PM - Human Resources Management
Start
Congratulations - you have completed PM - Human Resources Management.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
Which types of Human Resources are used on the projects?
A | Administrative and behavioral. |
B | Managerial and technical. |
C | Business and technical. |
D | Coordinating and executing. |
Question 1 Explanation:
Administrative and behavioral types of Human Resources are used on the projects.
[1 - 9 Human Resources]
Question 2 |
What does project sponsor do prior or during project initiation?
A | Dictate milestones, determine priorities between constrains, and between projects. |
B | Give a project manager authority via project charter. |
C | All choices are right. |
D | Guides the process to get project approval and formalization, and assists project manager. |
Question 2 Explanation:
All choices are right.
Question 3 |
The project management team is responsible for _____ activities such as initiating, planning, executing, monitoring, controlling, and closing the various project phases?
A | Management and leadership. |
B | Executing work package. |
C | Developing the detailed WBS dictionary. |
D | Commenting of the developed code and technical documentation. |
Question 3 Explanation:
The project management team is responsible Management and Leadership activities including initiating, planning, executing, monitoring, controlling, and closing the project phases and whole project. Other choices belong to the team members that assigned to particular roles and activities.
[1 - 9 Human Resources]
Question 4 |
What is the output of Develop Project Resource Management Plan?
A | Activity resource requirements. |
B | All choices are right. |
C | Award and recognition system. |
D | Project resource management plan. |
Question 4 Explanation:
Project Resource Management plan is the only output of the Develop Project Resource Management Plan process. Activity resource requirements is an input, and award and recognition system is a part of the Project Resource Management Plan.
[1 - 9.1.1 Develop Human Resources Management Plan: Input]
Question 5 |
There was a rumor that the project is going to be canceled. Who should address this issue?
A | Project manager. |
B | Functional manager. |
C | Team. |
D | Sponsor. |
Question 5 Explanation:
Sponsor advocates the project, and protects from such big changes.
[1 - 9 Human Resources]
Question 6 |
Which of the following describes life cycle of a project team?
A | Forming, storming, norming, performing, adjourning. |
B | Defining, identifying, acquiring, using, releasing. |
C | Acquiring, using, releasing. |
D | Acquiring, building, developing, releasing. |
Question 6 Explanation:
Forming - putting together a team; storming - solving disagreements within the team; norming - reaching working relations; performing - reaching highest level of working efficiency; adjourning - releasing resources from the project as the work is completed.
[1 - 9.3.2 Develop Project Team: Tools and Techniques]
Question 7 |
What of the following is true about Project Manager's role?
A | Coordinate interactions between the project team members and stakeholders. |
B | All choices are right. |
C | Should be assigned not later than Project Initiation, and may participate in creation of Project Charter. |
D | Is responsible for the project, but not always in charge of resources. Influences the project team and the ground rules, and resolves team issues. |
Question 7 Explanation:
All choices are right.
[1 - 9 Human Resources, and 1 Project Management Framework]
Question 8 |
A new team member decided to use another implementation method. The project team disagrees with priorities among activities. Who is responsible in this situation?
A | Functional manager. |
B | Sponsor. |
C | Project manager. |
D | Team member. |
Question 8 Explanation:
A team member is free to use more advanced method if it is coordinated with the project manager and team, meets project scope requirements, quality, cost and time constrains settled by project manager.
[1 - 9 Human Resources]
Question 9 |
What responsibilities does sponsor carry during project planning?
A | All choices are right. |
B | Helps evaluate trade-offs during crushing, fast tracking, and re-estimating. |
C | Approves the final project management plan. |
D | Provides expert judgement. |
Question 9 Explanation:
All choices are right.
Question 10 |
What of the following is wrong about the role of Project Manager?
A | Identifying dependencies and scheduling work on work packages and activities. |
B | Maintaining monitoring and control throughout the project and determining if any change is required. |
C | Have to be an expert in both technical area and in project management. |
D | Selecting, improving and leading in project processes. |
Question 10 Explanation:
Project manager does not have to be an expert in technical area, but being and expert in project management is the duty.
[1 - 9 Human Resources, and 1 Project Management Framework]
Question 11 |
What does project manager use in Acquire Project Team process?
A | Pr-assignment, and negotiation. |
B | Virtual teams. |
C | All choices are right. |
D | Acquisition. |
Question 11 Explanation:
All choices are right. This question means what tools and techniques are used in this process.
[1 - 9.2.2 Acquire Project Team: Tools and Techniques]
Question 12 |
There is a lack of resources on the project. Who is responsible to provide resources to the project?
A | PMO and functional manager. |
B | Sponsor and project manager. |
C | Sponsor and functional manager. |
D | Project manager. |
Question 12 Explanation:
Sponsor and functional manager are responsible to provide appropriate resources to the project.
[1 - 9 Human Resources]
Question 13 |
A functional manager is trying to assign a team member an additional work not related to the project project. Who should clarify the status if such additional work would be possible?
A | Project manager should provide functional manager with with information about team member's workload to clarify if additional load is possible. |
B | PMO assigns people on the project so have to provide functional manager with with information about team member's workload to clarify if additional load is possible. |
C | Sponsor assigns people on the project so have to provide functional manager with with information about team member's workload to clarify if additional load is possible. |
D | The team member should provide functional manager with information about his/her workload to clarify if additional load is possible. |
Question 13 Explanation:
The team member should provide functional manager with information about his/her workload to clarify if additional load is possible.
[1 - 9 Human Resources]
Question 14 |
What is the role of sponsor play during project executing?
A | Enforcement of quality polices and providing expert judgement. |
B | Protecting project from external influence. |
C | Supporting project manager in resolving conflicts. |
D | All choices are right. |
Question 14 Explanation:
All choices are right.
[1 - 9 Human Resources]
Question 15 |
The project team does not have a clue who is managing the project. Who is responsible for this situation?
A | Sponsor. |
B | Team. |
C | Project manager. |
D | Functional manager. |
Question 15 Explanation:
Sponsor describes project manager's authority in project charter, and assigns a project manager during project initiation.
[1 - 9 Human Resources]
Question 16 |
Which of the following processes is identifying and documenting project roles, responsibilities, and required skills, reporting relationship, and creating a staffing management plan?
A | Develop human resource plan. |
B | Develop project team. |
C | Manage project team. |
D | Acquire project team. |
Question 16 Explanation:
Develop human resource plan is the process to identifying and documenting project roles, responsibilities, and required skills, reporting relationship, and creating a staffing management plan.
[1 - 9 Human Resources]
Question 17 |
Which of the following information will be needed to manage a project team?
A | Project staff assignments and project plan. |
B | Team performance assessments, and performance reports.. |
C | Organizational process assets. |
D | All choices are correct. |
Question 17 Explanation:
All choices are correct.
[1 - 9.4.1 Manage Project Team: Inputs]
Question 18 |
Which of the following processes is improving the competencies, team interaction, and the overall environment to enhance project performance?
A | Develop human resource plan. |
B | Acquire project team. |
C | Develop project team. |
D | Manage project team. |
Question 18 Explanation:
Develop project team is the process to improving the competencies, team interaction, and the overall environment to enhance project performance.
[1 - 9 Human Resources]
Question 19 |
What does not Acquire Project Team process deliver?
A | Resource calendars. |
B | Project staff assignments. |
C | Project management plan updates. |
D | Human resources plan. |
Question 19 Explanation:
Human resources plan is an output if Develop Human Resource Plan - other choices are right.
[1 - 9.2.3 Acquire Project Team: Outputs]
Question 20 |
What does not a Staffing Management Plan include?
A | Staff acquisition plan, resource calendars, and staff release plan. |
B | Training needs, and compliance. |
C | Recognition and rewards, and safety. |
D | Project Resource Management Plan. |
Question 20 Explanation:
Staffing Management Plan is the part of Project Resource Management Plan. It describes when and how human requirements will met. This document is updating constantly due to acquisition of resources and team development actions.
[1 - 9.1.3 Develop Human Resources Plan: Output]
Question 21 |
What is the role the project team play?
A | Provide time and cost estimates. |
B | Comply with quality and communication plans. |
C | All choices are right. |
D | Participate in the risk management process. |
Question 21 Explanation:
A project team is a team whose members usually belong to different groups, functions and are assigned to activities for the same project. A team can be divided into sub-teams according to need. Usually project teams are only used for a defined period of time. They are disbanded after the project is deemed complete. Due to the nature of the specific formation and disbandment, project teams are usually in organizations.
http://en.wikipedia.org/wiki/Project_team
[1 - 9 Human Resources]
Question 22 |
What does project sponsor do?
A | Monitors progress of work packages, and convinces stakeholders accepting project results. |
B | Provides project funding, clarifying scope, monitoring progress, and influencing others in order to benefit the project. |
C | Audits the project to ensure all processes and standards are followed. |
D | All choices are right. |
Question 22 Explanation:
Sponsor provides funding to the project, and assists management team in clarifying project scope, monitoring project progress, and influencing others for the benefits of the project. There is a saying "sponsor is the best friend of the project manager".
[1 - 9 Human Resources]
Question 23 |
Which of the following techniques can be applied in managing project team activites?
A | Penalty - coercive method to reach the objective. |
B | All choices are correct. |
C | Forma/legitimate - using the position/role definition. Reward - the ability to provide advantage. |
D | Expert - demonstrating expert level of confidence in the matter. Referent - comes from others, who value your fame and charisma. |
Question 23 Explanation:
All choices are right.
[1 - 9.4.2 Manage Project Team: Tools and Techniques]
Question 24 |
New requirements were added to the project, which need additional funds and time. Who should be involved in this situation?
A | Functional manager. |
B | Sponsor. |
C | Project manager. |
D | Team. |
Question 24 Explanation:
In this case some additional work was added to the project, which was not supported with neither project budget nor management reserve - Sponsor's involvement is required.
Question 25 |
What does not a project manager need to create human resource management plan?
A | Organizational process assets. |
B | Activity resource requirements. |
C | Project charter. |
D | Enterprise environment factors. |
Question 25 Explanation:
Project charter may contain conceptual information about human resources and would not be needed in Develop Project Resources Plan process. Other choices are only inputs into this process.
Question 26 |
Which types of organizational charts are used in Develop Project Resource Management Plan process?
A | Hierarchical-type charts - graphically presenting the hierarchical relations between departments, as well as some key roles. In other words it called Organizational Breakdown Structure (OBS). |
B | Matrix-based charts - is two dimensional presentation of the resources against work packages or activities. In other words it called responsibility assignment matrix (RAM). |
C | Text-oriented formats - responsibilities that require detailed description can be provided in text-oriented format. |
D | All choices are correct. |
Question 26 Explanation:
The hierarchical charts help to identify the relations between departments and team members. RACI (responsible, accountable, consult, and inform) is one of the examples of RAM charts.
[1 - 9.1.2 Human Resources: Tools and Techniques]
Question 27 |
A project manager does not have required authority to run project. Who assigns project manager's authority?
A | Stakeholder. |
B | PMO. |
C | Functional manager. |
D | Project sponsor. |
Question 27 Explanation:
Project sponsor assigns project manager with appropriate authority via project charter.
[1 - 9 Human Resources]
Question 28 |
The project team disagrees with priorities among activities. Who is responsible for this situation?
A | Sponsor. |
B | Team. |
C | Project manager. |
D | Functional manager. |
Question 28 Explanation:
Project manager should coordinate the network diagram and critical path with the team, and setup priorities among activities on the project.
[1 - 9 Human Resources]
Question 29 |
Which of the following processes belongs to the planning process group?
A | Develop Human Resource Plan. |
B | Acquire Project Team. |
C | Develop Project Team. |
D | Manage Project Team. |
Question 29 Explanation:
Develop Human Resource Plan is a planning process; the rest of Human Resource Management processes belong to Executing process group.
[1 - 9 Human Resources]
Question 30 |
What What of the following duties does the Program Manager carry?
A | Managing the interdependent projects. |
B | Managing multiple project teams. |
C | Managing a group of project managers assigned on different projects. |
D | All choices are correct. |
Question 30 Explanation:
Managing the interdependent projects is the role pf Program Manager.
[1 - 9 Human Resources, and 1 Project Management Framework]
Question 31 |
What are responsibilities of a sponsor during project executing?
A | Lead quality assurance reviews. |
B | All choices are right. |
C | Approve and reject changes and clarify scope details. |
D | Assist project manager in monitoring progress. |
Question 31 Explanation:
All choices are right.
[1 - 9 Human Resources]
Question 32 |
What does sponsor do during project planning?
A | Provide project with time to plan. |
B | All choices are right. |
C | Review WBS, and lists the potential risks. |
D | Determine the project reports to oversee the project. |
Question 32 Explanation:
All choices are right.
Question 33 |
Which of the following activities may positively influence on project team development?
A | Participating in group training, participating tours and trips together. |
B | All choices are right. |
C | Milestone parties, cerebration of birthdays and holidays. |
D | Creating WBS, participating in planning activities. |
Question 33 Explanation:
All choices are right. Gathering a project team outside of day-to-day activities helps to create healthy relations and increase work performance.
[1 - 9.3.2 Develop Project Team: Tools and Techniques]
Question 34 |
What of the following is wrong about project manager's role related human resources?
A | Identify the gap of knowledge and skills in the team members are needed, and assure the training was provided. |
B | Provide resources to the project. |
C | Creating a human resource plan. |
D | Creating job description for team members and other stakeholders on the project. |
Question 34 Explanation:
It is responsibility of resource managers and functional manager to provide resources to the project.
[1 - 9 Human Resources]
Question 35 |
What of the following is wrong about project manager's responsibilities?
A | Coordinating with resource manager for the availability of resources. |
B | Determine the skills and quantity of required resources. |
C | Crating a project charter. |
D | Creating and developing a project team. |
Question 35 Explanation:
Crating a project charter is responsibility of sponsor and stakeholders, unless it was specifically assign to the project manager.
[1 - 9 Human Resources]
Question 36 |
What responsibilities does a project team have?
A | Identify constrain and assumptions; create WBS and WBS Dictionary. |
B | Break the work packages into schedule activities, and assist in identification of dependencies between work activities. |
C | All choices are right |
D | Identify and work with stakeholders; identify and gather requirements. |
Question 36 Explanation:
A project team members may belong to different groups, functions, but are assigned to activities for the same project. A team can be divided into sub-teams according to need. Usually project teams are only used for a defined period of time. They are disbanded after the project is deemed complete. Due to the nature of the specific formation and disbandment, project teams are usually in organizations.
http://en.wikipedia.org/wiki/Project_team
[1 - 9 Human Resources]
Question 37 |
What is the role of functional manager on the project?
A | All choices are right. |
B | Provide subject matter expertise, and provide input to planning of work packages. |
C | Informing project manager about possible impact on or to other projects. |
D | Coordinating with project manager and assigning selected individuals to the project team. |
Question 37 Explanation:
All choices are right.
[1 - 9 Human Resources, and 1 Project Management Framework]
Question 38 |
The project team re-evaluated the work and determined that extra time will be needed to complete the project. Who is a key person in this situation?
A | Functional manager. |
B | Project manager. |
C | Stakeholder. |
D | Sponsor. |
Question 38 Explanation:
Perhaps, the project charter has time constrain; changes in project charter require involvement of the Sponsor.
[1 - 9 Human Resources]
Question 39 |
A functional manager assigned a project team member to a full time work not related to the project project. Who should clarify the status if such additional work would be possible?
A | Manager PMO (prioritize projects and work, etc.). |
B | Project manager needs to deal with the situation (close the gap, etc.). |
C | Sponsor (protect project from losing resources, etc.) |
D | Functional manager (find replacement, etc.). |
Question 39 Explanation:
Project manager needs to deal with this situation (close the gap, etc.).
[1 - 9 Human Resources]
Question 40 |
who does determine stakeholders role and responsibilities on the project?
A | Project manager. |
B | PMO. |
C | Stakeholders. |
D | Project manager and stakeholders. |
Question 40 Explanation:
Project manager and stakeholders determine role of stakeholders on the project.
[1 - 9 Human Resources]
Question 41 |
Which of the following processes is tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance?
A | Develop project team. |
B | Develop human resource plan. |
C | Manage project team. |
D | Acquire project team. |
Question 41 Explanation:
Manage project team is the process to tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance.
[1 - 9 Human Resources]
Question 42 |
Which of the following processes is confirming human resources availability and obtaining the team necessary to complete project assignments?
A | Develop project team. |
B | Develop human resource plan. |
C | Acquire project team. |
D | Manage project team. |
Question 42 Explanation:
Acquire project team is the process to confirming human resources availability and obtaining the team necessary to complete project assignments.
[1 - 9 Human Resources]
Question 43 |
The project team is not sure what exactly should be done next. Who is responsible in this situation?
A | Project management office. |
B | Functional manager. |
C | Sponsor. |
D | Project manager. |
Question 43 Explanation:
Project manager is responsible to assign resources and ensure they know what and when they have to do.
[1 - 9 Human Resources]
Question 44 |
What does project sponsor do prior or during project initiation?
A | Provides information about initial scope of the project. |
B | All choices are right. |
C | Advocates the project and ensures its buy-in throughout of the performing organization. |
D | Generates project statement of work if it is not done by the customer. |
Question 44 Explanation:
All choices are right.
Question 45 |
Which of the following techniques can be used in developing project team?
A | Leadership, mentoring, social events, and empathy; create and give recognition and rewards. |
B | Encouraging team work, and intercommunicating honestly and in timely manner. |
C | All choices are right. |
D | Establish ground rules for appropriate team members behavior, and gain training when needed. |
Question 45 Explanation:
All choices are right.
[1 - 9.3.2 Develop Project Team: Tools and Techniques]
Question 46 |
In which of the following processes the stakeholders may be involved?
A | Development of project plan, and change management processes. |
B | Verifying scope, identifying constrains, requirements and risks; take risk response ownership. |
C | All choices are right. |
D | Creation of project charter, and project scope statement. |
Question 46 Explanation:
All choices are right.
[1 - 9 Human Resources, and 1 Project Management Framework]
Question 47 |
What effect does early involvement of team in planning have on project?
A | Adds expertize, and increases commitments. |
B | Increases waste of funds and time. |
C | Helps identify skills of the assigned resources. |
D | All choices are right. |
Question 47 Explanation:
Early involvement of the team in project planning increases their expertize, and commitments to the project.
[1 - 9 Human Resources]
Question 48 |
What does the Develop Project Team process deliver?
A | Resource calendars. |
B | Project staff assignments. |
C | Team performance assessments, and enterprise factors update. |
D | Human resources plan. |
Question 48 Explanation:
Team performance assessments, and enterprise factors update are outputs of Develop Project Team process.
[1 - 9.3.3 Develop Project Team: Outputs]
Question 49 |
Which of the following tools and techniques to be used in managing project team?
A | Issue log, interpersonal skills. |
B | Observation and conversation. |
C | Project performance appraisals, and conflict management. |
D | All choices are right. |
Question 49 Explanation:
All choices are right.
[1 - 9.4.2 Manage Project Team: Tools and Techniques]
Question 50 |
Who is the main decision maker in case of major change in project delivery?
A | PMO. |
B | Sponsor. |
C | Project Team. |
D | Project manager. |
Question 50 Explanation:
Sponsor is the main decision maker in major changes on the project.
[1 - 9 Human Resources]
Question 51 |
The sponsor sets an unrealistic end-date of the project. Who is responsible in this situation?
A | Project manager. |
B | Functional manager. |
C | Team. |
D | Sponsor. |
Question 51 Explanation:
Only the sponsor can make such significant change in the project charter, where the target date is provided.
[1 - 9 Human Resources]
Question 52 |
The project requires more funds than assumed initially. Who is in charge for this situation?
A | Project manager. |
B | Team. |
C | Sponsor. |
D | Functional manager. |
Question 52 Explanation:
It is Sponsor's role to provide project with required funding.
[1 - 9 Human Resources]
Question 53 |
What is the role of functional manager on the project?
A | Recommending changes to the project, including preventive and corrective actions. |
B | All choices are right. |
C | Approving project management plan and final schedule. |
D | Managing activities related to the related functional area. Influencing the team member performance and utilization. |
Question 53 Explanation:
All choices are right.
[1 - 9 Human Resources, and 1 Project Management Framework]
Question 54 |
What is the role the project sponsor play during project closing?
A | Accepting project deliverables and supporting historical records. |
B | Testing the project results against project charter. |
C | Generate final performance report. |
D | Provides input to lessons learned and updates project documentation. |
Question 54 Explanation:
During closing a project or phase, sponsor is accepting project deliverables and supporting historical records. Sponsor can provide input to Lessons Learned, but this shout be done by stakeholders. The actual testing is usually part of executing phase, but belongs to monitoring and controlling process group, and done against the requirements, not project charter. Final performance report should be generated by the project manager, not sponsor.
[1 - 9 Human Resources]
Question 55 |
What does not the Acquire Project Team process use?
A | Organizational process assets. |
B | Risk management plan. |
C | Project management plan. |
D | Enterprise environmental factors. |
Question 55 Explanation:
Risk management plan is nor an input to Acquire Project Team process.
[1 - 9.2.1 Acquire Project Team]
Question 56 |
Two members of a project team has personal disagreements. Who is responsible to solve their conflict?
A | Project Manager. |
B | PMO. |
C | Disagreed people. |
D | Project Sponsor. |
Question 56 Explanation:
Disagreed people should find a solution for their personal disagreement without involving of others.
[1 - 9 Human Resources]
Question 57 |
Some of the project team members can be assigned to selected project management responsibilities; in that case they are considered part of the _____.
A | Change control board. |
B | Steering committee. |
C | Executive team members. |
D | Project management team. |
Question 57 Explanation:
Some of the project team members can be assigned to selected project management responsibilities; is that case they are considered part of the Project Management Team.
[1 - 9 Human Resources]
Question 58 |
Which of the following are outputs of Manage Project Team process?
A | Project management plan updates. |
B | Enterprise environmental factors update, and organizational process assets updates. |
C | All choices are right. |
D | Change requests. |
Question 58 Explanation:
All choices are right. Manage Project Team process belong to executing process group and addresses the team day-to-day activities.
[1 - 9.4.3 Manage Project Team: Outputs]
Question 59 |
What does a project manager use to Develop Project Resource Management Plan?
A | Networking. |
B | Organizational theory. |
C | Organization charts and position descriptions. |
D | All choices are right. |
Question 59 Explanation:
All choices are right.
[1 - 9.2 Human Resources: Tools and Techniques]
Question 60 |
Project management team members are confused regarding priorities among projects. Who is responsible for this situation?
A | Functional managers or Project managers. |
B | Sponsor or program manager. |
C | Project managers or project teams. |
D | Company's management or PMO. |
Question 60 Explanation:
Sponsor or program manager, depends on organizational structure is responsible to determine priorities between projects in the company's portfolio or in program.
[1 - 9 Human Resources]
Question 61 |
Which of the following enterprise environmental factors are not used as input to Develop Project Resource Management Plan process?
A | Configuration management system. |
B | Personnel administration policies. |
C | Organizational culture and structure, and existing resources. |
D | Marketplace conditions. |
Question 61 Explanation:
The enterprise environmental factors related to human resources are related to the cultural environment and structural interactions between the resources, organizations will be involved in the project, and availability of training. It also important to recognize if there any hidden agendas or anyone is negatively influences the project. Personal administration policies will help to interact with resources managers and functional managers to influence the project resources performance. The information about marketplace condition may help to identify possible lose. For example, there is a risk of losing a high-demand skilled personnel for more competitive compensation on the market.
[1 - 9.1.1 Develop Human Resources Management Plan]
Question 62 |
Which of the following is not included in Project Resource Management Plan?
A | Project organization chart. |
B | Project charter. |
C | Staffing management plan. |
D | Roles and responsibilities. |
Question 62 Explanation:
Roles and Responsibilities chapter - provides the name of the roles, and describes their authority, responsibilities, boundaries, and required competency of skills. Project Organization Chart - - helps to identify the relations between departments and team members, and some key roles. Staffing Management Plan - describes when and how human requirements will met.
[1 - 9.1.3 Develop Human Resources Plan: Output]
Question 63 |
Which tool and techniques can be used to developing project team?
A | Recognition and rewards. |
B | Training, team building activities. |
C | Interpersonal skills, and co-location. |
D | All choices are right. |
Question 63 Explanation:
All choices are right.
[1 - 9.1.3 Develop Project Team: Outputs]
Question 64 |
The project is out of schedule. Who is responsible for this situation?
A | Project manager. |
B | Team. |
C | Sponsor. |
D | Functional manager. |
Question 64 Explanation:
The project manager should control project schedule and responsible for schedule divination.
[1 - 9 Human Resources]
Question 65 |
Which information is needed for developing project team?
A | Project staff assignments, team performance assessment, and resources calendars. |
B | Project staff assignments, project management plan, and resources calendars. |
C | Enterprise environmental factors, project management plan, and resources calendars. |
D | Project management plan, project resource plan, and resources calendars. |
Question 65 Explanation:
Project staff assignments, project management plan, and resources calendars.
[1 - 9.3.1 Develop Project Team: Inputs]
Question 66 |
What is the role of the project team?
A | All choices are right. |
B | Attending project team meeting, and conducting project improvement activities. |
C | Apply ground rules, and execute project management plan to complete work determined in project scope statement. |
D | Recommend changes to the project, including corrective and preventing actions. |
Question 66 Explanation:
A project team is a team whose members usually belong to different groups, functions and are assigned to activities for the same project. A team can be divided into sub-teams according to need. Usually project teams are only used for a defined period of time. They are disbanded after the project is deemed complete. Due to the nature of the specific formation and disbandment, project teams are usually in organizations.
http://en.wikipedia.org/wiki/Project_team
[1 - 9 Human Resources]
Question 67 |
Which of the following Ground Rules would be useful on the project?
A | How keep meeting focusing on the agenda and within boundaries of talking. |
B | Honesty in communications, and timing for status or notification about issues to deliver the work. How the changes in calendar to be coordinated and approved. |
C | All choices are right. |
D | What is an acceptable way to interrupt one another during meetings. |
Question 67 Explanation:
All choices are right.
[1 - 9.4.2 Manage Project Team: Tools and Techniques]
Question 68 |
What does a project manager responsible for human resources on the project?
A | Provide report of team members' performance for entering to their official employment records. |
B | All choices are right. |
C | Create recognition and award system and send out letters of commendation to team members and their managers. |
D | Address the team members needs. |
Question 68 Explanation:
All choices are right.
[1 - 9 Human Resources]
Question 69 |
Which organizational process assets will not be used in Develop Project Resource Management Plan process?
A | Templates for organizational chart and position descriptions. |
B | Historical information on organizational structures that have worked in previous projects. |
C | Configuration management system. |
D | Organizational standards processes an policies, and standardized role descriptions. |
Question 69 Explanation:
Configuration management system is used to keep the right version of the documents available. Other choices will be used in the process as input.
[1 - 9.1 Develop Human Resources Management Plan]
Question 70 |
A team member would not perform as planned. Who of the following people should be involved in this situation?
A | Project manager. |
B | Sponsor. |
C | Team. |
D | Functional manager. |
Question 70 Explanation:
Functional manager owns the resources, provides control their control, and is responsible for their performance.
[1 - 9 Human Resources]
Question 71 |
What is the role of Human Resource Management in projects?
A | Organize |
B | Manage. |
C | All choices are right. |
D | Lead the project team. |
Question 71 Explanation:
Human Resource Management is a project management area of knowledge that helps to organize, manage, and lead project team.
[1 - 9 Human Resources]
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 71 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
1 | 2 | 3 | 4 | 5 |
6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 |
26 | 27 | 28 | 29 | 30 |
31 | 32 | 33 | 34 | 35 |
36 | 37 | 38 | 39 | 40 |
41 | 42 | 43 | 44 | 45 |
46 | 47 | 48 | 49 | 50 |
51 | 52 | 53 | 54 | 55 |
56 | 57 | 58 | 59 | 60 |
61 | 62 | 63 | 64 | 65 |
66 | 67 | 68 | 69 | 70 |
71 | End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!