and perform quality management plan. |
D | Identify risks and execute risk response plan. |
Question 181 Explanation:
The right answer means actually execute the project or in other words, direct and manage project execution.
[1 - Project Integration Management]
Question 182 |
What kind of projects should have a charter?
A | Projects without contracts should have charters. |
B | Large projects should have charters. |
C | Only projects under contracts should have charters. |
D | All project should have charters. |
Question 182 Explanation:
All project should have charters. Read about definition of project charter.
Question 183 |
Which part of project initiation is supported by project integration management knowledge area?
A | Identify stakeholders. |
B | Develop stakeholder management plan. |
C | Develop business case. |
D | Develop project charter. |
Question 183 Explanation:
Develop project charter is supported by project integration knowledge area.
[1 - 3.1 Project Management Process Groups and Knowledge Areas]
Question 184 |
Changes in which documents may require update to the project management plan?
A | Team performance evaluation, quality audit report. |
B | Enterprise environmental factors, organizational process assets, project charter, outputs from planning processes. |
C | Business plan, product scope, change control system. |
D | List of vendors, conflict resolution report. |
Question 184 Explanation:
Enterprise environmental factors, organizational process assets, project charter, outputs from planning processes may require update of project management plan.
[1 - 4.2.1.2 Develop Project Management Plan: Inputs]
Question 185 |
Why close a project or phase is an integrated function?
A | Closes the scope, cost, and time knowledge areas. |
B | Closes executing, monitoring and controlling processes. |
C | Closes all processes and in all project knowledge areas. |
D | Completes closing process group. |
Question 185 Explanation:
Close a project or phase is an integrated function because it focuses on closing all project knowledge areas.
[1 - 4.6 Close Project or Phase]
Question 186 |
What is the purpose of project charter?
A | Documents the risks and quality requirements. |
B | Documents the business needs, understanding of users' preferences to a new product, service or project goals. |
C | Documents the budget and time constrains. |
D | Documents the product or service requirements. |
Question 186 Explanation:
Project charter documents the business needs, understanding of users' preferences to a new product or service, or project goals.
[1 - 4.1.3 Develop Project Charter: Outputs]
Question 187 |
Which process creates activity list?
A | Create WBS and WBS dictionary. |
B | Determine what needs to be purchased. |
C | Define activity. |
D | Create network diagram. |
Question 187 Explanation:
Process define activity creates activity list.
[1 - 3.4.5 Define Activities]
Question 188 |
What is the purpose of the project management plan?
A | Defining the way of executing, monitoring and controlling, and closing the project. |
B | Determine the processes of getting requirements, developing and delivering product or services, and closing of project. |
C | Documents the procedures of delivering product or services. |
D | Determining how to planning, monitoring and controlling the project. |
Question 188 Explanation:
Project management plan defines the way of executing, monitoring and controlling, and closing the project.
[1 - 4.2 Develop Project Management Plan]
Question 189 |
What influences the content of project management plan?
A | How complex the project and where the deliverables will be used. |
B | What type of procurement is applied to the project. |
C | Cost of the project. |
D | Duration of the project. |
Question 189 Explanation:
The complexity and application area of the project are influence the content of the project management plan.
[1 - Develop Project Management Plan]
Question 190 |
Why both buyer and seller should have project charter?
A | This is right when buyer and seller belong to different companies. |
B | Different reporting structures. |
C | Two organizations may have different reasons for run the project. |
D | Different contractual obligations. |
Question 190 Explanation:
Two organizations have different reasons for run the project. Buyer may want to get a product or services but buyer to increase revenue, get a new client or enhance reputation.
Question 191 |
Which process groups are integrated via human resources knowledge area?
A | Initiating and closing. |
B | Planning, monitoring and controlling. |
C | Planning and execution. |
D | Execution, monitoring and controlling. |
Question 191 Explanation:
Planning and execution are two project process groups that integrated via human resources knowledge area.
[1 - 3.1 Common Project Management Process Interactions]
Question 192 |
Which knowledge areas are used during project planning?
A | Risk identification, risk planning, planning rewarding. |
B | Cost management, time management, quality management, risk management, stakeholder management, monitoring and controlling management. |
C | Scope, time, cost, quality, human resources, communications, risk, procurement. |
D | Scope, time, cost, stakeholder management, bookkeeping, selecting vendors. |
Question 192 Explanation:
All project management knowledge areas are applied during project planning, which are scope, time, cost, quality, human resources, communications, risk and procurement.
Question 193 |
What is the objective of corrective action?
A | Executing the project work to ensure the expected future performance is inline with the project management plan. |
B | Implementing formally documented work to compensate the defect component in recommended way whether repair of replacement. |
C | Executing the project work to reduce probability of negative results associated with project risks. |
D | Declining the activities that may negatively affect the project cost or schedule. |
Question 193 Explanation:
Corrective action is actual execution of project work to bring the expected future performance inline with the project management plan.
[1 - 4.3 Direct and Manage Project Execution]
Question 194 |
What type of reporting should be done during project closure?
A | Profit/lose analysis. |
B | Resources performance report. |
C | Final project performance report. |
D | Root cause analysis of changes on the project. |
Question 194 Explanation:
Project manager needs to complete final project performance report.
[1 - 4.6 Close Project or Phase]
Question 195 |
In which process the economic model uses internal rate of return?
A | Project selection. |
B | Determine project status. |
C | Determine risks. |
D | Determine time and costs. |
Question 195 Explanation:
Internal rate of return is used in project selection process.
Question 196 |
What does it mean direct and manage project execution?
A | Perform initiation and closing processes. |
B | Perform monitoring and controlling. |
C | Perform planning processes. |
D | Perform integration management. |
Question 196 Explanation:
Direct and manage project execution means perform integration management.
[1 - 3.29 Execute Process Group]
Question 197 |
What needs to be done next after estimation of activity resources is completed?
A | Determine critical path. |
B | Develop project schedule. |
C | Perform estimate activity duration process. |
D | Design network diagram. |
Question 197 Explanation:
Perform estimate activity duration process is the next process to be performed after the estimation of activity resources is completed.
[1 - 3.4 Planning Process Group]
Question 198 |
A project manager verified the project deliverables against project scope and complete procurements. What next to be done?
A | Release resources. |
B | Close project. |
C | Report completion of project. |
D | Get formal acceptance of the project deliverables. |
Question 198 Explanation:
Get formal acceptance of the project deliverables would be the best next step.
[1 - 4.6 Close Project or Phase]
Question 199 |
What process to be uses for managing corrective action?
A | Perform implementation of corrective action process. |
B | Implement corrective action procedure. |
C | Perform integrated change control process. |
D | Identify and address risk process. |
Question 199 Explanation:
Significant corrective actions that require change in such documents as project management plan, project charter, project scope, and policies require using perform integrated change control process.
Question 200 |
What objectives monitoring and controlling work addresses?
A | Quality objectives defined in project management plan. |
B | Project performance defined in project management plan. |
C | Satisfy the requirements submitted by stakeholders. |
D | Meet the cost, time and quality constrains described in project management plan. |
Question 200 Explanation:
Project monitoring and controlling work targets the performance objectives defined in project management plan.
[1 - 4.4 Monitoring and Control Project Work]
Question 201 |
What is the objective of defect repair?
A | Declining the activities that may negatively affect the project cost or schedule. |
B | Executing the project work to ensure the expected future performance is inline with the project management plan. |
C | Implementing formally documented work to compensate the defect component in recommended way whether repair of replacement. |
D | Executing the project work to reduce probability of negative results associated with project risks. |
Question 201 Explanation:
Defect repair is an action of compensating the defect by replacement of repair to ensure the expected future performance is inline with the project management plan.
[1 - 4.3 Direct and Manage Project Execution]
Question 202 |
Which document describes how the work on the project will be executed to achieve its objectives?
A | Communication plan. |
B | Project management plan. |
C | PMLC implementation plan. |
D | Configuration plan. |
Question 202 Explanation:
Project management plan describes how the work on the project will be executed to achieve its objectives.
[1 - Develop Project Management Plan: Outputs]
Question 203 |
One of the four projects with different budget and payback period to be selected: A - $300K, 3 years; B - $180K, 2.5 years; C - $200K, 18 months; D - $200K, 12 months. Which project to be selected?
A | Project C. |
B | Project B. |
C | Project A. |
D | Project D. |
Question 203 Explanation:
Project D to be selected as its payback period is shorter.
Question 204 |
What needs to be done after activity list is created?
A | Sequence activities. |
B | Create WBS and WBS dictionary. |
C | Update project documents. |
D | Determine what needs to be purchased. |
Question 204 Explanation:
After activity list is created, the activities need to be sequenced; in other words, a network diagram needs to be created.
[1 - Sequence Activities]
Question 205 |
When defect repair usually occurs?
A | After the project is closed. |
B | Project deliverable doesn't met the requirements. |
C | During initiation process. |
D | During planning phase of the project. |
Question 205 Explanation:
Defect repair usually occur when project deliverable doesn't met the requirements.
[1 - 4.4.3 Monitoring and Control Project Work: Outputs]
Question 206 |
What document provides the following information: business need, product scope description and strategic plan of the organization?
A | Project statement of work. |
B | Project Charter. |
C | Business case. |
D | Marketing plan. |
Question 206 Explanation:
Project statement of work (SOW) provides the asked information.
[1 - 4.1.1 Develop Project Charter: Inputs]
Question 207 |
While closing process a project manager ensures that _____ document has been updated.
A | Customer satisfaction report. |
B | Lessons learned. |
C | Project charted. |
D | Operations plan. |
Question 207 Explanation:
Lessons learned project manager has to ensure that lessons learned have been updated.
Question 208 |
What parts are included in a project management plan?
A | Management plans from initiation, execution, monitoring and controlling, and closing process groups. |
B | Management plans, project charter, business case and project scope. |
C | Project charter, enterprise environmental factors, organizational process assets, business case, and project scope. |
D | All outputs from the planning processes, subsidiary management plans and baselines. |
Question 208 Explanation:
All outputs from the planning processes, subsidiary management plans and baselines is the right answer.
Question 209 |
Which document describes the preferences and techniques to be used for communicating with stakeholders?
A | Coordination plan. |
B | Stakeholders coordination guide. |
C | Stakeholders change management plan. |
D | Project management plan. |
Question 209 Explanation:
Project management plan describes the needs and techniques to be used for communicating with stakeholders.
[1 - Develop Project Management Plan: Outputs]
Question 210 |
Which of the following methods does not belong to comparative approach (benefit measurement) in choosing projects activities?
A | Economic models. |
B | Multi-objective programming. |
C | Peer review. |
D | Murder board. |
Question 210 Explanation:
Multi-objective programming belongs to constrain optimization method rather than comparative approach or benefit measurement for choosing projects.
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 210 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
| 1 | 2 | 3 | 4 | 5 |
| 6 | 7 | 8 | 9 | 10 |
| 11 | 12 | 13 | 14 | 15 |
| 16 | 17 | 18 | 19 | 20 |
| 21 | 22 | 23 | 24 | 25 |
| 26 | 27 | 28 | 29 | 30 |
| 31 | 32 | 33 | 34 | 35 |
| 36 | 37 | 38 | 39 | 40 |
| 41 | 42 | 43 | 44 | 45 |
| 46 | 47 | 48 | 49 | 50 |
| 51 | 52 | 53 | 54 | 55 |
| 56 | 57 | 58 | 59 | 60 |
| 61 | 62 | 63 | 64 | 65 |
| 66 | 67 | 68 | 69 | 70 |
| 71 | 72 | 73 | 74 | 75 |
| 76 | 77 | 78 | 79 | 80 |
| 81 | 82 | 83 | 84 | 85 |
| 86 | 87 | 88 | 89 | 90 |
| 91 | 92 | 93 | 94 | 95 |
| 96 | 97 | 98 | 99 | 100 |
| 101 | 102 | 103 | 104 | 105 |
| 106 | 107 | 108 | 109 | 110 |
| 111 | 112 | 113 | 114 | 115 |
| 116 | 117 | 118 | 119 | 120 |
| 121 | 122 | 123 | 124 | 125 |
| 126 | 127 | 128 | 129 | 130 |
| 131 | 132 | 133 | 134 | 135 |
| 136 | 137 | 138 | 139 | 140 |
| 141 | 142 | 143 | 144 | 145 |
| 146 | 147 | 148 | 149 | 150 |
| 151 | 152 | 153 | 154 | 155 |
| 156 | 157 | 158 | 159 | 160 |
| 161 | 162 | 163 | 164 | 165 |
| 166 | 167 | 168 | 169 | 170 |
| 171 | 172 | 173 | 174 | 175 |
| 176 | 177 | 178 | 179 | 180 |
| 181 | 182 | 183 | 184 | 185 |
| 186 | 187 | 188 | 189 | 190 |
| 191 | 192 | 193 | 194 | 195 |
| 196 | 197 | 198 | 199 | 200 |
| 201 | 202 | 203 | 204 | 205 |
| 206 | 207 | 208 | 209 | 210 |
| End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!